Dolly Varden Silver's 120 Meter Step-Out at the Wolf Vein Intersects 379 g/t Silver over 21.69 Meters, Including: 1,804 g/t Silver over 1.67 Meters
Dolly Varden Silver (DOLLF) has announced significant drilling results from the Wolf Vein, with drill hole DV24-421 intersecting 379 g/t Ag, 0.64% Pb and 0.66% Zn over 21.69 meters in a 120-meter step-out. The mineralization zone remains open for expansion as it plunges southwest.
Key highlights include multiple high-grade intersections:
- DV24-406: 465 g/t Ag over 7.67 meters
- DV24-413: 374 g/t Ag over 9.70 meters
- DV24-415: 357 g/t Ag over 9.17 meters
The 2024 exploration program was expanded from 25,000m to 32,000m at the Kitsault Valley Project. The Wolf Vein plunge extent has been expanded to over 1,100 meters. The company completed 22 drill holes totaling 9,731 meters at Wolf Vein, with this release covering the final 13 holes.
Dolly Varden Silver (DOLLF) ha annunciato risultati significativi di perforazione dalla Vene Wolf, con il foro di perforazione DV24-421 che ha intersecato 379 g/t Ag, 0.64% Pb e 0.66% Zn su 21.69 metri in un passo di 120 metri. La zona di mineralizzazione rimane aperta per espansione mentre si inclina a sudovest.
I punti salienti includono molteplici intersezioni ad alta grade:
- DV24-406: 465 g/t Ag su 7.67 metri
- DV24-413: 374 g/t Ag su 9.70 metri
- DV24-415: 357 g/t Ag su 9.17 metri
Il programma di esplorazione del 2024 è stato ampliato da 25.000m a 32.000m nel progetto Kitsault Valley. L'estensione della caduta della Vene Wolf è stata ampliata a oltre 1.100 metri. La società ha completato 22 fori di perforazione per un totale di 9.731 metri nella Vene Wolf, con questo comunicato che copre gli ultimi 13 fori.
Dolly Varden Silver (DOLLF) ha anunciado resultados significativos de perforación en la veta Wolf, con el pozo de perforación DV24-421 intersectando 379 g/t Ag, 0.64% Pb y 0.66% Zn en 21.69 metros en un paso de 120 metros. La zona de mineralización permanece abierta para expansión mientras se inclina hacia el suroeste.
Los puntos clave incluyen múltiples intersecciones de alta ley:
- DV24-406: 465 g/t Ag en 7.67 metros
- DV24-413: 374 g/t Ag en 9.70 metros
- DV24-415: 357 g/t Ag en 9.17 metros
El programa de exploración de 2024 se ha ampliado de 25,000m a 32,000m en el proyecto Kitsault Valley. La extensión de la inclinación de la veta Wolf se ha ampliado a más de 1,100 metros. La compañía completó 22 pozos de perforación totalizando 9,731 metros en la veta Wolf, con este comunicado cubriendo los últimos 13 pozos.
돌리 바든 실버(DOLLF)는 울프 베인에서의 중요한 시추 결과를 발표했으며, 시추 구멍 DV24-421이 379 g/t Ag, 0.64% Pb 및 0.66% Zn을 21.69미터에서 교차했습니다. 120미터의 확장에서 시추되었습니다. 광물화 구역은 남서쪽으로 탐색이 가능하게 남아 있습니다.
주요 하이라이트로는 여러 개의 고품위 교차점이 포함됩니다:
- DV24-406: 465 g/t Ag를 7.67미터에서
- DV24-413: 374 g/t Ag를 9.70미터에서
- DV24-415: 357 g/t Ag를 9.17미터에서
2024년 탐사 프로그램은 키솔트 밸리 프로젝트에서 25,000m에서 32,000m로 확대되었습니다. 울프 베인의 경사가 1,100미터 이상으로 확장되었습니다. 회사는 울프 베인에서 총 9,731미터의 22개의 시추 구멍을 완성했으며, 이 릴리스는 마지막 13개의 구멍을 포함하고 있습니다.
Dolly Varden Silver (DOLLF) a annoncé des résultats de forage significatifs de la veine Wolf, avec le trou de forage DV24-421 intersectant 379 g/t Ag, 0.64% Pb et 0.66% Zn sur 21.69 mètres dans une extension de 120 mètres. La zone de minéralisation reste ouverte à l'expansion alors qu'elle plonge vers le sud-ouest.
