G Mining Ventures Announces Formal Construction Decision for Tocantinzinho Gold Project and Provides Project Development Update
G Mining Ventures Corp. (GMINF) has officially approved the construction of the Tocantinzinho Gold Project, receiving essential installation license extensions and committing $136 million to date, representing 29% of the total budget. Early works have been completed on schedule and within budget. Key personnel have been appointed to oversee the project’s development. The feasibility study demonstrated a strong NPV of $622 million and an IRR of 24%. Construction is set to begin this month, targeting commercial production in the second half of 2024.
- Construction decision for the Tocantinzinho Gold Project approved.
- Received extension for key installation licenses.
- $136 million committed towards project costs (29% of total).
- Detailed engineering is 30% complete.
- Early works completed on time and budget.
- Appointment of experienced key personnel to manage the project.
- None.
- Positive construction decision approved by the Board of Directors on Tocantinzinho Gold Project
- Extension to key installation licenses received
- Advancing procurement and commitments for long lead items, with
$136 million committed to date (29% of total) in line with budget, with detailed engineering30% complete - Early works activities completed on time and on budget with no lost time incident
- Appointment of Mathieu Gignac as Project Director, Julie-Anaïs Debreil as Vice-President Geology & Resources, and Eduardo Leão as Sustainability Manager
BROSSARD, QC / ACCESSWIRE / September 12, 2022 / G Mining Ventures Corp. ("GMIN" or the "Corporation") (TSXV:GMIN) (OTCQX:GMINF) is pleased to announce that its Board of Directors has made a formal decision to proceed with the construction of the Tocantinzinho Gold Project ("TZ" or the "Project"). Additionally, GMIN is pleased to provide an update on developments on the Project, including the receipt of essential installation license extensions, recruitment, engineering, procurement, early works activities, and the appointment of additional key personnel.
Louis-Pierre Gignac, President & Chief Executive Officer, commented: "GMIN was reorganized in October 2020 with the objective of building the next intermediate gold producer. In less than two years, the management team acquired a great project in TZ, released an updated Feasibility Study in February 2022, and completed a
"The updated feasibility study from February 2022 incorporated many of inflationary pressures seen in the industry, while still demonstrating very positive results of NPV
Louis Gignac Sr., Chairman of the Board of Directors of GMIN, commented: "The Board of Directors' formal decision to begin construction on TZ reflects our confidence in the significant value that the Project can bring to stakeholders in the State of Pará and all GMIN shareholders. The Board also extends its gratitude to GMIN's established supportive shareholders as well as the new shareholders established through its recently completed financing package, with whom we are fully aligned to grow GMIN into the next intermediate gold producer, using TZ as the foundational asset."
Tocantinzinho Feasibility Study Economic Highlights
The following table sets out the economic highlights from the February 2022 Tocantinzinho feasibility study:
Description | Units | GMIN 2022 FS |
Production Data (Operations Period) | ||
Mine Life | years | 10.5 |
Average Milling Throughput | tpd | 12,587 |
Average Milling Throughput | MMt / year | 4.6 |
Strip Ratio | waste : ore | 3.4 |
Pre-Strip Tonnage | Mt | 17.1 |
Total Tonnage (exclusive of pre-strip) | Mt | 194.9 |
Ore Tonnage Milled | Mt | 48.3 |
Gold Head Grade | g/t | 1.31 |
Contained Gold | koz | 2,036 |
Recovery | % | |
Total Gold Production | koz | 1,834 |
Average Annual Gold Production | koz | 175 |
First Five Full Years | koz | 196 |
Operating Costs (Average LOM) | ||
Mining Cost | USD/t mined | |
Mining Cost | USD/t milled | |
Processing Cost | USD/t milled | |
G&A Cost | USD/t milled | |
Total Site Costs | USD/t milled | |
Total Site Costs | USD/oz | |
Total Operating Costs / Cash Costs | USD/oz | |
AISC | USD/oz | |
Capital Costs | ||
Initial Capital | USD MM | |
Life of Mine Sustaining Capital | USD MM | |
Closure Costs | USD MM | |
Capital Costs before Tax | USD MM | |
Net Taxes Payable | USD MM | |
Total Capital Costs | USD MM | |
Financial Evaluation | ||
Gold Price Assumption | USD/oz | |
USD:BRL FX Assumption | x | 5.20 |
After-Tax NPV | USD MM | |
After-Tax IRR | % | |
Payback | Years |
Note: Please refer to the technical report entitled "Feasibility Study - NI 43‐101 Technical Report, Tocantinzinho Gold Project" dated February 09, 2022 filed on SEDAR under the GMIN issuer profile
ESG and Permitting Update
The Corporation and its Brazilian subsidiary, Brazauro Recursos Minerais S.A. ("Brazauro"), maintain active and constant contact with all relevant environmental and governmental authorities, including the State Secretariat of Environment and Sustainability ("SEMAS"), Instituto Chico Mendes and Biodiversity ("ICMBio"), Equatorial Energia ("Equatorial"), National Agency of Electric Energy ("ANEEL"), National Mining Agency ("ANM"), and the Institute of Colonization and Agrarian Reform ("INCRA").
