Tailings Storage Facility No. 3 and New 1,500 tonne per day Mill Expansion Completed and in Operation at Ying Mine, China

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Silvercorp Metals Inc. (SVM) has successfully completed two major projects at its Ying Mining District in China: a new Tailings Storage Facility (TSF) No. 3 and a 1,500 tonne per day flotation production line. Both facilities were completed in early December 2024, under budget and are now fully operational.

The first phase of TSF No. 3 was constructed for US$28 million (below the original $38 million budget) and provides 9.92 million cubic metres of storage capacity, supporting operations for 12 years. The second phase will add 9.29 million cubic metres, bringing total capacity to 19.21 million cubic metres.

The new 1,500 tpd flotation production line, completed at a cost of $7.2 million, has exceeded expectations by achieving 1,700 tpd capacity after one month, with a target of 1,800 tpd. This expansion increases Ying's total milling capacity to over 1.3 million tonnes per year, accommodating increased mining capacity and future production from the Kuanping mine.

Silvercorp Metals Inc. (SVM) ha completato con successo due progetti importanti nel suo Distretto Minerario di Ying in Cina: una nuova Struttura di Stoccaggio dei Fanghi (TSF) No. 3 e una linea di produzione di flottazione da 1.500 tonnellate al giorno. Entrambe le strutture sono state completate all'inizio di dicembre 2024, sotto budget e ora sono completamente operative.

La prima fase del TSF No. 3 è stata realizzata con un investimento di 28 milioni di dollari USA (al di sotto del budget originale di 38 milioni di dollari) e offre una capacità di stoccaggio di 9,92 milioni di metri cubi, supportando le operazioni per 12 anni. La seconda fase aggiungerà 9,29 milioni di metri cubi, portando la capacità totale a 19,21 milioni di metri cubi.

La nuova linea di produzione di flottazione da 1.500 tpd, completata con un costo di 7,2 milioni di dollari, ha superato le aspettative raggiungendo una capacità di 1.700 tpd dopo un mese, con un obiettivo di 1.800 tpd. Questa espansione aumenta la capacità totale di macinazione di Ying a oltre 1,3 milioni di tonnellate all'anno, accogliendo una maggiore capacità mineraria e una futura produzione dalla miniera di Kuanping.

Silvercorp Metals Inc. (SVM) ha completado con éxito dos proyectos importantes en su Distrito Minero de Ying en China: una nueva Instalación de Almacenamiento de Relaves (TSF) No. 3 y una línea de producción de flotación de 1.500 toneladas por día. Ambas instalaciones se completaron a principios de diciembre de 2024, por debajo del presupuesto y ahora están completamente operativas.

La primera fase del TSF No. 3 se construyó por 28 millones de dólares (por debajo del presupuesto original de 38 millones de dólares) y proporciona una capacidad de almacenamiento de 9,92 millones de metros cúbicos, apoyando las operaciones durante 12 años. La segunda fase añadirá 9,29 millones de metros cúbicos, llevando la capacidad total a 19,21 millones de metros cúbicos.

La nueva línea de producción de flotación de 1.500 tpd, completada a un costo de 7,2 millones de dólares, ha superado las expectativas al alcanzar una capacidad de 1.700 tpd después de un mes, con un objetivo de 1.800 tpd. Esta expansión aumenta la capacidad total de molienda de Ying a más de 1,3 millones de toneladas al año, acomodando la creciente capacidad minera y la futura producción de la mina Kuanping.

Silvercorp Metals Inc. (SVM)는 중국의 잉 광산 지구에서 두 개의 주요 프로젝트를 성공적으로 완료했습니다: 새로운 배수 슬러지 저장 시설(TSF) No. 3 및 일일 1,500톤 플로테이션 생산 라인입니다. 두 시설 모두 2024년 12월 초에 예산보다 저렴하게 완료되었으며 이제 완전히 가동 중입니다.

TSF No. 3의 첫 번째 단계는 원래 예산인 3,800만 달러보다 낮은 2,800만 달러로 건설되었으며, 12년 동안 운영을 지원할 수 있는 9.92백만 입방미터의 저장 용량을 제공합니다. 두 번째 단계는 9.29백만 입방미터를 추가하여 총 용량을 19.21백만 입방미터로 증가시킬 것입니다.

새로운 1,500 tpd 플로테이션 생산 라인은 720만 달러의 비용으로 완료되었으며, 한 달 만에 1,700 tpd의 용량을 달성하여 기대치를 초과하였고, 목표는 1,800 tpd입니다. 이 확장은 잉의 총 제분 용량을 연간 130만 톤 이상으로 증가시켜, 증가하는 채굴 용량과 향후 쿠안핑 광산에서의 생산을 수용합니다.

Silvercorp Metals Inc. (SVM) a réussi à réaliser deux projets majeurs dans son District Minier de Ying en Chine : une nouvelle Installation de Stockage des Résidus (TSF) No. 3 et une ligne de production par flottation d'une capacité de 1.500 tonnes par jour. Les deux installations ont été achevées début décembre 2024, en respectant le budget, et sont désormais entièrement opérationnelles.

