Helium One Global Ltd Announces Jackson-31 Flow Testing and Gas Sampling Analysis
Helium One Global has announced positive flow testing and gas sampling results from the Jackson-31 development well at its Galactica helium project in Colorado. The well, drilled to 1,210 feet, demonstrated strong natural gas flow rates reaching approximately 250 thousand cubic feet per day (Mcfd).
Initial laboratory analysis revealed helium concentrations up to 2.2% air corrected (1.9% not air corrected), with projected reservoir helium concentration expected to equilibrate to 2.3-2.5%. Based on engineering analysis, the well's projected stabilized flow rates are expected between 300-400 Mcfd, with a maximum potential of 500 Mcfd.
The well encountered high-quality, gas-saturated Lyons Sandstone Formation at 1,153 feet, with strong pressure build-up post-testing indicating high permeability and good reservoir communication. The gas composition shows approximately 69% CO2 and 29% nitrogen.
Helium One Global ha annunciato risultati positivi di test di flusso e campionamento di gas dal pozzo di sviluppo Jackson-31 nel suo progetto di elio Galactica in Colorado. Il pozzo, perforato a 1.210 piedi, ha dimostrato forti tassi di flusso di gas naturale che raggiungono circa 250 mila piedi cubi al giorno (Mcfd).
L'analisi di laboratorio iniziale ha rivelato concentrazioni di elio fino a 2,2% corretto per l'aria (1,9% non corretto per l'aria), con una concentrazione di elio nel serbatoio prevista che dovrebbe equilibrarsi tra il 2,3% e il 2,5%. Basandosi su un'analisi ingegneristica, i tassi di flusso stabilizzati previsti per il pozzo sono attesi tra 300-400 Mcfd, con un potenziale massimo di 500 Mcfd.
Il pozzo ha incontrato la formazione di arenaria Lyons, satura di gas, a 1.153 piedi, con un forte aumento di pressione dopo il test che indica alta permeabilità e buona comunicazione del serbatoio. La composizione del gas mostra circa il 69% di CO2 e il 29% di azoto.
Helium One Global ha anunciado resultados positivos de pruebas de flujo y muestreo de gas del pozo de desarrollo Jackson-31 en su proyecto de helio Galactica en Colorado. El pozo, perforado a 1.210 pies, demostró fuertes tasas de flujo de gas natural alcanzando aproximadamente 250 mil pies cúbicos por día (Mcfd).
El análisis de laboratorio inicial reveló concentraciones de helio de hasta 2,2% corregido por aire (1,9% no corregido por aire), con una concentración de helio en el reservorio proyectada que se espera que se equilibre entre el 2,3% y el 2,5%. Según el análisis de ingeniería, se espera que las tasas de flujo estabilizadas del pozo estén entre 300-400 Mcfd, con un potencial máximo de 500 Mcfd.
El pozo encontró la formación de arenisca Lyons, saturada de gas, a 1.153 pies, con un fuerte aumento de presión después de la prueba que indica alta permeabilidad y buena comunicación del reservorio. La composición del gas muestra aproximadamente un 69% de CO2 y un 29% de nitrógeno.
Helium One Global는 콜로라도의 Galactica 헬륨 프로젝트에서 Jackson-31 개발 우물의 긍정적인 유량 테스트 및 가스 샘플링 결과를 발표했습니다. 이 우물은 1,210피트까지 뚫렸으며, 약 250,000 입방피트/일 (Mcfd)에 달하는 강한 천연가스 유량을 나타냈습니다.
초기 실험실 분석 결과, 헬륨 농도가 공기 보정 2.2% (비공기 보정 1.9%)까지 나타났으며, 예상되는 저수지 헬륨 농도는 2.3%에서 2.5%로 균형을 이룰 것으로 보입니다. 공학 분석에 따르면, 우물의 예상 안정화 유량은 300-400 Mcfd 사이로 예상되며, 최대 잠재력은 500 Mcfd입니다.
우물은 1,153피트에서 가스가 포화된 고품질의 Lyons 사암층을 만났으며, 테스트 후 강한 압력 상승이 높은 투과성과 좋은 저수지 통신을 나타냅니다. 가스 조성은 약 69%의 CO2와 29%의 질소를 보여줍니다.