Environmental Permitting
GMIN has received all the necessary environmental installation permits to progress with full construction, which include:
- Site installation license valid until August 2024
- Forest Suppression Authorization and related fauna and flora permits for the site
- Tubular well drilling and use permit for the temporary camp and construction
- Grant for release of sanitary sewage from the site
- Tubular well permit for permanent camp and aggregate plant
- Licenses for the transmission line, landfill, concrete plant, fuel station and tailings dam are currently valid and being further extended by SEMAS
Site preparation activities at TZ started on August 15th and focused initially on the permanent camp area where full construction is scheduled to commence in September. Our construction activities are supported by Brazauro's environmental team which follows thorough protocols to rescue fauna and flora limiting any potential impact to the local environment and ensuring a stable ecosystem.
Health & Safety
The health and safety of employees, contractors and other stakeholders is at the forefront of the Corporation's values and objectives. A total of 250,580 hours has been worked year to date without any Lost Time Incidents.
Figure 1 - Safety Standdown at TZ
Human Resources
Brazauro has grown to a workforce of 252 employees and contractors. Brazilian employees represent
Additional recruitment job fair days were held in our neighboring communities where we collected almost 200 resumes and conducted over 100 interviews. We now have over 1,000 resumes in the database in our effort to hire locally.
Employee Training
The construction working training programs in collaboration with the National Industrial Training Service ("SENAI") has graduated 24 successful students from its first training camp. The Program's main goal is to contribute to the socio-economic development of the micro-region of Itaituba and the southwestern region of the State of Pará by promoting employment, providing training and possibility to participate in the implementation phase of the TZ Project. The second class started in August 2022.
Social programs for the development of the region proposed in the environmental licenses are being implemented, such as environmental education, training of local labor and support to the development of economic diversification. Other social programs are under development to add even more local value with income generation, education, and other development opportunities.
Figure 2 - Graduates from the First Construction Training Class
Project Development Update
Since the most recent TZ project development update (as detailed in the press release dated July 18, 2022) the Corporation has continued to advance development of the Project on several fronts.
Procurement and Project Expenditures
Procurement to date totals
Project Cost Area | % Committed |
Mining | |
Process Plant | |
Construction Indirects | |
Pre-Prod / Commissioning | |
Owners Costs | |
Infrastructure | |
Surface Operations | |
Water Management | |
Power and Electrical | |
Total Commitments |
22 Major Equipment packages have been awarded including:
- Mechanical:
- Grinding Mills, Crushing Plant, Apron Feeders, Gravity Screens & Concentrators, Flotation Cells, Cyclone, Thickener, and 5 other smaller process plant equipment packages
- Electrical and Instrumentation:
- Mills Motors & VFD, Synchronous Condensers, and Emergency Diesel Generators
- Concrete, Structure, Architecture:
- Concrete Pump Truck, Batch Plant, and Kitchen Structural Steel
- Aggregate Plant
- Domestic & Sewage Treatment Plants
10 Major Contract Packages awarded including:
- Architecture (design, supply, install):
- All prefabricated dormitories for the camp
- Modular Buildings including the Administration Building, Camp Office, Welcome Center, Laundry, and Mill Office
- Earthworks:
- Early Works and Deforestation
- 4 Geotechnical Packages
- Electrical Overhead Distribution Line on site
Additionally, there are 37 Mine Mobile Equipment contracts and 8 External Engineering Services contracts awarded.
