Skyharbour to Carry Out Multi-Phased, 2025 Drilling Campaign Totalling 16-18,000 Metres at its Russell Lake and Moore Uranium Projects, Saskatchewan
Skyharbour Resources (SYHBF) has announced its largest-ever drilling campaign for 2025, planning 16,000-18,000 meters across 35-45 holes at its Russell Lake and Moore Uranium Projects in Saskatchewan. The fully-funded program includes:
At Russell Lake (73,294 hectares): 10,000-11,000 meters across 18-20 holes, focusing on the Fork target (where recent drilling discovered high-grade uranium of 0.721% U3O8 over 2.5 meters), Sphinx targets, M-Zone Extension, and Fox Lake Trail target.
At Moore Project (35,705 hectares): 5,000-7,000 meters across 18-24 holes, targeting the Maverick Corridor's 4.7-kilometer strike length. Recent drilling at Moore yielded significant results, including 4.61% U3O8 over 5.0m.
The campaign will operate from the exploration camp at Russell Lake, located along the road to Cameco's McArthur River Uranium Mine, with drilling set to commence within weeks.
Skyharbour Resources (SYHBF) ha annunciato la sua campagna di perforazione più grande mai realizzata per il 2025, pianificando 16.000-18.000 metri su 35-45 pozzi nei suoi progetti di uranio Russell Lake e Moore in Saskatchewan. Il programma è completamente finanziato e include:
Presso Russell Lake (73.294 ettari): 10.000-11.000 metri su 18-20 pozzi, concentrandosi sull'obiettivo Fork (dove recenti perforazioni hanno scoperto uranio di alta qualità dello 0,721% U3O8 su 2,5 metri), sugli obiettivi Sphinx, sull'estensione M-Zone e sull'obiettivo Fox Lake Trail.
Presso Moore Project (35.705 ettari): 5.000-7.000 metri su 18-24 pozzi, mirando alla lunghezza di strike di 4,7 chilometri del Maverick Corridor. Le recenti perforazioni a Moore hanno prodotto risultati significativi, inclusi il 4,61% U3O8 su 5,0m.
La campagna opererà dal campo di esplorazione di Russell Lake, situato lungo la strada verso la miniera di uranio McArthur River di Cameco, con la perforazione che inizierà entro poche settimane.
Skyharbour Resources (SYHBF) ha anunciado su campaña de perforación más grande hasta la fecha para 2025, planeando 16.000-18.000 metros a través de 35-45 pozos en sus Proyectos de Uranio Russell Lake y Moore en Saskatchewan. El programa está completamente financiado e incluye:
En Russell Lake (73.294 hectáreas): 10.000-11.000 metros en 18-20 pozos, centrándose en el objetivo Fork (donde perforaciones recientes descubrieron uranio de alta ley del 0,721% U3O8 en 2,5 metros), en los objetivos Sphinx, en la extensión M-Zone y en el objetivo Fox Lake Trail.
En Moore Project (35.705 hectáreas): 5.000-7.000 metros en 18-24 pozos, apuntando a la longitud de strike de 4,7 kilómetros del Maverick Corridor. Las perforaciones recientes en Moore han dado resultados significativos, incluidos 4,61% U3O8 en 5,0m.
La campaña operará desde el campo de exploración en Russell Lake, ubicado a lo largo de la carretera hacia la Mina de Uranio McArthur River de Cameco, con la perforación programada para comenzar en unas pocas semanas.
Skyharbour Resources (SYHBF)는 2025년을 위한 가장 큰 시추 캠페인을 발표하며, 사스카치완에 있는 러셀 레이크 및 무어 우라늄 프로젝트에서 35-45 개의 구멍에 대해 16,000-18,000 미터의 계획을 세우고 있습니다. 완전 자금 지원된 이 프로그램은 다음을 포함합니다:
러셀 레이크 (73,294 헥타르)에서는 10,000-11,000 미터를 18-20 개의 구멍에 걸쳐 시추할 계획이며, 최근 시추에서 2.5 미터 구간에 대해 0.721% U3O8의 고급 우라늄이 발견된 Fork 목표, Sphinx 목표, M-Zone Extension 및 Fox Lake Trail 목표에 집중합니다.
무어 프로젝트 (35,705 헥타르)에서는 5,000-7,000 미터를 18-24 개의 구멍에 걸쳐 시추하며, Maverick Corridor의 4.7 킬로미터 스트라이크 길이를 목표로 합니다. 무어에서의 최근 시추는 5.0m에 대해 4.61% U3O8를 포함한 중요한 결과를 가져왔습니다.