Les points forts incluent plusieurs intersections de haute teneur:
- DV24-406: 465 g/t Ag sur 7.67 mètres
- DV24-413: 374 g/t Ag sur 9.70 mètres
- DV24-415: 357 g/t Ag sur 9.17 mètres
Le programme d'exploration 2024 a été élargi de 25,000m à 32,000m dans le projet de Kitsault Valley. L'extension de la pente de la veine Wolf a été élargie à plus de 1,100 mètres. L'entreprise a complété 22 trous de forage totalisant 9,731 mètres dans la veine Wolf, ce communiqué couvrant les 13 derniers trous.
Dolly Varden Silver (DOLLF) hat bedeutende Bohrergebnisse aus der Wolf-Ader bekannt gegeben, wobei das Bohrloch DV24-421 379 g/t Ag, 0.64% Pb und 0.66% Zn über 21.69 Meter in einem 120-Meter-Schritt getroffen hat. Die Mineralisierungszone bleibt erweiterbar, während sie nach Südwesten geneigt ist.
Wichtige Höhepunkte sind mehrere hochgradige Schnittstellen:
- DV24-406: 465 g/t Ag über 7.67 Meter
- DV24-413: 374 g/t Ag über 9.70 Meter
- DV24-415: 357 g/t Ag über 9.17 Meter
Das Explorationsprogramm 2024 wurde von 25.000 m auf 32.000 m im Kitsault Valley-Projekt erweitert. Die Neigung der Wolf-Ader wurde auf über 1.100 Meter ausgedehnt. Das Unternehmen hat 22 Bohrlöcher mit einer Gesamtlänge von 9.731 Metern in der Wolf-Ader abgeschlossen, wobei diese Veröffentlichung die letzten 13 Löcher abdeckt.
- Significant high-grade silver intersection of 379 g/t Ag over 21.69m in step-out drilling
- Successful expansion of Wolf Vein plunge extent to over 1,100 meters
- Drilling program expanded from 25,000m to 32,000m indicating positive results
- Mineralization zone remains open for expansion
- None.
Vancouver, British Columbia--(Newsfile Corp. - January 7, 2025) - Dolly Varden Silver Corporation (TSXV: DV) (OTCQX: DOLLF) (FSE: DVQ1) (the "Company" or "Dolly Varden") is pleased to announce infill, step-out and resource expansion drilling results from the Wolf Vein. Drill hole DV24-421 is a significant 120 meter step-out down the plunge of the high grade silver zone and intersected 379 g/t Ag,
DV24-421 is the southernmost hole completed to date; results have delivered consistent wide, potentially underground bulk-mineable intervals. These include recently reported step-out results completed during the 2024 season, including previously released: DV24-416, intersecting and 654 g/t Ag /
Additionally, included in this release are results from follow-up exploration drilling from multiple prospects on the Dolly Varden Project Area. The Company's successful 2024 exploration drill program at the Kitsault Valley Project was expanded to 32,000 m from the initial planned 25,000 m.
Wolf Vein Drilling
Highlights include:
- DV24-421 - 120m step-out: 379g/t Ag,
0.64% Pb and0.66% Zn over 21.69 meters, including 1,804 g/t Ag,4.36% Pb and3.10% Zn over 1.67 meters.
- DV24-406 - infill: 465 g/t Ag,
0.49% Pb and0.22% Zn over 7.67 meters, including 1,416 g/t Ag,1.56% Pb and0.51% Zn with 0.24 g/t Au over 1.00 meters.
- DV24-413 - lower extension: 374g/t Ag,
0.54% Pb and0.82% Zn over 9.70 meters, including 975 g/t Ag,0.36% Pb and2.28% Zn over 2.30 meters. Individual Pb/Zn veins in the footwall to the main Wolf Vein graded 130 g/t Ag,2.48% Pb,14.65% Zn over a length of 2.07 meters.
- DV24-415 - upper extension: 357 g/t Ag,
0.52% Pb and0.41% Zn over 9.17 meters, including 2,034 g/t Ag,3.47% Pb and0.18% Zn over 1.15 meters.
* intervals shown are core length. Estimated true widths vary depending on intersection angles and range from
"Following our recently released, high-grade results from the Homestake Silver Deposit, these step-out drilling results from the Wolf Vein demonstrate the exceptional growth potential from the multiple deposits and exploration prospects that comprise the Kitsault Valley Project, "said Shawn Khunkhun, CEO of Dolly Varden Silver. "At Wolf, we continue to expand the extent of strong mineralization, veining and alteration as we get closer to the Torbrit Silver deposit, located 1,000 meters to the south."