Figure 3 - First Cat 6030 Hydraulic Mining Shovel Arriving at Site
Engineering
Detailed engineering is
- All site general arrangement layout is finalized
- Engineering of exploration camp expansion is completed
- Process plant 3D model initialed to a detailed engineering level of accuracy
- Permanent camp detail engineering advanced at
50% - General arrangement drawing for all buildings approved and issued for detailed engineering design
- Water management strategy confirmed, and detail engineering started
Metallurgical Test Work
Test work on comminution, floatation and leaching have been completed to confirm equipment sizing, reagent consumption rates and the metallurgical recovery. Regrind test work has so far been inconclusive due to limited samples of concentrate, and additional follow up test work is planned once in production.
Power Supply
As previously disclosed, Brazil's national grid operator, Operador Nacional do Sistema Elétrico ("ONS"), has confirmed the availability of 22.9 megawatts of power supply requested by GMIN. ONS is the government agency responsible for the coordination and monitoring of electric power generation and transmission facilities connected to Brazil's national grid, where
Construction - Early Works Activities
Exploration camp expansion is ongoing to support initial construction activities. The installation of 10 additional sleepers expanded the capacity to 350 beds. A new water well has been installed. Additional sewage treatment facility has been commissioned. Access road extension and widening, and drainage improvements is ongoing. The freight forwarder logistics base in Moraes Almeida was completed in August and will allow for the consolidation of certain good for delivery to site to optimize cost and schedule.
Figure 4 - Exploration Camp Expansion
Figure 5 - Pit Access Road
Key Management Appointments
GMIN has made several critical management appointments to advance both the TZ project development and corporate activities, including:
Mathieu Gignac, Project Director
Mr. Gignac has more than 20 years of experience in the mining industry. He is President of G Mining Services, providing project management expertise and leadership to mine development projects. He has proven leadership abilities in managing large mining projects through feasibility, construction and operations. He was Operations Manager for Iamgold's Rosebel Gold Mines, Project Director of Newmont Mining Corporation's Merian Project and Project Director of Lundin Gold Inc.'s Fruta del Norte Project. As such, most of his career has been spent operating and building projects similar to TZ's size, scope and environment. He is a member of the Ordre des Ingénieurs du Quebec (OIQ) and the Canadian Institute of Mining, Metallurgy and Petroleum. Mr. Gignac is proficient in English, French and Spanish, and is a McGill University graduate in mining engineering.
Julie-Anaïs Debreil, VP Geology & Resources
Ms. Debreil has more than 15 years of professional geology and research experience in greenfield and brownfields exploration, mine geology, and resource estimation. Ms. Debreil held a senior technical role for Premier Gold Mines Ltd. where she managed exploration projects, mineral resource estimation and production reconciliation. Most recently, Ms. Debreil worked as a senior member of the Geology team with G Mining Services where her responsibilities included NI 43-101 compliant reporting, mineral resource estimation and geological modelling for client properties and due diligences. Ms. Debreil holds a Ph.D. in Geology and a M.Sc. in Volcanology. Ms. Debreil is a member of L'Ordre des Géologues du Québec (OGQ) and the Professional Geoscientists Ontario (PGO).
Eduardo Leão, Sustainability Manager
Mr. Leão has more than 15 years of experience in mining, environmental management, strategic planning, risk, and crisis analysis and project development. He previously served as Director of the National Mining Agency (ANM), Secretary of Economic Development, Mining and Energy of the State of Pará, and Sustainability Manager at Vale. Mr. Leão holds a Master's degree in hydrogeology, MBA in business management from Fundação Dom Cabral, and a postgraduate degree in Water Resources Management and Industrial Environmental Management.
Timetable and Next Steps
Having made the positive construction decision, the Corporation will be focused on the following activities:
- Finalization and results of 10,000-meter exploration and drilling program in Q4-22;
- Completion of detailed engineering through H1-23;
- Issuance of inaugural ESG report in 2023; and
- Expected first gold production in H2-24 with the first year of full production in 2025.
Additionally, the Corporation will be attending key investor conferences in the fall in order to update current shareholders and prospective investors on the progress being made at TZ, including:
- Precious Metals Summit, Beaver Creek, Colorado (Sept 13-16)
- OTC Metals & Mining Conference, Virtual (Oct 18-20)
- Swiss Mining Institute Conference, Virtual (Nov 8-10)
- Precious Metals Summit, Zurich (Nov 14-15)
- Deutsche Goldmesse, Frankfurt (Nov 18-19)
- Mines and Money, London (Nov 29-Dec 1)
Please reach out should you wish to schedule a meeting with GMIN at any of the conferences.
