STOCK TITAN

TeraWulf Announces September 2024 Production and Operations Update

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

TeraWulf Inc. (Nasdaq: WULF) released its September 2024 production and operations update, highlighting significant advancements in HPC/AI digital infrastructure. Key points include:

- Mined 176 bitcoin in September, averaging 5.9 bitcoin per day
- Operational self-mining capacity at 10.0 EH/s, a 100% year-over-year increase
- Average power cost per bitcoin mined: $35,109 ($0.042/kWh)
- Closed sale of 25% equity interest in Nautilus facility for $92 million
- Reinvesting capital into 20 MW CB-1 facility at Lake Mariner
- Completed 2 MW 'WULF Den' proof-of-concept for high-density GPU workloads
- CB-1 construction on track for Q1 2025 completion
- Secured long-lead items for 50 MW CB-2 AI/HPC facility

TeraWulf continues to advance its HPC/AI projects, including a 2.5 MW proof-of-concept and the 20 MW CB-1 facility designed to support 16 MW of critical IT load with Tier 3 data center features.

TeraWulf Inc. (Nasdaq: WULF) ha pubblicato l'aggiornamento sulla produzione e operazioni di settembre 2024, evidenziando notevoli progressi nell'infrastruttura digitale HPC/AI. I punti chiave includono:

- Estratti 176 bitcoin a settembre, con una media di 5.9 bitcoin al giorno
- Capacità operativa di auto-mining a 10.0 EH/s, un aumento del 100% rispetto all'anno precedente
- Costo medio dell'energia per bitcoin estratto: $35,109 ($0.042/kWh)
- Vendita conclusa del 25% di partecipazione azionaria nella struttura Nautilus per $92 milioni
- Reinvestimento di capitale nella struttura CB-1 da 20 MW a Lake Mariner
- Completato il 'WULF Den' proof-of-concept da 2 MW per carichi di lavoro GPU ad alta densità
- Costruzione di CB-1 in linea per il completamento nel Q1 2025
- Aggiudicati articoli a lungo termine per la struttura AI/HPC CB-2 da 50 MW

TeraWulf continua a far progredire i propri progetti HPC/AI, compreso un proof-of-concept da 2.5 MW e la struttura CB-1 da 20 MW progettata per supportare 16 MW di carico IT critico con caratteristiche di data center di livello 3.

TeraWulf Inc. (Nasdaq: WULF) lanzó su actualización de producción y operaciones de septiembre de 2024, destacando avances significativos en la infraestructura digital HPC/AI. Los puntos clave incluyen:

- Se minaron 176 bitcoin en septiembre, con un promedio de 5.9 bitcoin por día
- Capacidad operativa de auto-minería de 10.0 EH/s, un aumento del 100% año tras año
- Costo promedio de energía por bitcoin minado: $35,109 ($0.042/kWh)
- Venta cerrada del 25% de participación en la instalación de Nautilus por $92 millones
- Re-inversión de capital en la instalación CB-1 de 20 MW en Lake Mariner
- Completado el 'WULF Den' proof-of-concept de 2 MW para cargas de trabajo GPU de alta densidad
- La construcción de CB-1 está programada para completarse en el Q1 de 2025
- Se aseguraron artículos de plazos largos para la instalación AI/HPC CB-2 de 50 MW

TeraWulf continúa avanzando en sus proyectos HPC/AI, incluyendo un proof-of-concept de 2.5 MW y la instalación CB-1 de 20 MW diseñada para soportar 16 MW de carga crítica de TI con características de centro de datos de nivel 3.

TeraWulf Inc. (Nasdaq: WULF)가 2024년 9월의 생산 및 운영 업데이트를 발표하며, HPC/AI 디지털 인프라에서의 중요한 발전을 강조했습니다. 주요 내용은 다음과 같습니다:

- 9월에 176 비트코인을 채굴했으며, 하루 평균 5.9 비트코인 채굴
- 자가 채굴 능력 10.0 EH/s, 전년 대비 100% 증가
- 채굴된 비트코인당 평균 전력 비용: $35,109 ($0.042/kWh)
- Nautilus 시설의 25% 지분을 $92 백만에 매각 완료
- Lake Mariner의 20 MW CB-1 시설에 자본 재투자
- 고밀도 GPU 작업 부하를 위한 2 MW 'WULF Den' 개념 증명 완료
- CB-1 건설은 2025년 1분기 완료 예정
- 50 MW AI/HPC 시설을 위한 장기 물품 확보

TeraWulf는 2.5 MW 개념 증명 및 16 MW의 중요한 IT 부하를 지원하도록 설계된 20 MW CB-1 시설을 포함한 HPC/AI 프로젝트를 계속 발전시켜 나가고 있습니다.