Helium One Global a annoncé des résultats positifs de tests de débit et d'échantillonnage de gaz du puits de développement Jackson-31 dans son projet d'hélium Galactica au Colorado. Le puits, foré à 1 210 pieds, a montré de forts débits de gaz naturel atteignant environ 250 000 pieds cubes par jour (Mcfd).
L'analyse de laboratoire initiale a révélé des concentrations d'hélium allant jusqu'à 2,2% corrigé pour l'air (1,9% non corrigé pour l'air), avec une concentration d'hélium dans le réservoir prévue pour s'équilibrer entre 2,3% et 2,5%. Sur la base d'une analyse technique, les débits stabilisés projetés du puits devraient être compris entre 300-400 Mcfd, avec un potentiel maximal de 500 Mcfd.
Le puits a rencontré la formation de grès Lyons, saturée de gaz, à 1 153 pieds, avec une forte augmentation de pression après le test indiquant une haute perméabilité et une bonne communication du réservoir. La composition du gaz montre environ 69% de CO2 et 29% d'azote.
Helium One Global hat positive Fließtest- und Gasprobenresultate aus dem Entwicklungsbohrloch Jackson-31 in seinem Galactica-Heliumprojekt in Colorado bekannt gegeben. Das Bohrloch, das auf 1.210 Fuß gebohrt wurde, zeigte starke natürliche Gasfließraten von etwa 250.000 Kubikfuß pro Tag (Mcfd).
Die erste Laboranalyse ergab Heliumkonzentrationen von bis zu 2,2% luftkorrekt (1,9% nicht luftkorrekt), wobei die erwartete Heliumkonzentration im Reservoir voraussichtlich auf 2,3-2,5% ausgeglichen wird. Basierend auf ingenieurtechnischen Analysen werden die projizierten stabilisierten Fließraten des Bohrlochs zwischen 300-400 Mcfd erwartet, mit einem maximalen Potenzial von 500 Mcfd.
Das Bohrloch traf bei 1.153 Fuß auf die gasgesättigte Lyons-Sandsteinformation, wobei der starke Druckanstieg nach den Tests auf eine hohe Durchlässigkeit und gute Reservoirkommunikation hinweist. Die Gaszusammensetzung zeigt etwa 69% CO2 und 29% Stickstoff.
- Strong natural gas flow rates reaching 250 Mcfd with projected increase to 300-400 Mcfd
- High helium concentration up to 2.2% (air corrected)
- High-quality, gas-saturated reservoir with strong pressure build-up
- No water encountered during drilling, indicating clean gas production
- High CO2 content (69%) in gas composition may require additional processing
LONDON, UNITED KINGDOM / ACCESS Newswire / March 14, 2025 / Helium One Global (AIM:HE1), the primary helium explorer in Tanzania with a
Summary
Jackson-31 well flowed naturally during drilling and at total depth ("TD"), demonstrating strong reservoir communication
Flow testing measurements since drilling operations were completed have seen increasing natural flow rates to around 250 thousand cubic feet per day ("Mcfd") of total gas
Potential initial stabilised flow rates constrained for production optimisation of 300-400 Mcfd, with a maximum potential rate of 500 Mcfd projected
Early gas samples have returned a helium concentration up to
2.2% air corrected (up to1.9% not air corrected), expected to represent around2.3% to2.5% helium in reservoir based on State-16 recently equilibrated sample
The Company is pleased to announce the initial flow rate results from the Jackson-31 SENW 3054 development well at its Galactica helium project in Las Animas County, Colorado.

Well head testing at Jackson-31 well, Galactica Project
Jackson-31 Summary Analysis
The well reached a TD of 1,210 feet (368m) within the Upper Lyons Formation, encountering the Lyons Sandstone at 1,153 feet (351m). As expected, no water was encountered during drilling of the Lyons Sandstone with wireline logs confirming that the penetrated Lyons Sandstone Formation is of high-quality and gas saturated.