La première phase du TSF No. 3 a été construite pour 28 millions de dollars (sous le budget initial de 38 millions de dollars) et offre une capacité de stockage de 9,92 millions de mètres cubes, soutenant les opérations pendant 12 ans. La deuxième phase ajoutera 9,29 millions de mètres cubes, portant la capacité totale à 19,21 millions de mètres cubes.

La nouvelle ligne de production par flottation de 1.500 tpd, achevée pour un coût de 7,2 millions de dollars, a dépassé les attentes en atteignant une capacité de 1.700 tpd après un mois, avec un objectif de 1.800 tpd. Cette expansion augmente la capacité totale de broyage de Ying à plus de 1,3 million de tonnes par an, permettant d'absorber la capacité d'extraction accrue et la production future de la mine de Kuanping.

Silvercorp Metals Inc. (SVM) hat erfolgreich zwei bedeutende Projekte im Ying Mining District in China abgeschlossen: eine neue Tailings Storage Facility (TSF) No. 3 und eine Flotationsproduktionslinie mit einer Kapazität von 1.500 Tonnen pro Tag. Beide Einrichtungen wurden zu Beginn des Dezembers 2024 unter Budget fertiggestellt und sind jetzt vollständig betriebsbereit.

Die erste Phase der TSF No. 3 wurde für 28 Millionen US-Dollar (unter dem ursprünglichen Budget von 38 Millionen US-Dollar) gebaut und bietet eine Lagerkapazität von 9,92 Millionen Kubikmetern, die 12 Jahre lang die Betriebe unterstützt. Die zweite Phase wird weitere 9,29 Millionen Kubikmeter hinzufügen, was die Gesamtkapazität auf 19,21 Millionen Kubikmeter erhöht.

Die neue Flotationsproduktionslinie von 1.500 tpd, die zu Kosten von 7,2 Millionen US-Dollar fertiggestellt wurde, hat die Erwartungen übertroffen, indem sie nach einem Monat eine Kapazität von 1.700 tpd erreicht hat, mit einem Ziel von 1.800 tpd. Diese Erweiterung erhöht die gesamte Mahlkapazität von Ying auf über 1,3 Millionen Tonnen pro Jahr und ermöglicht eine höhere Bergbaukapazität sowie zukünftige Produktionen aus der Kuanping-Mine.

Positive
  • TSF No. 3 completed under budget, saving US$10 million from original estimate
  • New flotation line exceeding design capacity, reaching 1,700 tpd vs 1,500 tpd target
  • Total milling capacity increased to over 1.3 million tonnes per year
  • TSF No. 3 provides 12 years of operational capacity with Phase 1 alone
Negative
  • None.

Insights

The completion of TSF No. 3 and the new flotation line represents a significant operational milestone for Silvercorp. The TSF No. 3's 19.21 million cubic meters total storage capacity, coupled with the $10 million under-budget delivery, demonstrates exceptional project execution. The facility's sophisticated design, including the non-contact water system and HDPE liner, aligns with best-in-class environmental standards.

The new 1,500 tpd flotation line achieving 1,700 tpd in just one month showcases robust engineering. The $7.2 million cost efficiency was achieved through smart integration with existing infrastructure. The expanded capacity to 1.3 million tonnes per year positions Ying for substantial production growth, particularly valuable with the Kuanping mine integration plans.

Most notably, the multi-metal processing capability (silver-lead, zinc, copper and gold) enhances operational flexibility and revenue potential. This expansion effectively future-proofs operations for at least 12 years through Phase 1 alone.

This infrastructure completion carries strong financial implications. The $28 million TSF investment, coming in $10 million under budget, immediately strengthens the company's capital efficiency metrics. The expanded processing capacity to 1.3 million tonnes annually creates significant revenue growth potential without proportional cost increases, suggesting improved economies of scale.

The multi-metal processing capabilities provide valuable optionality in commodity price cycles, while the 12-year minimum lifespan of TSF Phase 1 offers long-term operational visibility. The ability to exceed design capacity (1,700 tpd vs 1,500 tpd) indicates potential for throughput optimization beyond current projections. The efficient integration with existing infrastructure demonstrates strong capital allocation, maintaining a lean cost structure despite significant capacity expansion.

Silvercorp Metals Inc. (CNW Group/Silvercorp Metals Inc)

Trading Symbols: SVM (TSX/NYSE American)

VANCOUVER, BC, Jan. 14, 2025 /PRNewswire/ - Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX: SVM) (NYSE American: SVM), reports the construction of tailings storage facility ("TSF") No. 3 and the new 1,500 tonne per day ("tpd") flotation production line at the Ying Mining District, Henan Province, China ("Ying") were completed in early December 2024, on time and under budget. Both facilities are now fully operating as designed, following a one-month commissioning period. The addition of the new flotation production line will enable the milling capacity at Ying to be increased to over 1.3 million tonnes per year.

Operation of TSF No. 3

Currently the Company is operating three TSFs at Ying, with TSF No. 1 in the process of closing and decommissioning, and TSF No. 2. having 6 years of life remaining.  The first phase of TSF No. 3, with storage capacity of approximately 9.92 million cubic metres, will support Ying at the expanded operating rate of 1.3 million tonnes of ore per year over 12 years. The second phase of TSF No. 3 will have approximately 9.29 million cubic metres of capacity. The total storage capacity of TSF No. 3 is 19.21 million cubic metres.