TeraWulf Inc. (Nasdaq: WULF) a publié sa mise à jour de production et d'opérations pour septembre 2024, mettant en avant des avancées significatives dans l'infrastructure numérique HPC/AI. Les points clés comprennent :

- 176 bitcoin extraits en septembre, avec une moyenne de 5,9 bitcoin par jour
- Capacité d'auto-minage opérationnelle de 10,0 EH/s, une augmentation de 100 % d'une année sur l'autre
- Coût moyen de l'électricité par bitcoin extrait : 35 109 $ (0,042 $/kWh)
- Vente conclue de 25 % des intérêts propres dans l'installation de Nautilus pour 92 millions $
- Réinvestissement de capital dans l'installation CB-1 de 20 MW au lac Mariner
- Achèvement d'un concept de preuve de 2 MW 'WULF Den' pour des charges de travail GPU haute densité
- Construction de la CB-1 sur la bonne voie pour une finition au T1 2025
- Articles à long terme sécurisés pour l'installation AI/HPC CB-2 de 50 MW

TeraWulf continue de faire progresser ses projets HPC/AI, y compris une preuve de concept de 2,5 MW et l'installation CB-1 de 20 MW, conçue pour soutenir 16 MW de charge informatique critique avec des caractéristiques de centre de données de niveau 3.

TeraWulf Inc. (Nasdaq: WULF) hat sein Produktions- und Betriebsupdate für September 2024 veröffentlicht, das bedeutende Fortschritte in der HPC/AI-Digitalinfrastruktur hervorhebt. Die wichtigsten Punkte umfassen:

- Im September wurden 176 Bitcoin abgebaut, durchschnittlich 5,9 Bitcoin pro Tag
- Operative Selbst-Abbaukapazität von 10,0 EH/s, ein Anstieg von 100% im Vergleich zum Vorjahr
- Durchschnittliche Stromkosten pro abgebautem Bitcoin: 35.109 $ (0,042 $/kWh)
- Verkauf von 25% der Beteiligung an der Nautilus-Anlage für 92 Millionen $ abgeschlossen
- Reinvestition von Kapital in die 20 MW CB-1-Anlage am Lake Mariner
- Abschluss eines 2 MW 'WULF Den'-Machbarkeitsnachweises für hochdichte GPU-Arbeitslasten
- Bau von CB-1 verläuft nach Plan und soll im 1. Quartal 2025 fertiggestellt werden
- Langfristige Beschaffung für die 50 MW AI/HPC-Anlage CB-2 sichergestellt

TeraWulf setzt weiterhin auf die Weiterentwicklung seiner HPC/AI-Projekte, darunter ein 2,5 MW Machbarkeitsnachweis und die 20 MW CB-1-Anlage, die für die Unterstützung einer kritischen IT-Belastung von 16 MW mit Tier-3-Rechenzentrumsmerkmalen konzipiert wurde.

Positive
  • Mined 176 bitcoin in September, averaging 5.9 bitcoin per day
  • 100% year-over-year increase in operational self-mining capacity to 10.0 EH/s
  • Closed sale of 25% equity interest in Nautilus facility for $92 million
  • Completed 2 MW 'WULF Den' proof-of-concept for high-density GPU workloads
  • Construction of 20 MW CB-1 HPC/AI facility on track for Q1 2025 completion
  • Secured long-lead items for 50 MW CB-2 AI/HPC facility
Negative
  • Average power cost per bitcoin mined increased to $35,109 in September from $35,407 in August

Insights

TeraWulf's September update reveals solid operational progress and strategic moves. The company mined 176 bitcoin at an average rate of 5.9 per day, maintaining a 10.0 EH/s operational capacity, which represents a 100% year-over-year increase. The average power cost per bitcoin mined was $35,109, translating to $0.042/kWh.