이 캠페인은 Cameco의 McArthur River 우라늄 광산으로 가는 도로를 따라 위치한 러셀 레이크의 탐사 캠프에서 운영될 예정이며, 시추는 몇 주 안에 시작될 예정입니다.
Skyharbour Resources (SYHBF) a annoncé sa plus grande campagne de forage jamais réalisée pour 2025, prévoyant 16 000 à 18 000 mètres à travers 35 à 45 trous sur ses projets d'uranium Russell Lake et Moore en Saskatchewan. Le programme entièrement financé comprend :
À Russell Lake (73 294 hectares) : 10 000 à 11 000 mètres sur 18 à 20 trous, en se concentrant sur la cible Fork (où des forages récents ont découvert un uranium de haute teneur à 0,721 % U3O8 sur 2,5 mètres), les cibles Sphinx, l'extension de la zone M et la cible Fox Lake Trail.
Au Moore Project (35 705 hectares) : 5 000 à 7 000 mètres sur 18 à 24 trous, ciblant la longueur de frapper de 4,7 kilomètres du corridor Maverick. Des forages récents à Moore ont donné des résultats significatifs, y compris 4,61 % U3O8 sur 5,0 m.
La campagne fonctionnera depuis le camp d'exploration à Russell Lake, situé le long de la route de la mine d'uranium McArthur River de Cameco, avec un début de forage prévu dans quelques semaines.
Skyharbour Resources (SYHBF) hat seine größte Bohrkampagne für 2025 angekündigt, die 16.000-18.000 Meter über 35-45 Löcher in seinen Uranprojekten Russell Lake und Moore in Saskatchewan umfasst. Das vollständig finanzierte Programm beinhaltet:
Bei Russell Lake (73.294 Hektar): 10.000-11.000 Meter über 18-20 Löcher, mit Fokus auf dem Fork-Ziel (wo bei aktuellen Bohrungen hochgradiges Uran mit 0,721% U3O8 über 2,5 Meter entdeckt wurde), den Zielen Sphinx, der M-Zone-Erweiterung und dem Fox Lake Trail-Ziel.
Bei Moore Project (35.705 Hektar): 5.000-7.000 Meter über 18-24 Löcher, mit Fokus auf der 4,7 Kilometer langen Strike-Linie des Maverick-Korridors. Kürzliche Bohrungen bei Moore ergaben bedeutende Ergebnisse, einschließlich 4,61% U3O8 über 5,0 m.
Die Kampagne wird vom Explorationscamp bei Russell Lake aus betrieben, das sich entlang der Straße zur McArthur River Uranmine von Cameco befindet, und die Bohrungen sollen in wenigen Wochen beginnen.
- Largest annual drill campaign in company history with 16,000-18,000 meters planned
- Program is fully funded
- Recent high-grade uranium discovery at Fork target with 0.721% U3O8 over 2.5m
- Strong recent drilling results at Moore with 4.61% U3O8 over 5.0m
- Strategic location between major uranium projects with existing infrastructure
- Pending assay results from late 2024 drilling campaigns at both projects
- Core loss and significant faulting reported in some historical drilling
Vancouver, BC, Jan. 16, 2025 (GLOBE NEWSWIRE) -- Skyharbour Resources Ltd. (TSX-V: SYH) (OTCQX: SYHBF) (Frankfurt: SC1P) (“Skyharbour” or the “Company”) is pleased to announce plans for fully-funded, upcoming drill programs at its co-flagship Russell Lake and Moore Uranium Projects in 2025 totalling approx. 16,000 – 18,000 metres in 35 – 45 holes representing the largest annual drill campaign ever carried out by the Company.
Russell Lake and Moore Projects Location Map:
https://www.skyharbourltd.com/_resources/images/SKY_RussellLake.jpg
At the 73,294 hectare Russell Lake Uranium Project (“Russell”), which is majority owned by Skyharbour as operator with minority joint-venture partner Rio Tinto Exploration Canada Inc. (“RTEC”), the Company is planning 10,000 - 11,000 metres of diamond drilling in 18 to 20 holes. This drilling will take place in multiple phases through the year, with mobilization and commencement planned within the next few weeks. Following the initial phase of drilling at Russell, Skyharbour plans to move the drill rig over to its adjacent
Jordan Trimble, President and CEO of Skyharbour, stated: “The upcoming commencement of drilling at Russell and Moore marks the start of our most ambitious annual drilling campaign we have ever carried out. The fully-funded 16-18,000-metre, multi-phased program will provide steady news flow throughout the year as we advance the projects using systematic and proven exploration methodologies to follow up on the success of the 2024 drilling. We are confident in the exploration upside at both projects given the high-grade mineralization in recent drilling along with the many highly prospective target areas hosting the geology necessary for high-grade uranium deposition. We also benefit from low-cost drilling and relatively shallow target depths at our Russell and Moore projects. Finally, Skyharbour will have plenty of additional news flow and catalysts from its prospect generator business consisting of partner companies advancing several of our other projects throughout the Athabasca Basin. This year, the Company is anticipating drilling and exploration at its partner-funded projects of Preston, South Falcon East, Falcon, South Dufferin, Highway and 914W.”
