E3 Lithium Executes Contribution Agreement Underpinning up to $36.5 million in Federal Support to Accelerate Clearwater Project
The execution of the contribution agreement confirms
As previously announced on March 2, 2026, the Funding will support
“Canada is building strong domestic critical minerals value chains, and that means investing at the stages that matter most in getting projects over the line. Through the Global Partnerships Initiative, we are supporting the engineering, demonstration and feasibility work needed for E3 Lithium’s Clearwater Project to reach final investment decision. This is how we move faster, reduce risk and ensure sustainable, sovereign Canadian lithium can power our economy at home and supply our allies abroad,” said the Honourable Tim Hodgson, Minister of Energy and Natural Resources.
“E3 began ramping up the aspects of this project beginning in April this year, upon conditional approval of the funding,” commented Chris Doornbos, CEO & Chair of E3 Lithium. “With the execution of the contribution agreement, E3 is now fully executing towards some of the biggest technical milestones we have in front of us, aiming to significantly derisk our Clearwater Project ahead of the final investment decision. We appreciate the Government of Canada’s support in advancing a domestic lithium supply chain and strengthening Canada’s position in the global critical minerals market.”
The Funding provided through the GPI will also support
The two key project-based components supported by the Funding include:
1. Completion of the Demonstration Facility Phase 3
With the execution of the contribution agreement, E3 has commenced equipment orders required to complete the third and final phase of the Demonstration Facility. Phase 3 includes operation of the previously commissioned 30-column Direct Lithium Extraction (“DLE”) and purification/carbonation skids, along with the construction and operation of a commercial size, single DLE column (the “Single Commercial Column”). Phase 3 of the Demonstration Facility will enable the operation of E3’s DLE process at full commercial scale, further validating process performance, reliability, and scalability of the technology. In addition, the Company expects to have increased production volumes of battery-grade lithium carbonate, which will enable E3 to continue progressing product qualification with offtake partners and evaluate commercial battery supply chain value opportunities. The successful completion of Phase 3 of the Demonstration Facility is a major derisking milestone for the Company and will be a critical component in the evaluation of the Clearwater Project by potential strategic and offtake partners, project financers, and any potential additional government support.
E3’s goals for Phase 3 of the Demonstration Facility include:
- Construction of Phase 3, the Single Commercial Column, through the second half of 2026 with ongoing operations throughout the year
-
Demonstrating lithium recovery of greater than
85% through the Single Commercial Column, a milestone that supports project economics - Production of the lithium chloride at an equivalent rate of up to 100 tonnes of lithium carbonate per year
- Continual validation of product quality by pre-qualifying the lithium chloride and/or lithium carbonate to potential customers at an increased scale
2. Completion of the Feasibility Study
The GPI funding will support E3’s completion of the Clearwater Project Feasibility Study, targeting 12,000 tonnes per year of battery-grade lithium carbonate in Stage 1. The internal and external engineering deliverables will be directly supported through the GPI funding. The engineering scope will include the final designs for the reservoir development, gas-handling system, lithium extraction and purification, and lithium carbonatation. While Phase 3 of the Demonstration Facility aims to support process validation and readiness for project financing, the Feasibility Study and related engineering represent the Company’s final major technical milestones prior to detailed engineering and advancement toward a Final Investment Decision (“FID”).
E3’s goals for the Feasibility Study and related engineering include:
- Completion of Front-End Engineering Design (“FEED”) of the Clearwater Stage 1
- Completion of the Feasibility Study and Class III cost estimate, aiming for Q1 2027
- Readiness to begin ordering long-lead equipment for the commercial facility
The Company has retained Sedgman, a CIMIC Group Company and globally recognized engineering firm, to lead the FEED for the Clearwater Project. Sedgman’s expertise in process plant design and project execution is expected to support advancement of the Clearwater Project toward final engineering, cost estimation, and FID. Sedgman is currently involved in the engineering and delivery of other advanced lithium processing facilities incorporating DLE technologies, including projects progressing toward commercial-scale implementation.
