STOCK TITAN

GoGold Provides Update on Ongoing Los Ricos Definitive Feasibility Study

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) has provided an update on its Los Ricos South (LRS) and Los Ricos North (LRN) projects. The company is finalizing a definitive feasibility study (DFS) for LRS, with a significant change from the preliminary economic assessment:

1. The mine plan has been re-engineered into a 12-year underground bulk mine with a 2,000 tonne per day capacity.
2. This approach reduces surface disturbance and eliminates the need for an open pit permit.
3. Metallurgical testing confirms a conventional whole ore leaching process producing silver-gold dore bars and copper precipitate.
4. The company is finalizing a power agreement with CFE and has secured land rights for the mill and processing facilities.
5. GoGold is also working on converting the LRN project to an underground mine plan, with a revised PEA/PFS expected in 2025.

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ha fornito un aggiornamento sui suoi progetti Los Ricos South (LRS) e Los Ricos North (LRN). L'azienda sta finalizzando uno studio di fattibilità definitivo (DFS) per LRS, con un cambiamento significativo rispetto alla valutazione economica preliminare:

1. Il piano minerario è stato riprogettato in un miniera sotterranea bulk di 12 anni con una capacità di 2.000 tonnellate al giorno.
2. Questo approccio riduce il disturbo superficiale ed elimina la necessità di un permesso per una miniera a cielo aperto.
3. I test metallurgici confermano un processo di lavaggio convenzionale dell'intero minerale che produce lingotti di oro e argento e precipitato di rame.
4. L'azienda sta finalizzando un accordo di fornitura di energia con CFE e ha ottenuto i diritti di terra per il mulino e le strutture di lavorazione.
5. GoGold sta inoltre lavorando per convertire il progetto LRN in un piano minerario sotterraneo, con una PEA/PFS revisionata attesa nel 2025.

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ha proporcionado una actualización sobre sus proyectos Los Ricos South (LRS) y Los Ricos North (LRN). La compañía está finalizando un estudio de viabilidad definitivo (DFS) para LRS, con un cambio significativo respecto a la evaluación económica preliminar:

1. El plan minero ha sido reingenierizado en una minería subterránea a granel de 12 años con una capacidad de 2.000 toneladas por día.
2. Este enfoque reduce la alteración de la superficie y elimina la necesidad de un permiso para una mina a cielo abierto.
3. Las pruebas metalúrgicas confirman un proceso de lixiviación de mineral convencional que produce lingotes de oro y plata y precipitado de cobre.
4. La compañía está finalizando un acuerdo de energía con CFE y ha asegurado derechos de tierras para el molino y las instalaciones de procesamiento.
5. GoGold también está trabajando en convertir el proyecto LRN en un plan de minería subterránea, con una PEA/PFS revisada prevista para 2025.

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF)는 Los Ricos South (LRS) 및 Los Ricos North (LRN) 프로젝트에 대한 업데이트를 제공했습니다. 회사는 LRS에 대한 최종 타당성 조사(DFS)를 마무리하고 있으며, 초기 경제 평가에서 중요한 변화가 있었습니다:

1. 채굴 계획이 12년간의 지하 대량 채굴로 재설계되어 하루 2,000톤의 용량을 갖추게 되었습니다.
2. 이 접근법은 표면 교란을 줄이고 노천 채굴 허가의 필요성을 없앱니다.
3. 금속 시험 결과는 전통적인 전체 광석 침출 공정이 은-금 도련과 구리 침전을 생산하는 것을 확인합니다.
4. 회사는 CFE와의 전력 계약을 마무리하고 공장 및 가공 시설을 위한 토지 권리를 확보했습니다.
5. GoGold는 2025년에 개정된 PEA/PFS가 예상되는 LRN 프로젝트를 지하 채광 계획으로 전환하기 위해 노력하고 있습니다.

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) a fourni une mise à jour sur ses projets Los Ricos South (LRS) et Los Ricos North (LRN). L'entreprise finalise une étude de faisabilité définitive (DFS) pour LRS, avec un changement significatif par rapport à l'évaluation économique préliminaire :

1. Le plan minier a été repensé en une mine souterraine massive de 12 ans avec une capacité de 2 000 tonnes par jour.
2. Cette approche réduit la perturbation de la surface et élimine le besoin d'un permis pour une mine à ciel ouvert.
3. Les tests métallurgiques confirment un processus de lixiviation conventionnel de l'ensemble du minerai produisant des lingots d'argent-or et un précipité de cuivre.
4. L'entreprise finalise un accord d'approvisionnement en électricité avec CFE et a sécurisé des droits fonciers pour l'usine et les installations de traitement.
5. GoGold travaille également à la conversion du projet LRN en un plan de mine souterraine, avec une PEA/PFS révisée prévue pour 2025.

GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) hat ein Update zu seinen Projekten Los Ricos South (LRS) und Los Ricos North (LRN) bereitgestellt. Das Unternehmen schließt derzeit eine abschließende Machbarkeitsstudie (DFS) für LRS ab, mit einer signifikanten Änderung im Vergleich zur vorläufigen Wirtschaftlichkeitsbewertung:

1. Der Bergbauplan wurde in eine 12-jährige unterirdische Großbergbau mit einer Kapazität von 2.000 Tonnen pro Tag umgestaltet.
2. Dieser Ansatz reduziert Störungen an der Oberfläche und beseitigt die Notwendigkeit für eine Tagebauerlaubnis.
3. Metallurgische Tests bestätigen ein konventionelles Gesamterz-Auslaugungsverfahren, das Silber-Gold-Dorebarren und Kupfer-Niederschlag produziert.
4. Das Unternehmen schließt derzeit eine Energievereinbarung mit CFE ab und hat Landrechte für die Mühle und die Verarbeitungseinrichtungen gesichert.
5. GoGold arbeitet auch daran, das LRN-Projekt in einen unterirdischen Bergbauplan umzuwandeln, wobei eine überarbeitete PEA/PFS für 2025 erwartet wird.

Positive
  • Re-engineered LRS mine plan for 12 years of underground mining at 2,000 tonnes per day
  • Underground mining approach reduces surface disturbance and avoids open pit permit requirements
  • Metallurgical testing confirms viable process for producing silver-gold dore bars and copper precipitate
  • Secured land rights for mill and processing facilities
  • Finalizing power agreement with CFE for adequate supply from nearby hydroelectric dam
  • Process mill design work is 90% complete
Negative
  • Potential delay in project development due to re-engineering of mine plan
  • Possible increased costs associated with underground mining compared to open pit operations

Shares Outstanding: 329,527,261
 Trading Symbols: TSX: GGD
OTCQX: GLGDF 

HALIFAX, NS, Sept. 10, 2024 /PRNewswire/ - GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ("GoGold", "the Company") is pleased to provide an update on the activities related to their Los Ricos South ("LRS") and Los Ricos North ("LRN") projects.  The Company is in the final phases of completing a definitive feasibility study ("DFS") for LRS.  The most significant change from the LRS preliminary economic assessment to the DFS is a reworking of the mine plan with a focus on underground mining. The mine plan has now been re-engineered into an underground mine life for 12 years of mining.

"In the DFS, the Company has opted for an underground bulk mine taking advantage of the large widths of mineralization within the deposit. We have been able to re-engineer a 2,000 tonne per day mine plan for at least 12 years of underground mining using the longitudinal sub-level long-hole mining method," said Brad Langille, President and CEO.  "The advantages of re-engineering the mine for the first 12 years as an underground-only mine are a reduced surface disturbance and no requirement for an open pit permit.  There has been no controversy regarding underground mine permits in Mexico, while open pit permits are currently the subject of potential constitutional amendments.  Our geological team have now turned their attention to remodeling the LRN deposit as an underground mine as well.  We believe LRN has the potential and opportunity to engineer the deposit as an underground mine without the need for open pit permits."

The LRS DFS is nearing completion with many key components of the study currently completed.  The underground mining will be completed through contract mining.  Management will develop a mine services team to manage contractors for the project.

Metallurgy

In support of the feasibility study on the Los Ricos South deposits, an extensive metallurgical test program was completed at SGS Lakefield on representative drill core from the deposit. The program was designed to test and validate the key components of the process to confirm plant performance including:

-          Crushing and grinding
-          Thickening and filtration
-          Cyanide leaching and reagent consumptions
-          SART (sulfidation, acidification, re-neutralization and thickening) performance
-          Merrill Crowe (zinc precipitation)
-          Dry-stack tailings detoxification and dewatering (maximizing water recovery)

Based on the extensive program, and life of mine mill simulation, the plant will use a conventional whole ore leaching process with a simplistic flow sheet and will produce silver-gold dore bars and a copper precipitate.

Dewatered and detoxified tailings were tested at Paterson and Cook in Sudbury, Ontario to determine the paste backfill recipe (cement addition rate) for the underground mine and minimize process water usage.  The advantages of underground paste backfill are both maximum stability of the mine and the majority of the mine tailings will be placed as cemented paste underground reducing surface impact.

LRS Power and Land Rights

The Company is finalizing an agreement with the Comision Federal de Electricidad ("CFE"), to secure an adequate power supply for LRS.  Electricity for the project sourced from the nearby La Yesca hydroelectric dam.

Figure 1 - La Yesca Dam (CNW Group/GoGold Resources Inc.)