This release includes the final 13 holes of the total 22 drill holes (9,731 meters) completed at the Wolf Vein in the 2024. Six of the drill holes from this release are from the Wolf directional drilling program (Table 3). Directional drilling technology was used to precisely target areas for vertical extension and infill of the high-grade silver mineralized plunge.
Additionally, the final 17 of the total 19 drill holes (5,815 meters) from several other prospects on the Dolly Varden portion of the Kitsault Valley Project are reported in this release (Table 4).
Figure 1. Longitudinal Section of Wolf Vein looking west, with mineralization envelope in red. Plunge of high-grade silver mineralization has been extended over 180 meters from 2023 limit (shown in red) and expanded vertically over 100m vertical extent with 2024 step out holes. Drill holes from this release shown with white halo on Hole ID label.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_002full.jpg
Wolf Drilling
The 2024 drilling program at Wolf was comprised of step-out exploration drilling, extension/definition of the vertical extent of the high-grade silver plunge and infill within areas of wide spaced drilling. Complete results are presented in Table 1.
Drill hole DV24-405 tested the vertical extent and targeted the upper area of high-grade silver plunge mineralization, intersecting the Wolf Main Zone with 12.58 meters averaging 227 g/t Ag /
Drill hole DV24-406 is an infill hole, intersecting mineralization approximately 45m below previously reported Wolf Extension discovery hole DV21-273 and 70m above previously released DV24-402. This hole intersected the Wolf Vein grading 465 g/t Ag /
Drill hole DV24-407 tested a potentially parallel, deep zone approximately 33 meters east of drill hole DV22-311, intersecting the structure and associated alteration with a vein grading 202 g/t Ag over 1.53m along with elevated zinc grades, which was also encountered in adjacent drill holes.
Drill hole DV24-411 tested the vertical extent and targeted the upper area of the high-grade silver plunge and intersected the Wolf structure and associated alteration further up-dip. Vein style mineralization was intersected over 1.08 meters, grading 332 g/t Ag with high base metal grades of
Drill hole DV24-413 was drilled to test the down-dip extent of the high-grade plunge, approximately 50 meters from DV24-410 (previously reported) and below DV24-405 (reported above). The hole encountered 25.00m of
Drill holes DV24-417, 418 tested the down-dip extent of the silver mineralization, intersecting the Wolf structure below the wider plunge but still showing intervals with strong zinc values over narrower intervals.
Drill holes DV24-419, 420 tested for extensions to previously released drill hole DV22-329, which intersected 24,997 g/t Ag,
Drill hole DV24-421 is a 120m step-out to the south along the plunge of the high-grade silver zone (75 meters along strike) from previously released drill hole DV24-409. This hole was drilled towards the west from the Wolf access road that connects the historic Torbrit Mine to the Wolf exploration adits, intersecting 379g/t Ag,
Drill holes DV24-425, 426 filled a gap above the projected silver mineralization, testing for a connection between the Wolf Vein and of the Wolf Extension below the sediment cap. The potassic alteration with zinc halo within the host structure was observed in drill core, with narrow silver-bearing veins along with anomalous base metal signature.
Figure 2. Plan of Wolf Vein mineralized zone (in red) highlighting 2024 drilling with lithology shown on drill trace- grey: sedimentary rock, green: volcanic rock, pink/red: mineralization. Drill holes reported in this release are shown with white halo on Hole ID label. Step-out drill hole DV24-421 was collared from the Wolf Access Road.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_003full.jpg
Wolf Vein
The Wolf Vein is hosted in Jurassic-age Hazelton Formation volcanic rocks and is interpreted as a structurally controlled, multi phased, epithermal vein and vein breccias that occur along a southwest plunging zone of high grade silver mineralization. Native silver, pyargerite, argentite and argentiferous galena are hosted in multiple phases of silica and iron carbonate veins and breccias. The extention of the mineralization, discovered underneath the sedimentary rock cap to the south west of the outcropping Wolf Vein has a plunge extent of over 1,100 meters at approximately -45° to the southwest.
