Avangrid’s Vineyard Wind 1 Begins Wind Turbine Installation Campaign
- Avangrid's Vineyard Wind 1 project will power more than 400,000 homes and businesses in Massachusetts
- The GE Haliade-X turbine has a nameplate capacity of 13 Megawatts and can power more than 6,000 homes and businesses
- The project will consist of 62 wind turbines generating 806 Megawatts
- None.
GE Haliade-X Is First of 62 Wind Turbines that Will Power More than 400,000 Homes and Businesses in
Components of the first GE Haliade-X turbine transported through the hurricane barrier in
“Over the past year, we have achieved significant milestones in the development of Avangrid’s Vineyard Wind 1, but the installation of the project’s first turbine stands as a singular landmark for offshore wind, clean energy, and climate action in the United States,” said Avangrid CEO Pedro Azagra. “We are proud that local union labor will pioneer the installation of the massive GE turbines that will harness the winds off the shores of
- The GE Haliade-X is the largest turbine in the western world, with a nameplate capacity of 13 Megawatts including a power boost mode of 13.6 Megawatts. Each machine is capable of providing power to more than 6,000 homes and businesses.
-
One rotation of a single turbine, which is twice as tall as the Statue of Liberty from the surface of the water, can power one
Massachusetts household for an entire day. -
The blades span 351 ft (or 107 meters) each, equivalent to the length of the field at Gillette Stadium in Foxborough,
Massachusetts . - The components transported to the project area weigh a total of 1,700 metric tons combined – equivalent to more than eight Boeing 747 airplanes.
- The diameter of the rotor is 722 ft (or 220 meters) which is equivalent to the height of the Golden Gate Bridge above the water.
- The surface of the blade sweep is equivalent to seven American football fields.
The project will consist of 62 wind turbines to generate 806 Megawatts, enough to power more than 400,000 homes and businesses in
The project will consist of 62 wind turbines to generate 806 Megawatts, enough to power more than 400,000 homes and businesses in
The massive components were transported by two 400 foot barges, the only two in existence capable of transporting in an upright position GE’s massive Haliade-X turbine components. Once installed, the Haliade-X will rise more than 860 ft (or 260 meters) which is equivalent to 3X the height of the Flat Iron Building.
GE loaded the
As a part of the Project Labor Agreement for the project, local union labor will be used both on the vessels and onshore at the New Bedford Marine Commerce Terminal. The project estimates that approximately 400 union members have worked on the project to date.
An 806-megawatt project located 30 miles off the coast of
About Avangrid: Avangrid, Inc. (NYSE: AGR) aspires to be the leading sustainable energy company in
View source version on businesswire.com: https://www.businesswire.com/news/home/20230912575267/en/
Craig Gilvarg
craig.gilvarg@avangrid.com
(857) 998-1130
Source: AVANGRID, Inc.