Silvercorp Announces the Construction Plan and Schedule for the Development of the El Domo Project
Silvercorp Metals (TSX/NYSE: SVM) has announced its construction budget for the El Domo Project development, targeting production by end of 2026. The total estimated cost is $240.5 million, slightly lower than the 2021 feasibility study estimate of $247.6 million.
The project is divided into five bid packages: (1) Site preparation/Roads/TSF ($47.5M), (2) Open Pit Mining ($39.0M), (3) Processing Plant Construction ($33.0M), (4) Power line construction, and (5) Diesel generators. CRCC 14 Bureau Group was awarded Package #1 in January 2025.
The construction plan includes stripping 5.4 million cubic metres of sediments and waste rocks, with 3.5 million cubic metres of NAG waste rock for dam construction. The processing plant construction and equipment installation is expected to complete by November 2026, with commissioning in December 2026.
Silvercorp Metals (TSX/NYSE: SVM) ha annunciato il budget per la costruzione del progetto El Domo, con l'obiettivo di avviare la produzione entro la fine del 2026. Il costo totale stimato è di 240,5 milioni di dollari, leggermente inferiore alla stima di 247,6 milioni di dollari del studio di fattibilità del 2021.
Il progetto è suddiviso in cinque lotti di gara: (1) Preparazione del sito/Strade/TSF (47,5 milioni di dollari), (2) Estrazione a cielo aperto (39,0 milioni di dollari), (3) Costruzione dell’impianto di lavorazione (33,0 milioni di dollari), (4) Costruzione della linea elettrica e (5) Generator diesel. Il gruppo CRCC 14 Bureau è stato assegnatario del Lotto #1 a gennaio 2025.
Il piano di costruzione prevede la rimozione di 5,4 milioni di metri cubi di sedimenti e rocce di scarto, con 3,5 milioni di metri cubi di rocce di scarto NAG utilizzate per la costruzione della diga. La costruzione dell’impianto di lavorazione e l’installazione delle attrezzature dovrebbero essere completate entro novembre 2026, con la messa in servizio prevista per dicembre 2026.
Silvercorp Metals (TSX/NYSE: SVM) ha anunciado su presupuesto de construcción para el desarrollo del Proyecto El Domo, con la meta de iniciar la producción a finales de 2026. El costo total estimado es de 240,5 millones de dólares, ligeramente inferior a la estimación del estudio de factibilidad de 2021, que era de 247,6 millones de dólares.
El proyecto se divide en cinco paquetes de licitación: (1) Preparación del sitio/Carreteras/TSF (47,5 millones de dólares), (2) Minería a cielo abierto (39,0 millones de dólares), (3) Construcción de la planta de procesamiento (33,0 millones de dólares), (4) Construcción de la línea eléctrica y (5) Generadores diésel. El grupo CRCC 14 Bureau fue adjudicado con el Paquete #1 en enero de 2025.
El plan de construcción incluye la remoción de 5,4 millones de metros cúbicos de sedimentos y rocas de desecho, con 3,5 millones de metros cúbicos de rocas de desecho NAG para la construcción de la presa. Se espera que la construcción de la planta de procesamiento y la instalación del equipo finalicen en noviembre de 2026, con la puesta en marcha en diciembre de 2026.
Silvercorp Metals (TSX/NYSE: SVM)는 2026년 말까지 생산을 목표로 하는 El Domo 프로젝트 개발을 위한 건설 예산을 발표했습니다. 총 예상 비용은 2억 4,050만 달러로, 2021년 타당성 조사에서 추정한 2억 4,760만 달러보다 다소 낮습니다.
이 프로젝트는 다섯 개의 입찰 패키지로 나뉩니다: (1) 부지 준비/도로/TSF (4,750만 달러), (2) 노천 채굴 (3,900만 달러), (3) 가공 공장 건설 (3,300만 달러), (4) 전력선 건설, (5) 디젤 발전기. CRCC 14 Bureau 그룹은 2025년 1월에 패키지 #1을 수주했습니다.
건설 계획에는 540만 입방미터의 퇴적물과 폐석을 제거하는 작업이 포함되며, 350만 입방미터의 NAG 폐석은 댐 건설에 사용될 예정입니다. 가공 공장 건설과 장비 설치는 2026년 11월까지 완료될 예정이며, 시운전은 2026년 12월에 이루어집니다.