Figure 3. Drill core of Wolf Vein and Vein Breccia in DV24-421, showing interval 762m to 767m with multiple veining events and low pressure textures. Mineralization includes: argentiferous galena, honey sphalerite, pyrite and native silver, part of sample grading 1,804 g/t Ag,
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_004full.jpg
Table 1: Completed Assays from 2024 Wolf Vein Drilling
Hole ID | From (m) | To (m) | Length (m)* | Ag (g/t) | Pb (%) | Zn (%) | Au (g/t) |
DV24-405 | 635.00 | 677.36 | 42.36 | 131 | 0.15 | 0.12 | |
Main Vein | 635.00 | 647.58 | 12.58 | 227 | 0.38 | 0.12 | |
including | 651.08 | 652.08 | 1.00 | 953 | 0.06 | 0.09 | |
and | 657.26 | 658.11 | 0.85 | 536 | 0.16 | 0.11 | |
DV24-406 | 363.03 | 370.70 | 7.67 | 465 | 0.49 | 0.22 | |
including | 363.76 | 368.26 | 4.50 | 744 | 0.77 | 0.25 | 0.13 |
including | 364.26 | 365.26 | 1.00 | 1,416 | 1.56 | 0.51 | 0.24 |
DV24-407 | 672.68 | 678.30 | 5.62 | 35 | 0.44 | 0.40 | |
Deep Vein | 706.28 | 709.15 | 2.87 | 189 | 0.25 | 1.11 | |
including | 707.07 | 708.60 | 1.53 | 303 | 0.27 | 1.21 | |
DV24-411 | 522.12 | 523.20 | 1.08 | 332 | 1.24 | 3.29 | |
DV24-413 | 698.35 | 699.49 | 1.14 | 337 | 7.11 | 5.34 | |
Entire Zone | 734.46 | 757.28 | 22.82 | 198 | 2.42 | 1.92 | |
Main Vein | 734.46 | 744.16 | 9.70 | 374 | 0.54 | 0.82 | |
including | 734.96 | 737.26 | 2.30 | 975 | 0.36 | 2.28 | |
including | 734.96 | 735.46 | 0.50 | 1,685 | 0.91 | 9.92 | |
including | 736.52 | 737.26 | 0.74 | 1,045 | 0.35 | 0.13 | 0.13 |
Pb/Zn Veins | 746.70 | 748.77 | 2.07 | 130 | 2.48 | 14.65 | 0.11 |
Pb/Zn Veins | 746.70 | 747.20 | 0.50 | 179 | 4.82 | 30.00 | 0.10 |
Pb/Zn Veins | 751.66 | 753.16 | 1.50 | 126 | 11.14 | 1.83 | 0.14 |
Pb/Zn Veins | 756.41 | 757.28 | 0.87 | 201 | 30.78 | 0.30 | 0.10 |
DV24-415 | 503.75 | 518.80 | 15.05 | 244 | 0.46 | 0.21 | |
including | 509.63 | 518.80 | 9.17 | 354 | 0.52 | 0.41 | |
510.13 | 513.53 | 3.40 | 868 | 1.31 | 0.12 | ||
including | 510.88 | 512.03 | 1.15 | 2,034 | 3.47 | 0.18 | 0.11 |
DV24-417 | 570.80 | 573.00 | 2.20 | 2 | 0.12 | 1.62 | |
DV24-418 | 551.00 | 551.60 | 0.60 | 1 | 0.09 | 1.23 | |
651.33 | 652.68 | 1.35 | 17 | NSV | 1.02 | ||
DV24-419 | 71.58 | 72.57 | 0.99 | 201 | 0.45 | 0.22 | |
DV24-420 | NSV | ||||||
DV24-421 | 757.37 | 779.06 | 21.69 | 379 | 0.64 | 0.66 | |
Vein 1 | 757.37 | 767.80 | 10.43 | 556 | 1.02 | 1.00 | |
including | 759.81 | 760.49 | 0.68 | 1,165 | 1.33 | 1.87 | |
including | 764.09 | 765.76 | 1.67 | 1,804 | 4.36 | 3.10 | |
mid Stockwork | 767.80 | 772.81 | 5.01 | 203 | 0.11 | 0.11 | |
including | 770.59 | 771.25 | 0.66 | 1,185 | 0.28 | 0.07 | |
Vein 2 | 772.81 | 779.06 | 6.25 | 225 | 0.44 | 0.53 | |
including | 778.56 | 779.06 | 0.50 | 1,525 | 1.13 | 1.15 | |
Footwall Stockwork | 779.06 | 788.75 | 9.69 | 67 | 0.72 | 4.09 | |
DV24-425 | NSV | ||||||
DV24-426 | 272.14 | 273.35 | 1.21 | 189 | 0.17 | 0.19 | 0.10 |
*All intervals shown are core length. Estimated true widths vary depending on intersection angles and range from
Exploration Drilling
Areas of Exploration Drilling to follow up on areas of 2023 successes and test geological models in new areas were included in the 2024 drill plan. Significant results from the North Star Deposit and the Red Point prospect warrant follow up drilling during the 2025 program.