Flow testing since reaching TD has revealed increasing natural flow rates, reaching approximately 250 Mcfd of total gas. Strong pressure build-up post-testing indicates high permeability and good reservoir communication. Based on previous engineering analysis, and the observed flow rates, the projected stabilised flow rates constrained for production optimisation are expected to be between 300-400 Mcfd, with a maximum of 500 Mcfd projected.
Initial laboratory analysis of gas samples from Jackson-31 showed a helium concentration up to
Jackson-31 Initial Flow Test Results
The well reached a TD of 1,210 feet (368m), encountering the Lyons Formation at 1,153 feet (351m) and was deliberately completed 57 feet (17m) into the Upper Lyons Sandstone Formation.
The well exhibited natural gas flow during drilling and at TD. Flow testing has continued, with increasing results demonstrating natural flow rates of approximately 250 Mcfd total gas. Strong pressure build-up post-testing confirms high permeability and good reservoir communication. Well testing and sampling will continue throughout the current drilling campaign.
Blue Star previously released results of an independent engineering analysis of wells in the Galactica-Pegasus project and this analysis established maximum stabilised rates and drawdown for development planning and economic modelling.
The analysis integrated results from the State-16 well with test data from the JXSN-1, JXSN-2, JXSN-3, and JXSN-4 discovery wells, and compared to public information from the adjacent Red Rocks development.
The study concluded:
Calculated permeabilities in the JXSN discovery wells and State-16 well range from 300 to 750 millidarcies ("mD")
This permeability range suggests initial flow rates at 6 psia wellhead pressure of 334 to 780 Mcfd
The State-16 well showed a calculated permeability of 405 mD in the Upper Lyons Formation
State-16 stabilised initial flow rates constrained for production optimisation would be 250 to 350 Mcfd with a maximum of 441 Mcfd
Development planning includes considering vacuum compression ranging from 11 psia (-1 psig) to 6 psia (-6 psig) wellhead pressure which provides the ranges above.
The Jackson-31 well has shown a natural flow rate of approximately 250 Mcfd which compares favourably to the State-16 well which showed a sustained natural flow rate of 150 Mcfd.
Given the higher natural flow at Jackson-31, due to greater permeability in the high-quality Lyons Sandstone Formation and based on previous independent engineering, projected potential stabilised flow rates are expected to be 300-400 Mcfd with a maximum potential rate of 500 Mcfd.
Jackson-31 Well Gas Sampling Results
Gas samples from the Jackson-31 well have been collected and sent for laboratory analysis to determine helium and carbon dioxide concentrations.
Early gas samples from the Jackson-31 well showed a helium concentration up to
Further laboratory analysis will be conducted to perform air correction on samples taken during ongoing flow testing.
For further information please visit the Company's website: www.helium-one.com
Contact
Helium One Global Ltd | +44 20 7920 3150 |
|
|
Panmure LiberumLimited (Nominated Adviser and Joint Broker) | +44 20 3100 2000 |
|
|
Zeus Capital Limited (Joint Broker) | +44 20 3829 5000 |
|
|
Tavistock(Financial PR) | +44 20 7920 3150 |
Notes to Editors
Helium One Global, the AIM-listed Tanzanian explorer, holds prospecting licences across two distinct project areas, with the potential to become a strategic player in resolving a supply-constrained helium market.
The Rukwa and Eyasi projects are located within rift basins on the margin of the Tanzanian Craton in the north and southwest of the country. These assets lie near surface seeps with helium concentrations ranging up to
The Company's flagship southern Rukwa Project is located within the southern Rukwa Rift Basin covering 1,664km2 in south-west Tanzania. This project is considered to be entering an appraisal stage following the success of the 2023/24 exploration drilling campaign, which proved a helium discovery at Itumbula West-1 and, following an extended well test, successfully flowed
Following the success of the extended well test, the Company has now flowed significant quantities of helium to surface and has filed a Mining Licence ("ML") application with the Mining Commission ("MC") of the Tanzanian Government and the MC have now offered the Company an ML consistent with the ML application.
The Company also owns a
Helium One is listed on the AIM market of the London Stock Exchange with the ticker of HE1 and on the OTCQB in the United States with the ticker HLOGF.
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
SOURCE: Helium One Global Ltd
View the original press release on ACCESS Newswire