Silvercorp Metals (TSX/NYSE : SVM) a annoncé son budget de construction pour le développement du projet El Domo, visant une production d'ici fin 2026. Le coût total estimé est de 240,5 millions de dollars, légèrement inférieur à l'estimation de l'étude de faisabilité de 2021, qui était de 247,6 millions de dollars.
Le projet est divisé en cinq lots : (1) préparation du site/routes/TSF (47,5 M$), (2) exploitation à ciel ouvert (39,0 M$), (3) construction de l’usine de traitement (33,0 M$), (4) construction de la ligne électrique et (5) groupes électrogènes diesel. Le groupe CRCC 14 Bureau a obtenu le lot n°1 en janvier 2025.
Le plan de construction comprend le décapage de 5,4 millions de mètres cubes de sédiments et de roches stériles, avec 3,5 millions de mètres cubes de stériles NAG utilisés pour la construction du barrage. La construction de l’usine de traitement et l’installation des équipements devraient être terminées d’ici novembre 2026, avec la mise en service prévue en décembre 2026.
Silvercorp Metals (TSX/NYSE: SVM) hat sein Bau-Budget für die Entwicklung des El Domo Projekts bekanntgegeben, mit dem Ziel, die Produktion bis Ende 2026 aufzunehmen. Die geschätzten Gesamtkosten belaufen sich auf 240,5 Millionen US-Dollar, was leicht unter der Schätzung der Machbarkeitsstudie von 2021 in Höhe von 247,6 Millionen US-Dollar liegt.
Das Projekt ist in fünf Ausschreibungspakete unterteilt: (1) Standortvorbereitung/Straßen/TSF (47,5 Mio. USD), (2) Tagebau (39,0 Mio. USD), (3) Bau der Aufbereitungsanlage (33,0 Mio. USD), (4) Bau der Stromleitung und (5) Dieselgeneratoren. Die CRCC 14 Bureau Group erhielt im Januar 2025 das Paket Nr. 1.
Der Bauplan umfasst das Abtragen von 5,4 Millionen Kubikmetern Sedimenten und Abraum, wobei 3,5 Millionen Kubikmeter NAG-Abraum für den Damm verwendet werden. Der Bau der Aufbereitungsanlage und die Installation der Ausrüstung sollen bis November 2026 abgeschlossen sein, die Inbetriebnahme ist für Dezember 2026 geplant.
- Project cost estimate decreased to $240.5M from $247.6M in feasibility study
- Direct costs reduced by $32.6M to $159.5M through Unit Cost contract
- 550,000 cubic metres of ore will be ready to support three years of production
- Package #1 construction already commenced in January 2025
- Owner's costs increased by $20M to $30M from initial $10M estimate
- Contingency costs increased by $9.9M to $31.9M from $22M
- Climate change impacts requiring additional standby diesel power generators
- Power line construction timeline uncertainty (13-17 months)
Insights
Silvercorp's $240.5M El Domo construction plan shows disciplined capital management with production targeted by end-2026, following feasibility study parameters.
Silvercorp's announced
The detailed cost breakdown shows financial discipline, with
Notable engineering improvements include enhanced steel-framed buildings to protect equipment from tropical storms, showing adaptation to local conditions. The company's approach to power supply demonstrates risk mitigation - they're constructing a traditional powerline while also securing standby diesel generators to address potential climate-related power challenges in Ecuador.
The cost structure revisions compared to the feasibility study reveal a more conservative financial approach - direct costs decreased by
The mining plan includes stripping 5.4 million cubic meters of material, with 3.5 million cubic meters of non-acid generating waste rock being repurposed for tailings storage facility construction, showing efficient resource utilization. By project completion, they expect to have 550,000 cubic meters of ore ready to support three years of production.
El Domo's carefully structured $240.5M capital plan balances cost efficiency with increased contingencies, signaling measured development approach.