The recent sale of their 25% stake in the Nautilus facility for $92 million is a significant development. This capital will be reinvested into expanding their Lake Mariner facility, particularly the 20 MW CB-1 HPC/AI infrastructure. The completion of the 2 MW 'WULF Den' proof-of-concept for high-density GPU workloads signals TeraWulf's commitment to diversifying into AI and HPC markets.

The ongoing construction of CB-1 and plans for CB-2 (50 MW) demonstrate a clear growth strategy in the high-performance computing sector. This pivot towards AI/HPC infrastructure could potentially provide more stable and diversified revenue streams compared to volatile bitcoin mining. However, investors should monitor the execution of these projects and their impact on the company's financials in the coming quarters.

TeraWulf's strategic shift towards HPC/AI infrastructure is a notable development in the crypto mining sector. The completion of the 2.5 MW HPC/AI proof-of-concept project at Lake Mariner is a significant milestone, showcasing the company's ability to support next-generation GPU technology. This move aligns with the growing demand for AI computing resources and could position TeraWulf as a key player in the intersection of blockchain and AI technologies.

The ongoing construction of CB-1, a 20 MW colocation building with Tier 3 data center features, demonstrates TeraWulf's commitment to high-quality infrastructure. The 16 MW of critical IT load with liquid cooling and redundancy features is particularly impressive, as it caters to the high-density computing needs of AI workloads. This infrastructure could attract partnerships with AI companies and research institutions, potentially opening up new revenue streams.

However, the transition from pure bitcoin mining to a hybrid model including HPC/AI services will require careful management of resources and potential challenges in scaling operations. Investors should watch for updates on client acquisition and utilization rates of these new facilities to gauge the success of this strategic pivot.

Significant advancements in HPC/AI digital infrastructure at Lake Mariner

10.0 EH/s of operational self-mining capacity, doubling year-over-year

EASTON, Md., Oct. 04, 2024 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), a leading owner and operator of vertically integrated, next-generation digital infrastructure powered by predominantly zero-carbon energy, today provided an unaudited monthly production and operations update for September 2024.

September 2024 Production and Operations Highlights

  • Self-Mined Bitcoin: TeraWulf mined 176 bitcoin in September, achieving an average production rate of approximately 5.9 bitcoin per day.
  • Operating Capacity: The Company's operational self-mining capacity remained at approximately 10.0 EH/s, representing a 100.0% increase year-over-year.
  • Power Cost: The average power cost per bitcoin mined was $35,109 in September, corresponding to an approximate rate of $0.042/kWh. This figure excludes anticipated proceeds from demand response and ancillary services.

Key Metrics1September 2024August 2024
Bitcoin Self-Mined Lake Mariner 140 147
Bitcoin Self-Mined Nautilus 36 37
Value per Bitcoin Self-Mined2$60,168$60,025
Power Cost per Bitcoin Self-Mined$35,109$35,407
Avg. Operating Hash Rate (EH/s)3 8.2 8.2
Nameplate Miner Efficiency (J/TH)4 24.6 24.6


Recent Strategic Development

On October 3, 2024, TeraWulf announced the closing of the sale of its 25% equity interest in the Nautilus facility for total consideration of approximately $92 million. The Company plans to reinvest this capital into the construction of the 20 MW CB-1 facility at Lake Mariner, as detailed further below.

Management Commentary

"During September, TeraWulf mined 176 bitcoin, maintaining an average production rate of approximately 6 bitcoin per day,” said Sean Farrell, Senior Vice President of Operations at TeraWulf. “We are currently implementing large-scale PSU replacements and ventilation upgrades in miner building 3, “MB-3”, to enhance performance as cooler fall temperatures arrive.”

Farrell continued, "The recent sale of our equity interest in Nautilus has provided significant capital to accelerate the expansion of our HPC and AI data center at Lake Mariner. This strategic reinvestment strengthens our ongoing initiatives, including the successful completion of our 2 MW 'WULF Den' proof-of-concept for WULF Compute, designed for high-density GPU workloads. Construction of CB-1, our 20 MW HPC/AI facility at Lake Mariner, is on track, with completion expected in Q1 2025. We’ve also secured long-lead items for CB-2, a 50 MW AI/HPC facility, to ensure timely completion in early Q2 2025."