Feasibility Study 3D VRIFY Presentation
To view a 3D VRIFY presentation of the Study please click on the following link: Feasibility Study 3D VRIFY Presentation, or visit the Corporation's website at www.gminingventures.com.
About G Mining Ventures Corp.
G Mining Ventures Corp. (TSXV:GMIN) (OTCQX:GMINF) is a mineral exploration company engaged in the acquisition, exploration and development of precious metal projects, to capitalize on the value uplift from successful mine development. GMIN is well-positioned to grow into the next mid-tier precious metals producer by leveraging strong access to capital and proven development expertise. GMIN is currently anchored by its flagship Tocantinzinho Project in mining friendly and prospective State of Pará, Brazil.
Additional Information
For further information on GMIN, please visit the website at www.gminingventures.com or contact:
Jessie Liu-Ernsting
Director, Investor Relations and Communications
647.728.4176
info@gminingventures.com
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.
Cautionary Statement on Forward-Looking Information
All statements, other than statements of historical fact, contained in this press release constitute "forward-looking information" and "forward-looking statements" within the meaning of certain securities laws and are based on expectations and projections as of the date of this press release. Forward-looking statements contained in this press release include, without limitation, those related to (i) the de-risking of the technical, permitting and funding aspects, (ii) the Project proving itself as a robust and responsible opportunity, (iii) the management team having the qualifications and relevant experience to advance TZ as contemplated, (iv) the economic highlights set out in the above table (extracted from the February 2022 feasibility study), (v) the construction activities limiting their potential impact on the local environment and ensuring a stable ecosystem, (vi) the Corporation's social programs adding value with income generation, education and other development opportunities, (vii) the eventual power supply arrangements and, more generally, the President & Chief Executive Officer's comments hereinabove as well as the contents of the above sections entitled "Timesheet and Next Steps" and "About G Mining Ventures Corp.".
Forward-looking statements are based on expectations, estimates and projections as of the time of this press release. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by the Corporation as of the time of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. These estimates and assumptions may prove to be incorrect. Such assumptions include, without limitation, those relating to the price of gold and currency exchange rates and those underlying the items listed on the above section entitled "About G Mining Ventures Corp.".
Many of these uncertainties and contingencies can directly or indirectly affect, and could cause, actual results to differ materially from those expressed or implied in any forward-looking statements. There can be no assurance that, notably but without limitation, the Corporation will (i) continue to advance the Project's procurement and commitments in line with budget and to carry the "Buy, Build, Operate" strategy as planned, (ii) carry its next steps as per the above timetable, (iii) bring the Project into commercial production in the second half of 2024, or at all, (iv) advance TZ into one of the largest operating gold mines in Brazil, or (v) use TZ as the foundational asset to grow GMIN into the next intermediate producer, as future events could differ materially from what is currently anticipated by the Corporation.
By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. Forward-looking statements are provided for the purpose of providing information about management's expectations and plans relating to the future. Readers are cautioned not to place undue reliance on these forward-looking statements as a number of important risk factors and future events could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. All of the forward-looking statements made in this press release are qualified by these cautionary statements and those made in the Corporation's other filings with the securities regulators of Canada including, but not limited to, the cautionary statements made in the relevant sections of the Corporation's (i) Annual Information Form dated June 3, 2022, for the financial year ended December 31, 2021, and (ii) Management Discussion & Analysis. The Corporation cautions that the foregoing list of factors that may affect future results is not exhaustive, and new, unforeseeable risks may arise from time to time. The Corporation disclaims any intention or obligation to update or revise any forward-looking statements or to explain any material difference between subsequent actual events and such forward-looking statements, except to the extent required by applicable law.
SOURCE: G Mining Ventures Corp.
View source version on accesswire.com:
https://www.accesswire.com/715468/G-Mining-Ventures-Announces-Formal-Construction-Decision-for-Tocantinzinho-Gold-Project-and-Provides-Project-Development-Update
FAQ
What is the latest update from G Mining Ventures Corp. regarding the Tocantinzinho Gold Project (GMINF)?
How much budget has G Mining Ventures committed to the Tocantinzinho Gold Project (GMINF)?
What are the financial highlights of the Tocantinzinho Gold Project (GMINF) from the feasibility study?