This construction budget announcement represents a significant capital commitment for Silvercorp, with the
The financial structure of the project shows thoughtful capital allocation. Direct costs represent
Compared to the 2021 feasibility study, the company has achieved a
The use of unit price contracts for Package #1 (and potentially Package #2) represents a risk-sharing approach that may help control cost overruns, as contractors assume some execution risk under such arrangements. The contract award to CRCC 14 for the
The company's decision to incorporate both grid power and backup diesel generators addresses Ecuador's climate-related power supply challenges, though this dual approach will impact both capital and potentially operating costs. Without production estimates or economic projections in this announcement, investors must refer to the 2021 feasibility study to evaluate the project's potential financial returns relative to this capital investment.
Trading Symbol: TSX/NYSE American: SVM
As discussed in its January 7, 2025 Press Release, the Company has been building upon the 2021 Feasibility Study, with work to date focusing on:
- Advanced Detailed Engineering for: a) Optimized design with Klohn Crippen Berger (KCB) for the Tailings Storage Facilities ("TSF"), Saprolite Waste Dump ("SWD"), and non-contact water channels; b) Optimized open pit mine design for mining, stripping, and scheduling, and coordinated the mining schedule with ongoing tailings dam construction by internal mining engineers; and c) Detailed Engineering Design for the process plant and equipment selection by Yantai Jinpeng Mining Machinery Co., Ltd and Yantai Orient Metallurgical Design and Research Institute Co., Ltd (together "Jinpeng"), a
China certified Engineering Design, Manufacture and Construction Group which has provided design, equipment, and construction for mining process plants inChina and internationally. - Advanced Project Infrastructure for: a) Optimized designs for a new public bypass road and internal operational haul roads; b) Executed a powerline contract with the Ecuadorian state-owned power company (CNEL EP) and initiated bidding process for contractor selection; and c) permitting and sourcing for standby diesel power generators for the dry season, as climate change has impacted the power supply situation in
Ecuador . - Produced Project Materials Balance for: a) Bid Package 1: Construction of temporary camp, TSF to starter dam phase, SWD, non-contact water channels, internal haul roads, and preparation of the process plant site and permanent camp site; b) Bid Package 2: Open Pit Mining, stripping and ongoing tailings dam raises using stripped waste rocks; c) Bid Package 3: Construction of the process plant, tailings discharge and reclaim water systems, water treatment plants, permanent camp, and other site infrastructures; d) Bid Package 4 for the construction of the Power line; and e) Bid Package 5 for the diesel power generators.
Capital Cost Estimate Details
The table below summarizes the schedule and costs to construct the El Domo Project:
Fiscal 2026 | Fiscal 2027 | Total | ||
($ Million) | ($ Million) | ($ Million) | ||
1 | Package #1 - Site preparation/Roads/Channels/TSF/SWD | |||
2 | Package #2 - Open Pit Mining and Stripping | 7.0 | 32.0 | 39.0 |
3 | Package #3 - Processing Plant Construction and Equipment | 14.0 | 19.0 | 33.0 |
4 | Temporary and Permanent Camps | 2.0 | 5.0 | 7.0 |
5 | Packages #4,5 -Site Infrastructure (bypass roads, powerline, standby diesel generators, water treatment plant) | 16.0 | 17.0 | 33.0 |
Direct costs sub-total | ||||
6 | Owner's Contingency | 13.6 | 18.3 | 31.9 |
7 | Owner's Cost | 12.0 | 18.0 | 30.0 |
8 | Value added tax (VAT) | 8.2 | 10.9 | 19.1 |
Total |
Package #1 - Site Preparation/Roads/Channel/TSF
The commercial contract for Package #1 was awarded in January 2025 to CRCC 14 Bureau Group Co. Ltd. ("CRCC 14"), a company with a regional headquarters in
The estimated capital costs for Package #1 are based on the unit prices as indicated in the contract multiplied by the design quantities of each activity. The table below summarizes the estimated schedule and costs for Package #1.
Fiscal 2026 | Fiscal 2027 | Total | |
($ Million) | ($ Million) | ($ Million) | |
Package #1 | |||
Site Preparation | 10.4 | — | 10.5 |
TSF | 2.8 | 8.4 | 11.2 |
Roads | 5.7 | 3.0 | 8.7 |
Channels | 6.2 | 6.4 | 12.6 |
Other (SWD) | 4.1 | 0.4 | 4.5 |
Package #1 |
Package #2 – Open Pit Mining and Stripping
The cost estimates are based on the optimized mine plan, which is based on the 2021 Feasibility Study, and the initial quotations received from interested contractors on a "Unit Cost" basis, that is the cost of drilling, blasting and removing each cubic metre of rock a certain distance. The Company has not yet awarded the commercial contract for Package #2. The table below summarizes the estimated schedule and costs for Package #2.