Upcoming Winter Phase of Diamond Drilling at Russell Lake:
Skyharbour will soon commence its 2025 drilling program at the Russell Lake Project with plans for a first phase consisting of approx. 5,000 metres to follow up on notable recent exploration success and to test new targets developed by the geological team. The focus for this phase of drilling will be on the Fork and Sphinx targets within the broader Grayling target area, as well as the M-Zone Extension (“MZE”) target and the Fox Lake Trail target. This initial winter program will consist of 10 to 12 drill holes, with most of the targets being road accessible and near the exploration camp, bringing the drill costs down. Further details on the drilling are forthcoming, and geochemical assay results are pending from the drilling recently carried out in late 2024 at Russell.
Russell Lake Project Target Areas:
https://www.skyharbourltd.com/_resources/images/20240110-MainTargetsRussellLake2024.jpg
The Fork target is a newly identified target to the southwest of the Grayling Zone and on-strike with Denison’s M-Zone at their adjacent Wheeler River Project. Last year, high-grade uranium was discovered at the Fork target in hole RSL24-02, which returned a 2.5 metre wide intercept of
Grayling and Fork Target Areas:
https://skyharbourltd.com/_resources/images/2024-Fork-East-Grayling-Drill-Hole-Location-Map_NR.jpg
Skyharbour also plans to drill targets in the M-Zone Extension area along trend from the Grayling Zone and Denison’s M-Zone, where historical drilling intersected basement-hosted uranium mineralization. More recent drilling by Denison in 2020 at the M-Zone encountered uranium mineralization with significant faulting, core loss, geochemical anomalies, and radioactivity encountered in other drill holes. Like the Grayling Zone, the mineralization at the MZE target is hosted by a graphitic thrust fault within a significant magnetic low. It is also noted that cross structures associated with Denison’s Phoenix and Gryphon uranium deposits potentially trend onto the Russell Lake property within the M-Zone Extension target area, further enhancing the prospectivity of this target.
M-Zone Extension Drill Targets:
https://www.skyharbourltd.com/_resources/images/20240110-M-ZoneExtensionTargetsRussellLake.jpg
Upcoming Winter Phase of Diamond Drilling at Moore:
Skyharbour plans to conduct a second phase of drilling consisting of 3,000-3,500 metres in 9 to 12 holes at its Moore Project upon completion of the initial phase of drilling at Russell. Drilling at the Maverick Corridor will focus on identifying new trends and extensions within untested portions of its 4.7-kilometre strike length. Additional drilling is planned within the Maverick Main and East Zones to concentrate on refinement and expansion of the currently identified mineralized zones. The Maverick Main Zone is characterized by basement- and unconformity-hosted mineralization with a highlight interval drilled previously by Skyharbour of
Moore Uranium Project Regional Grid Targets Map:
https://skyharbourltd.com/_resources/maps/Moore-Lake-Property-Wide.jpg
Russell Lake Uranium Project Overview:
The Russell Lake Project is a large, advanced-stage uranium exploration property totalling 73,294 hectares strategically located between Cameco’s Key Lake and McArthur River Projects, and adjoining Denison’s Wheeler River Project to the west and Skyharbour’s Moore Uranium Project to the east. The northern extension of Highway 914 between Key Lake and McArthur River runs through the western extent of the property and greatly enhances accessibility, while a high-voltage powerline is situated alongside this road. Skyharbour’s acquisition of a majority interest in Russell Lake creates a large, nearly contiguous block of highly prospective uranium claims totalling 108,999 hectares between the Russell Lake and the Moore uranium projects. Several notable exploration targets exist on Russell, including the Grayling Zone, the M-Zone Extension target, the Little Man Lake target, the Christie Lake target, the Fox Lake Trail target and the newly identified Fork Zone target. More than 35 kilometres of largely untested prospective conductors in areas of low magnetic intensity also exist on the Property. Skyharbour is the operator and owns a majority interest in Russell Lake, having formed a joint venture partnership with RTEC at the project.