Production and Operations Update

As of September 30, 2024, TeraWulf's operational bitcoin mining capacity included 195 MW at the Lake Mariner facility and 50 MW at the Nautilus facility. The Company's total self-mining hash rate stands at approximately 10.0 EH/s. In September, TeraWulf's miners operated at an average of 8.2 EH/s, influenced by demand response events and performance tuning strategies aimed at maximizing profitability.

On the WULF Compute front, TeraWulf continues to advance its large-scale HPC/AI project at the Lake Mariner facility. This includes the recent completion of a 2.5 MW (gross) HPC/AI digital infrastructure proof-of-concept project, designed to support both current and next-generation GPU technology. Furthermore, TeraWulf is constructing CB-1, a 20 MW colocation building engineered to support 16 MW of critical IT load with liquid cooling and redundancy features typical of a Tier 3 data center (e.g., N+1 redundant cooling systems, variable speed fans, chilled water systems, dual power supply and redundant fiber network paths). The CB-1 facility is on track to be operational in Q1 2025.

About TeraWulf

TeraWulf develops, owns, and operates environmentally sustainable, next-generation data center infrastructure in the United States, specifically designed for Bitcoin mining and high-performance computing. Led by a team of seasoned energy entrepreneurs, the Company owns and operates the Lake Mariner facility situated on the expansive site of a now retired coal plant in Western New York. Currently, TeraWulf generates revenue primarily through Bitcoin mining, leveraging predominantly zero-carbon energy sources, including nuclear and hydroelectric power. Committed to environmental, social, and governance (ESG) principles that align with its business objectives, TeraWulf aims to deliver industry-leading economics in mining and data center operations at an industrial scale.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “predict,” “should,” “would” and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf’s management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf’s operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf and/or its business; and (12) other risks and uncertainties detailed from time to time in the Company’s filings with the Securities and Exchange Commission (“SEC”). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company’s filings with the SEC, which are available at www.sec.gov.

Company Contact:
Jason Assad
Director of Corporate Communications
assad@terawulf.com
(678) 570-6791


1 The Company’s share of the earnings or losses from operations at the Nautilus Cryptomine facility is reflected within “Equity in net income (loss) of investee, net of tax” in the consolidated statements of operations. Accordingly, operating results of the Nautilus Cryptomine facility are not reflected in revenue, cost of revenue or cost of operations lines in TeraWulf’s consolidated statements of operations. The Company uses these metrics as indicators of operational progress and effectiveness and believes they are useful to investors for the same purposes and to provide comparisons to peer companies. All figures except Bitcoin Self-Mined are estimates and remain subject to standard month-end adjustments.
2 Computed as the weighted-average opening price of bitcoin on each respective day the Bitcoin Self-Mined is earned.
3 While nameplate mining inventory as of September 30, 2024 for WULF’s two facilities is estimated at 10.0 EH/s, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.
4 Nameplate miner efficiency excludes auxiliary load.


FAQ

How many bitcoin did TeraWulf (WULF) mine in September 2024?

TeraWulf mined 176 bitcoin in September 2024, achieving an average production rate of approximately 5.9 bitcoin per day.

What was TeraWulf's (WULF) operational self-mining capacity in September 2024?

TeraWulf's operational self-mining capacity remained at approximately 10.0 EH/s, representing a 100.0% increase year-over-year.

What was the average power cost per bitcoin mined for TeraWulf (WULF) in September 2024?

The average power cost per bitcoin mined was $35,109 in September 2024, corresponding to an approximate rate of $0.042/kWh.

What strategic development did TeraWulf (WULF) announce on October 3, 2024?

TeraWulf announced the closing of the sale of its 25% equity interest in the Nautilus facility for total consideration of approximately $92 million.

What is the status of TeraWulf's (WULF) CB-1 facility construction at Lake Mariner?

The construction of CB-1, a 20 MW HPC/AI facility at Lake Mariner, is on track, with completion expected in Q1 2025.

TeraWulf Inc.

NASDAQ:WULF

WULF Rankings

WULF Latest News

WULF Stock Data

2.50B
277.46M
28.53%
46.17%
14.18%
Capital Markets
Finance Services
Link
United States of America
EASTON