Fiscal 2026 | Fiscal 2027 | Total | |
($ Million) | ($ Million) | ($ Million) | |
Package #2 | |||
Stripping | 5.5 | 24.0 | 29.5 |
Ore Mining | — | 0.1 | 0.1 |
Other | 1.5 | 7.9 | 9.4 |
Package #2 – Open pit Mining and Stripping |
The Company expects to commence stripping of the open pit in August 2025, and a total of 5.4 million cubic metres of sediments and waste rocks will be stripped and among this, 3.5 million cubic metres of non-acid generation (NAG) waste rock will be used to build the starter dam and Stage 2 dam of the TSF, permanent camp foundation, and 43,000 tonnes of ore to be produced by the end of 2026. With this stripping of waste rocks, ore in pit, ready to be mined, is expected to be 550,000 cubic metres to support three years of ore production.
Package #3 - Processing Plant Construction and Equipment
The Company has engaged Jinpeng to complete the detailed engineering design of the processing plant based on the 2021 Feasibility Study. Jinpeng is also finalizing the detailed flowsheet, equipment selection and cost estimates for the processing plant construction and equipment. The improvements from the design of the 2021 Feasibility Study are to build a steel-framed building to cover run of ore to avoid tropical storm leaching, and to cover all equipment and operational facilities with steel-framed building. The cost estimates are based on the engineering design, initial bidding price for major equipment from international vendors, market prices for minor equipment in
Fiscal 2026 | Fiscal 2027 | Total | |
($ Million) | ($ Million) | ($ Million) | |
Package #3 | |||
Run of Mine Platform/Shack + Crushing | 1.4 | 0.8 | 2.2 |
Grinding and Cyclone Facilities | 2.1 | 3.2 | 5.3 |
Flotation Workshop Facilities | 3.3 | 5.3 | 8.6 |
Concentrate/Tailings Dewatering Facility | 1.4 | 2.1 | 3.5 |
Process Water Supply/TSF Water Reclaim System | 1.0 | 1.6 | 2.6 |
Laboratory/Maintenance/Electrical/Automation | 1.9 | 2.5 | 4.4 |
General Layout Engineering | 0.5 | 0.7 | 1.2 |
Other | 2.4 | 2.8 | 5.2 |
Package #3 – Processing plant construction and equipment |
The total cost for the processing plant and equipment is estimated at
Power line construction and Stand-by Diesel Power Generators
The Company is currently updating the engineering work for the power line construction and is in the process of selecting contractors to construct the power line. The construction of the power line is expected to be initiated in May 2025 and completed in 13-17 months. The Company has also sourced diesel power generators as standby and emergency power to satisfy
Cost estimates comparison
Compared to the cost estimate of
- Direct costs reduced by
to$32.6 million from$159.5 million , due to savings by employing a Unit Cost contract and detailed engineering;$192 million - VAT reduced by
to$5.9 million from$19.1 million due to reduction of direct costs;$25 million - Contingency increased by
to$9.9 million from$31.9 million ; and$22.0 million - Owner's costs and burn rates increased by
to$20.0 million from$30.0 million .$10 million
Guoliang Ma, P. Geo., Manager of Exploration and Resource of the Company, is the Qualified Person for Silvercorp for the purposes of National Instrument 43-101 – Standards of Disclosure for Mineral Projects and has reviewed and approved the technical information contained in this news release.
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.
For further information
Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding the construction schedule, duration, and costs for the development of the El Domo project, ore tonnage in 2026 and subsequent three year production, and striping ratio etc. By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.
We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including fluctuating commodity prices; recent market events and condition; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in
A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports and filings which are available under its profile at www.sedarplus.ca.
View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-announces-the-construction-plan-and-schedule-for-the-development-of-the-el-domo-project-302435620.html
SOURCE Silvercorp Metals Inc.