STOCK TITAN

Panuco plan: Vizsla Silver (NYSE: VZLA) sets EPCM and mine design deals

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Vizsla Silver Corp. has awarded an Engineering, Procurement and Construction Management (EPCM) contract to M3 Engineering & Technology Corp. and a mine design contract to Mining Plus to advance its 100%-owned Panuco silver-gold project in Sinaloa, Mexico.

The EPCM scope covers the process plant and surface infrastructure, valued at about US$170 million. The mine design work includes roughly US$50 million in development capital and US$40 million in ore development over the next two years of pre-production. The company reiterates that no production decision has been made.

The November 2025 Feasibility Study for Panuco outlines average annual production of 17.4 Moz AgEq over an initial 9.4-year mine life, after-tax NPV(5%) of US$1.8 billion, 111% IRR and a 7‑month payback, based on US$35.50/oz silver and US$3,100/oz gold price assumptions.

Positive

  • None.

Negative

  • None.

Insights

Vizsla locks in key engineering partners for Panuco while reiterating strong feasibility economics but no production decision yet.

Vizsla Silver has moved Panuco further along the development path by selecting M3 Engineering for a US$170 million EPCM scope and Mining Plus for mine design tied to US$50 million of development capital and US$40 million of ore development over two years. These contracts provide clearer responsibility for plant, infrastructure and underground planning.

The Feasibility Study numbers remain a key reference point: average annual production of 17.4 Moz AgEq over 9.4 years, after-tax NPV(5%) of US$1.8B, 111% IRR and a roughly 7‑month payback at stated metal prices. While attractive on paper, outcomes still depend on securing financing, receiving permits such as the MIA, and delivering construction on time and on budget.

Management explicitly states that no production decision has been made and that a go-ahead would follow completion of detailed engineering, financing arrangements and all required approvals. Subsequent company disclosures may clarify contract finalization, permitting progress and funding plans for construction.

EPCM scope value US$170 million Process plant and surface infrastructure at Panuco
Mine development capital US$50 million Development capital in mine design scope over pre-production
Ore development spending US$40 million Ore development over next two years of pre-production
Average annual production 17.4 Moz AgEq Feasibility Study, initial 9.4-year mine life
Mine life 9.4 years Initial mine life in Panuco Feasibility Study
After-tax NPV (5%) US$1.8 billion Panuco Feasibility Study economics
Internal rate of return 111% After-tax IRR from Panuco Feasibility Study
Payback period 7 months Panuco Feasibility Study payback at stated prices
Engineering, Procurement and Construction Management technical
"it has awarded the Engineering, Procurement and Construction Management (the "EPCM") contract"
A project delivery approach where a firm handles detailed design, sources major equipment and materials, and oversees construction on behalf of the project owner, acting like the owner’s project manager. It matters to investors because the firm’s performance determines whether a project is built on time, on budget and to specification—similar to hiring a general contractor for a house, where delays or cost overruns directly affect returns, cash flow and project risk.
Feasibility Study financial
"Since finalizing the Panuco Feasibility Study (published in November 2025)"
A feasibility study is an assessment that evaluates whether a proposed project or idea is practical and likely to succeed before investing significant time and resources. It considers factors like costs, potential benefits, and challenges, helping stakeholders decide if moving forward makes sense. Think of it as a detailed plan that gauges if a new venture is worth pursuing.
Preliminary Economic Assessment financial
"following the Preliminary Economic Assessment (PEA), published in July 2024"
A preliminary economic assessment is an initial analysis that estimates the potential profitability and feasibility of a project or resource, such as a new mineral deposit or development venture. It provides a rough idea of costs, benefits, and risks, helping investors decide whether to pursue more detailed studies. This early evaluation is important because it offers a snapshot of whether the project is worth further investment and development.
net present value financial
"an after-tax NPV (5%) of US$1.8B"
Net present value is a way to measure the value of a future amount of money today. It considers how money available in the future is worth less than money now because of potential earning opportunities or inflation. Investors use it to decide whether an investment is worthwhile, aiming for projects with positive net present value, meaning they are expected to generate more value than they cost.
internal rate of return financial
"111% IRR and a 7-month payback"
A percentage that represents the annualized yield an investment would earn, taking into account the timing and amount of all cash inflows and outflows; mathematically it is the rate that makes the discounted sum of future cash flows equal the initial cost. Investors use it to compare different projects or deals the way they compare interest rates — a higher internal rate of return suggests a stronger potential payoff, but it does not by itself show risk, scale, or timing nuances.
MIA permit regulatory
"Begin mining operations upon receipt of the MIA permit"

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

FORM 6-K

 

 

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

OF THE SECURITIES EXCHANGE ACT OF 1934

For the month of April 2026

Commission File Number: 001-41225

 

 

VIZSLA SILVER CORP.