ON BEHALF OF THE BOARD OF DIRECTORS
Chris Doornbos, CEO & Chair
E3 Lithium Ltd.
About E3 Lithium
E3 Lithium is a development company with a total of 21.2 million tonnes of lithium carbonate equivalent (LCE) Measured and Indicated1 as well as 0.3 Mt LCE Inferred mineral resources2 in Alberta. The Clearwater Pre-Feasibility Study outlined a 1.13 Mt LCE proven and probable mineral reserve with a pre-tax NPV(
1: The Clearwater Project NI 43-101 Pre-Feasibility Study, effective June 20, 2024, identified 16.2 Mt LCE (measured and indicated) and is available on the E3 Lithium’s website (www.e3lithium.ca/technical-reports/) and SEDAR+ (www.sedarplus.ca).
2: The mineral resource NI 43-101 Technical Report for the Garrington District Lithium Resource Estimate, effective June 25, 2025, identified 5.0 Mt LCE (measured and indicated) and 0.3 Mt LCE (inferred) and is available on the E3 Lithium’s website (www.e3lithium.ca/technical-reports/) and SEDAR+ (www.sedarplus.ca).
Unless otherwise indicated, Chris Doornbos, P. Geo., Chief Executive Officer and a Qualified Person under National Instrument 43-101, has reviewed and approved the technical information contained on this news release.
Forward-Looking and Cautionary Statements
This news release includes certain forward-looking statements as well as management’s objectives, strategies, beliefs and intentions or forward-looking information within the meaning of applicable securities laws. Forward-looking statements are frequently identified by such words as “believe”, “may”, “will”, “plan”, “expect”, “anticipate”, “estimate”, “intend”, “project”, “potential”, “possible” and similar words referring to future events and results. Forward-looking statements are based on the current opinions, expectations, estimates and assumptions of management in light of its experience, perception of historical trends, and results of the PFS, but such statements are not guarantees of future performance. In particular, this news release contains forward-looking information relating to: E3 accelerating and expanding the scope of the Demonstration Facility that will enable the Company to build and operate its third phase; Funding supporting the Company's FEED and supporting hiring of additional 25 full time positions; Funding enabling the ongoing production of battery-grade lithium carbonate at an increased scale, de-risking E3’s Direct Lithium Extraction (DLE) technology on a 1:1 scale commercial column and finalizing Clearwater Project engineering to enable FID; Demonstrating lithium recovery of greater than
All forward-looking information (including future-orientated financial information) is inherently uncertain and subject to a variety of assumptions, risks and uncertainties, including the speculative nature of mineral exploration and development, fluctuating commodity prices, the effectiveness and feasibility of emerging lithium extraction technologies which have not yet been tested or proven on a commercial scale or on the Company’s brine, risks related to the availability of financing on commercially reasonable terms and the expected use of proceeds; operations and contractual obligations; changes in estimated mineral reserves or mineral resources; future prices of lithium and other metals; availability of third party contractors; availability of equipment; failure of equipment to operate as anticipated; accidents, effects of weather and other natural phenomena and other risks associated with the mineral exploration industry; the Company’s lack of operating revenues; currency fluctuations; risks related to dependence on key personnel; estimates used in financial statements proving to be incorrect; competitive risks and the availability of financing, as described in more detail in our recent securities filings available under the Company’s profile on SEDAR+ (www.sedarplus.ca). Actual events or results may differ materially from those projected in the forward-looking statements and we caution against placing undue reliance thereon. We assume no obligation to revise or update these forward-looking statements except as required by applicable law.
View source version on businesswire.com: https://www.businesswire.com/news/home/20260610554047/en/
E3 Lithium - Investor Relations
investor@e3lithium.ca
587-324-2775
E3 Lithium - Media Inquiries
communications@e3lithium.ca
587-324-2775
Source: E3 Lithium Ltd.