Phase 1 of TSF No. 3 was constructed for approximately US$28 million, less than the original budget of $38 million (February 24, 2022 news release); the main components of the project included:

  1. Land purchasing and compensation;
  2. Upstream "non-contact water" dam and 1,825 metre long "non-contact water" discharge tunnel, with a 40 centimetre thick steel reinforced concrete liner;  
  3. A 3,200 metre long tailings water discharge tunnel, with a 40 centimetre thick reinforced concrete liner.  Eleven decant towers/wells (shown in Figure 1) at different elevations connected to the 3,200 metre long tunnel to discharge re-settled water to a recycling pond downstream;
  4. A 52 metre high starter dam;
  5. Non-contact water channels and emergency access road surrounding the entire tailings impoundment area,
  6. Impoundment area covered by approximately 400,000 square metres of high density poly-ethylene liner to prevent tailings water from penetrating into the ground;
  7. Tailings discharge and water recycle pumping system; and
  8. Real-time tailings dam stability monitoring and video surveillance system.

In accordance with Chinese safety regulations, TSF No. 3 will be checked and assessed after a three month test run for safety and quality by the Department of Emergency Response of Henan Province, then have a safety production license issued.

Figure 1: Impoundment Area of TSF No. 3 

Figure 1: Impoundment Area of TSF No. 3 (CNW Group/Silvercorp Metals Inc)

1,500 tpd New Flotation Production Line

As previously announced (April 23, 2024 news release), the Company started to construct a 1,500 tpd flotation production line at Ying's No. 2 Mill with a completion date by Q4 2024 and a cost of $7.2 million pursuant to a signed EPCM contract. The 1,500 tpd line was completed on time and on budget, with commissioning taking place in November 2024. 

The relatively low capital expenditures are in part due to taking advantage of existing facilities and infrastructure at the No. 2 mill, including the crushing circuit, concentrate thickener and dewatering system, and the existing tailings discharge system.

The new 1,500 tpd flotation production line, equipped with a Knelson gravity concentrator, is able to produce silver-lead, zinc and copper concentrates, plus gold gravity concentrate.  The robust design of the production line allowed it to achieve 1,700 tpd capacity after one month in operation, with a final target of 1,800 tpd capacity.

With the addition of the new production line, the total milling capacity at Ying is expected to reach over 1.3 million tonnes per year, enough to process increased mining capacity at Ying, plus future production from the nearby Kuanping mine.

Figure 2: Completion Ceremony for the 1,500 tpd New Production Line

Figure 2: Completion Ceremony for the 1,500 tpd New Production Line (CNW Group/Silvercorp Metals Inc)

About Silvercorp

Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cashflow from long-life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) a long-term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.

For further information:

Silvercorp Metals Inc.
Lon Shaver 
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com   

CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS

This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding future milling capacity;  the timing of receipt of licenses and regulatory approvals; remaining life and decomissioning of TSFs; processing of ore stockpiles; and upcoming mine production from the proposed Kuang-Ping underground mine . By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements.  Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including  fluctuating commodity prices; recent market events and condition; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in China; regulatory environment and political climate in Bolivia and Ecuador; integration and operations of Adventus; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; public health crises; the Company's investment in New Pacific Metals Corp. and Tincorp Metals Inc.;  and the other risk factors described in the Company's Annual Information Form and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represent expectations as of the date of this news release and are subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.

A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports and filings which are available under its profile at www.sedarplus.ca.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/tailings-storage-facility-no-3-and-new-1-500-tonne-per-day-mill-expansion-completed-and-in-operation-at-ying-mine-china-302350165.html

SOURCE Silvercorp Metals Inc

FAQ

What is the total storage capacity of Silvercorp's (SVM) new TSF No. 3 facility?

The total storage capacity of TSF No. 3 is 19.21 million cubic metres, with Phase 1 providing 9.92 million cubic metres and Phase 2 adding 9.29 million cubic metres.

How much did SVM save on the construction of TSF No. 3?

Silvercorp saved US$10 million on TSF No. 3 construction, completing it for US$28 million versus the original budget of US$38 million.

What is the new milling capacity at SVM's Ying Mining District after the expansion?

The total milling capacity at Ying has increased to over 1.3 million tonnes per year following the addition of the new flotation production line.

How much did SVM spend on the new 1,500 tpd flotation production line?

The new 1,500 tpd flotation production line was completed on budget at US$7.2 million.

What is the actual processing capacity achieved by SVM's new flotation line?

The new flotation line achieved 1,700 tpd capacity after one month of operation, exceeding its design capacity of 1,500 tpd, with a final target of 1,800 tpd.

Silvercorp Metals Inc. Common Shares

NYSE:SVM

SVM Rankings

SVM Latest News

SVM Stock Data

676.90M
209.41M
3.64%
39.03%
4.52%
Silver
Basic Materials
Link
United States of America
Vancouver