(Registrant)

 

 

 

Suite 1723, 595 Burrard Street

Vancouver, BC V7X 1J1 Canada

(Address of Principal Executive Offices) 

 

Indicate by check mark whether the Registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F              Form 40-F  

 

 

 

 

 

SIGNATURES


Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

             
        VIZSLA SILVER CORP.
        (Registrant)
       
Date: April 23, 2026       By  

/s/ Michael Konnert

            Michael Konnert
            Chief Executive Officer

 

 

 

 

 

EXHIBIT INDEX

     

Exhibit

  Description of Exhibit
   
99.1   News Release dated April 23, 2026 - VIZSLA SILVER AWARDS EPCM AND MINE DESIGN CONTRACTS FOR THE DEVELOPMENT OF THE PANUCO SILVER-GOLD PROJECT

 

EXHIBIT 99.1 

  

 

 

VIZSLA SILVER AWARDS EPCM AND MINE DESIGN CONTRACTS FOR THE DEVELOPMENT OF THE PANUCO SILVER-GOLD PROJECT

NYSE: VZLA     TSX: VZLA

VANCOUVER, BC, April 23, 2026 /CNW/ - Vizsla Silver Corp. (TSX: VZLA) (NYSE: VZLA) (Frankfurt: 0G3) ("Vizsla Silver" or the "Company") today announced that it has awarded the Engineering, Procurement and Construction Management (the "EPCM") contract to M3 Engineering & Technology Corp. ("M3" or "M3 Engineering") and has entered into a Mine Design contract with Mining Plus. Both contractors will support the advancement of its flagship Panuco silver-gold project.

"The appointment of key engineering and mine design partners represents an important step in advancing our Panuco Project," said Michael Konnert, President and CEO. "We are pleased to partner with M3 and Mining Plus as we move towards mobilization."

With its partners, the Company will work off-site to advance detailed design, construction planning and equipment procurement, while continuing to advance go-forward, long-term security plans for the Panuco Project. Vizsla Silver advises that key development activities continue to progress in line with previously disclosed timelines.

EPCM Contract Selection

M3 Engineering is an experienced engineering firm specializing in mineral processing and infrastructure projects. The firm has participated in the design and construction of several mining projects in Mexico, including Mercedes, Los Gatos, Peñasquito, Camino Rojo and Terronera.

Since finalizing the Panuco Feasibility Study (published in November 2025), Vizsla Silver has worked with M3 Engineering to support the planning and development of the Project. The EPCM scope of work covers the process plant and surface infrastructure, valued at approximately US$170 million. The Company and M3 Engineering are currently finalizing the terms and conditions of the definitive EPCM agreement.

"M3 Engineering & Technology Corp. is proud to contribute our technical expertise to support Vizsla Silver in advancing the development of the Panuco Silver-Gold Project," said Alberto Bennett, President and CEO of M3 Engineering. "We look forward to continuing working closely with Vizsla Silver's team to deliver another successful project in Mexico, on time and on budget."

Mining Design Contract

Mining Plus, part of The Byrnecut Group, is a global mining services firm. Vizsla Silver and Mining Plus have worked together since finalizing the Panuco Preliminary Economic Assessment (PEA), published in July 2024.

Mining Plus has supported mine design, planning, scheduling and geotechnical work, including contributions to the development of the Company's Morgan Test Mine at Panuco. The mining design scope of work covers approximately US$50 million in development capital, and approximately US$40 million in ore development over the next two years of pre-production.

Key mining schedule items include:

  • Award mining contract in Q2 2026
  • Begin mining operations upon receipt of the MIA permit
  • Implement an infill drilling program over an initial two-year period to support ramp-up and stockpiling ahead of process plant commissioning

"Mining Plus is pleased to continue its partnership with Vizsla Silver as the Panuco Project advances toward production," said Vahid Haydari, Chief Executive Officer of Mining Plus. "Since our initial involvement following the Preliminary Economic Assessment, we have worked closely with the team on mine design and planning. This next phase focuses on detailed planning and disciplined execution as this high grade, technically compelling project advances toward commercial production."

About Vizsla Silver and the Panuco Project

Vizsla Silver is a Canadian mineral exploration and development company headquartered in Vancouver, BC, focused on advancing its flagship, 100%-owned Panuco silver-gold project located in Sinaloa, Mexico. The Company recently completed a Feasibility Study for Panuco in November 2025 which highlights 17.4 Moz AgEq of annual production over an initial 9.4-year mine life, an after-tax NPV (5%) of US$1.8B, 111% IRR and a 7-month payback at US$35.50/oz Ag and US$3,100/oz Au. Vizsla Silver aims to position itself as a leading silver company by implementing a dual track development approach at Panuco, advancing mine development while continuing district-scale exploration through low-cost means. 