The Company has also secured the rights to the land where the mill and processing for LRS will be located.  Agreements were entered into with multiple farmers and stakeholders providing compensation for the usage of the required land.

Mill Design

The process mill design work is nearing completion, with design and engineering work 90% complete currently.  Similar to the PEA design, the process plant is comprised of conventional crushing and grinding followed by cyanide tank leaching. Back-end filtration is required to maximize water recycling (dry stack tailings) as well as a SART (sulfidation, acidification re-neutralization and thickening) circuit to re-generate cyanide back to the process and to produce a saleable copper sulfide product.  The mill will produce saleable silver-gold dore bars.

Figure 2 - Mill Design (CNW Group/GoGold Resources Inc.)

Los Ricos North

GoGold's geological team has began relogging drill holes and data at LRN with a focus on converting the 2023 LRN PEA mine plan for the deposits which was designed as an open-pit mine into and underground mine plan similar to LRS.   Management is working towards a revised PEA / PFS to be released in 2025.

About GoGold Resources

GoGold Resources (TSX: GGD) is a Canadian-based silver and gold producer focused on operating, developing, exploring and acquiring high quality projects in Mexico.  The Company operates the Parral Tailings mine in the state of Chihuahua and has the Los Ricos South and Los Ricos North projects in the state of Jalisco. Headquartered in Halifax, NS, GoGold is building a portfolio of low cost, high margin projects. For more information visit gogoldresources.com.

CAUTIONARY STATEMENT:

The securities described herein have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the "U.S. Securities Act"), or any state securities laws, and may not be offered or sold within the United States or to, or for the benefit of, U.S. persons (as defined in Regulation S under the U.S. Securities Act) except in compliance with the registration requirements of the U.S. Securities Act and applicable state securities laws or pursuant to exemptions therefrom. This release does not constitute an offer to sell or a solicitation of an offer to buy of any of GoGold's securities in the United States.

This news release may contain "forward-looking information" as defined in applicable Canadian securities legislation. All statements other than statements of historical fact, included in this release, including, without limitation, statements regarding the Parral tailings project, the Los Ricos project, future operating margins, future production and processing, and future plans and objectives of GoGold, constitute forward looking information that involve various risks and uncertainties. Forward-looking information is based on a number of factors and assumptions which have been used to develop such information but which may prove to be incorrect, including, but not limited to, assumptions in connection with the continuance of GoGold and its subsidiaries as a going concern, general economic and market conditions, mineral prices, the accuracy of mineral resource estimates, and the performance of the Parral project There can be no assurance that such information will prove to be accurate and actual results and future events could differ materially from those anticipated in such forward-looking information.

Important factors that could cause actual results to differ materially from GoGold's expectations include exploration and development risks associated with the GoGold's projects, the failure to establish estimated mineral resources or mineral reserves, volatility of commodity prices, variations of recovery rates, and global economic conditions. For additional information with respect to risk factors applicable to GoGold, reference should be made to GoGold's continuous disclosure materials filed from time to time with securities regulators, including, but not limited to, GoGold's Annual Information Form. The forward-looking information contained in this release is made as of the date of this release.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/gogold-provides-update-on-ongoing-los-ricos-definitive-feasibility-study-302243242.html

SOURCE GoGold Resources Inc.

FAQ

What is the new mine plan for GoGold's Los Ricos South project (GLGDF)?

GoGold has re-engineered the Los Ricos South project into a 12-year underground bulk mine with a capacity of 2,000 tonnes per day, using the longitudinal sub-level long-hole mining method.

What are the advantages of GoGold's new underground mine plan for Los Ricos South (GLGDF)?

The advantages include reduced surface disturbance and no requirement for an open pit permit, which is currently subject to potential constitutional amendments in Mexico.

What is the status of GoGold's Los Ricos South definitive feasibility study (GLGDF)?

The definitive feasibility study (DFS) for Los Ricos South is nearing completion, with many key components already finished, including metallurgical testing and 90% completion of process mill design work.

What type of processing will GoGold use for the Los Ricos South project (GLGDF)?

GoGold will use a conventional whole ore leaching process with a simplistic flow sheet, producing silver-gold dore bars and a copper precipitate.

What are GoGold's plans for the Los Ricos North project (GLGDF)?

GoGold is working on converting the Los Ricos North project from an open-pit to an underground mine plan, similar to Los Ricos South. A revised PEA/PFS is expected to be released in 2025.

GOGOLD RESOURCES INC ORD

OTC:GLGDF

GLGDF Rankings

GLGDF Latest News

GLGDF Stock Data

280.58M
304.31M
6.41%
28.8%
Other Precious Metals & Mining
Basic Materials
Link
United States of America
Halifax