Moore Uranium Project Overview:
The Moore project consists of 12 contiguous claims totaling 35,705 hectares located 42 kilometres northeast of the Key Lake mill, 15 kilometres east of Denison’s Wheeler River project, and 39 kilometres south of Cameco’s McArthur River uranium mine. Unconformity-style, high-grade uranium mineralization has been discovered on the Moore Project along the Maverick conductive corridor. In addition to the Maverick zones, the project hosts other mineralized targets with strong discovery potential which the Company plans to test with future drill programs. The project is fully accessible via winter and ice roads, which simplifies logistics and lowers costs, while most of the property is accessible in the summer as well.
Qualified Person:
The technical information in this news release has been prepared in accordance with the Canadian regulatory requirements set out in National Instrument 43-101 and reviewed and approved by Serdar Donmez, P.Geo., VP of Exploration for Skyharbour as well as a Qualified Person.
About Skyharbour Resources Ltd.:
Skyharbour holds an extensive portfolio of uranium exploration projects in Canada's Athabasca Basin and is well positioned to benefit from improving uranium market fundamentals with interest in thirty-six projects covering over 614,000 hectares (over 1.5 million acres) of land. Skyharbour has acquired from Denison Mines, a large strategic shareholder of the Company, a
Skyharbour also has joint ventures with industry leader Orano Canada Inc., Azincourt Energy, and Thunderbird Resources at the Preston, East Preston, and Hook Lake Projects, respectively. The Company also has several active earn-in option partners, including CSE-listed Basin Uranium Corp. at the Mann Lake Uranium Project; TSX-V listed North Shore Uranium at the Falcon Project; UraEx Resources at the South Dufferin and Bolt Projects; Hatchet Uranium at the Highway Project; CSE-listed Mustang Energy at the 914W Project; and TSX-V listed Terra Clean Energy at the South Falcon East Project. In aggregate, Skyharbour has now signed earn-in option agreements with partners that total to over
Skyharbour's goal is to maximize shareholder value through new mineral discoveries, committed long-term partnerships, and the advancement of exploration projects in geopolitically favourable jurisdictions.
Skyharbour’s Uranium Project Map in the Athabasca Basin:
https://www.skyharbourltd.com/_resources/images/SKY_SaskProject_Locator_2024-11-21_v1.jpg
To find out more about Skyharbour Resources Ltd. (TSX-V: SYH) visit the Company’s website at www.skyharbourltd.com.
SKYHARBOUR RESOURCES LTD.
“Jordan Trimble”
__________________________________
Jordan Trimble
President and CEO
For further information contact myself or:
Nicholas Coltura
Investor Relations Manager
Skyharbour Resources Ltd.
Telephone: 604-558-5847
Toll Free: 800-567-8181
Facsimile: 604-687-3119
Email: info@skyharbourltd.com
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.
Forward-Looking Information
This news release contains “forward‐looking information or statements” within the meaning of applicable securities laws, which may include, without limitation, completing ongoing and planned work on its projects including drilling and the expected timing of such work programs, other statements relating to the technical, financial and business prospects of the Company, its projects and other matters. All statements in this news release, other than statements of historical facts, that address events or developments that the Company expects to occur, are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in the forward-looking statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which the Company will operate in the future, including the price of uranium, the ability to achieve its goals, that general business and economic conditions will not change in a material adverse manner, that financing will be available if and when needed and on reasonable terms. Such forward-looking information reflects the Company’s views with respect to future events and is subject to risks, uncertainties and assumptions, including the risks and uncertainties relating to the interpretation of exploration results, risks related to the inherent uncertainty of exploration and cost estimates and the potential for unexpected costs and expenses, and those filed under the Company’s profile on SEDAR+ at www.sedarplus.ca. Factors that could cause actual results to differ materially from those in forward looking statements include, but are not limited to, continued availability of capital and financing and general economic, market or business conditions, adverse weather or climate conditions, failure to obtain or maintain all necessary government permits, approvals and authorizations, failure to obtain or maintain community acceptance (including First Nations), decrease in the price of uranium and other metals, increase in costs, litigation, and failure of counterparties to perform their contractual obligations. The Company does not undertake to update forward‐looking statements or forward‐looking information, except as required by law.
FAQ
What is the size of Skyharbour's (SYHBF) 2025 drilling campaign?
What were the recent uranium discovery results at SYHBF's Fork target?
How many meters will SYHBF drill at the Russell Lake project in 2025?
What are the recent drilling results from SYHBF's Moore Project?