Website: www.vizslasilvercorp.ca  

SPECIAL NOTE REGARDING FORWARD LOOKING STATEMENTS

Forward-looking statements in this release include, but are not limited to, statements regarding: the Company's objectives and milestones; the strategic vision for the Company following the proposed development of the Panuco Project and expectations regarding future financial or operating performance following such development; the timing and receipt of environmental and other regulatory permits, including but not limited to the MIA Permit; the timing and entry into the EPCM agreement as proposed or at all; the timing and execution of construction activities as proposed or at all, including the commencement of construction, advancement of detailed engineering, and selection of contractors and development partners; the Company's ability to advance the Panuco Project toward production; the results, timing and scope of planned drilling programs, including underground infill and expansion drilling, district-wide surface drilling, and follow-up drilling at Animas, Santa Fé, La Garra, Peñoles and other targets and their anticipated impact on project economics and mine design; the conversion of inferred mineral resources to indicated mineral resources, including targeted conversion of inferred mineralization within the Copala zone; the size, grade, continuity and potential expansion of mineral resources, including the potential to add mine life beyond the current Feasibility Study's mine plan; the completion and outcomes of bulk sampling, metallurgical testing, geotechnical work and optimization studies, and their anticipated impact on project economics and mine design; the economic results of the Panuco Project, including forecast production rates, mine life, capital costs, operating costs, free cash flow, net present value, internal rate of return, and payback period, as derived from the Feasibility Study; the assumptions underlying the Feasibility Study, including commodity prices, metallurgical recoveries, operating and capital cost estimates, permitting timelines, and development schedules; the Company's ability to fund construction and development, including expectations regarding the sufficiency of existing cash balances and access to financing; the anticipated benefits of property acquisitions and exploration programs, including the identification of new mineralized zones and discovery of additional deposits; and the Company's long-term growth strategy, including its ability to enhance shareholder value through continued exploration success, project development and operational execution.

Forward-looking statements are based on a number of assumptions believed to be reasonable by the Company as of the date of this release, including, without limitation: the accuracy of the Feasibility Study parameters; the availability of financing on acceptable terms; that required permits and approvals will be obtained in the expected timeframe; continued community and government support; stability in market, political and economic conditions; reasonable accuracy of operating and capital cost estimates; and continued favourable metal prices and exchange rates.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially. Such risks include, but are not limited to: exploration, development and operating risks; permitting, environmental and regulatory risks; community relations and social licence risks; commodity price and currency fluctuations; inflation and cost escalation; financing and liquidity risks; reliance on contractors and suppliers; title and surface rights risks; changes in project development and construction parameters; inaccuracies in technical or economic modelling; the risk that the Feasibility Study assumptions prove inaccurate; and other risks described in the Company's continuous disclosure filings available under its profile on SEDAR+ at www.sedarplus.ca.

There can be no assurance that the Panuco Project will be placed into production as proposed in this news release or at all, that the EPCM definitive agreement will be entered into and on what terms or that the results of the Feasibility Study will be realized. The purpose of the forward-looking statements is to provide information about management's current expectations and plans and may not be appropriate for other purposes. Readers are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date of this release. Except as required by applicable law, the Company undertakes no obligation to update or revise any forward-looking statements contained herein.

No Production Decision: The Company has not made a production decision for the Panuco Project. A decision to proceed with construction will only be made following the completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals.

View original content to download multimedia:https://www.prnewswire.com/news-releases/vizsla-silver-awards-epcm-and-mine-design-contracts-for-the-development-of-the-panuco-silver-gold-project-302750621.html

SOURCE Vizsla Silver Corp.

 

View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2026/23/c3064.html

%CIK: 0001796073

For further information: Contact Information: For more information and to sign-up to the mailing list, please contact: Michael Konnert, President and Chief Executive Officer, Tel: (604) 364-2215, Email: info@vizslasilver.ca

CO: Vizsla Silver Corp.

CNW 06:00e 23-APR-26

FAQ

What did Vizsla Silver (VZLA) announce about the Panuco project?

Vizsla Silver announced it awarded an EPCM contract to M3 Engineering and a mine design contract to Mining Plus for its Panuco silver-gold project, advancing detailed plant, infrastructure and mine planning while continuing off-site design and equipment procurement work.

How large is the EPCM and mine design scope at Vizsla Silver’s Panuco project?

The EPCM scope with M3 Engineering covers the process plant and surface infrastructure valued at about US$170 million. Mining Plus’ mine design work covers approximately US$50 million in development capital and about US$40 million in ore development over two pre-production years.

What are the key feasibility economics for Vizsla Silver’s Panuco project?

The Panuco Feasibility Study outlines average annual production of 17.4 million silver-equivalent ounces over 9.4 years, with an after-tax NPV (5%) of US$1.8 billion, 111% internal rate of return and a 7‑month payback, using specified silver and gold price assumptions.

Has Vizsla Silver decided to proceed to production at Panuco?

Vizsla Silver has not made a production decision for Panuco. Management states construction will only proceed after completing detailed engineering, arranging financing, and obtaining all required permits and approvals, including environmental authorizations such as the MIA permit.

What pre-production mining activities are planned at Vizsla Silver’s Panuco project?

Key pre-production activities include awarding a mining contract in Q2 2026, commencing mining operations upon receipt of the MIA permit, and running a two-year infill drilling program to support ramp-up and stockpiling before process plant commissioning at Panuco.

What price assumptions underpin Vizsla Silver’s Panuco Feasibility Study?

The Feasibility Study’s economic metrics are based on assumed prices of US$35.50 per ounce of silver and US$3,100 per ounce of gold, alongside assumptions on recoveries, costs, permitting timelines and development schedules for the Panuco silver-gold project.

Filing Exhibits & Attachments

1 document