Figure 4 Dolly Varden Property Exploration drilling area location Plan
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_005full.jpg
North Star Deposit
Four drill holes were completed at the North Star Deposit associated with the Torbrit Deposit. These holes were oriented to test the shallow dipping mineralization at a perpendicular intersection angle than historic 1980s underground drilling. The North Star deposit is located approximately 350 meters southwest of the Torbrit Mine and is included in the current Mineral Resource Estimate. Drilling has shown that it is a continuation of stratabound mineralization along the Torbrit Horizon and that there is an increase in base metal mineralization, distal to the silver rich zone at the Torbrit Deposit. Within the mineralization intersected in the 2024 drilling, there are silver rich layers of strong base metal content, such as drill hole DV24-423 which intersected. 432 g/t Ag /
Figure 5. North Star Area 2024 drilling plan
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_006full.jpg
Red Point
Two drill holes were completed at the Red Point Gold Zone as follow up to 2023 drilling which intersected broad zones of quartz sericite pyrite (QSP) alteration, along with variable intensity of gold bearing quartz stockwork zones similar to the to the Homestake Ridge gold and silver deposits located 5.500 meters to the northwest along a trend of alteration and mineralized prospects.
Background gold values encountered in 2023 and 2024 drilling within the alteration zone are 0.15 to 0.25 g/t Au, with higher grade gold intervals in areas of intense stockwork, such as drill hole DV24-400 which intersected 21.10 g/t Au over 0.50m, within a broader zone averaging 0.79 g/t Au over 20.15 meters. Additionally, drill hole DV24-395 intersected 2.99 g/t Au over 3.11 meters within a broader interval that averaged 0.50 g/t Au over 59.09 meters. The style of mineralization and alteration at Red Point suggest a porphyry or intrusive-related mineralization system, which can host significant mineralization at Jurassic-age deposits throughout the Golden Triangle.
Insufficient drilling has been done to determine true width, estimates from intersect angles are that the true width is 80
Figure 6. Drill core of mineralization at Red Point from hole DV24-400. Sample interval 269.35 to 269.80m averaged 21.10 g/t Au in a wide zone of vein stockwork within strong quartz-sericite-pyrite alteration zone, hosted within Hazelton volcanic rocks.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1728/236263_f096f000a438ca2b_007full.jpg
Moose Vein
An additional five drill holes were completed at the Moose Vein, where previously released drill hole DV24-387 is located. Although narrow intervals of the Moose Vein were intersected in these drill holes, it appears that the silver mineralization is at a plunge angle than estimated and that the outcropping Moose vein may be the upper expression of a deeper mineralization system. Further modelling and a deeper test are planned for 2025.
Chance Vein
Two drill holes were completed at the Chance Vein where previously released drill hole DV24-388 is located. No significant mineralization was encountered.
Ace Galena
Two drill holes were completed at the Ace Galena showing, targeting anomalous lead and silver values in soil samples, located near an historic trench. A set of narrow, high grade lead and silver veins were intersected near surface and warrant follow up in 2025 (see Table 2).
Silver Horde
Two exploration holes were drilled at Silver Horde, located approximately 450 meters southwest of Moose Vein. These holes tested an area with potassic alteration in outcrops of Hazelton volcanic rocks at the edge of the post-mineralization sediment cover. Strong alteration was intersected with DV24-399 intersecting 108 g/t Ag and
Table 2: Completed 2024 Drill Hole Assays from Dolly Varden Property Exploration
Target Area | Hole ID | From (m) | To (m) | Length (m)* | Ag (g/t) | Pb (%) | Zn (%) | Au (g/t) |
Ace Galena | DV24-401 | 67.23 | 68.23 | 1.00 | 134 | 4.24 | NSV | |
including | 67.23 | 67.73 | 0.50 | 213 | 6.71 | NSV | ||
Ace Galena | DV24-403 | 83.60 | 85.60 | 2.00 | 17 | 0.79 | 2.00 | |
90.88 | 96.34 | 5.46 | 71 | 1.43 | 0.73 | |||
including | 94.12 | 96.34 | 2.22 | 125 | 1.39 | 0.18 | ||
106.34 | 108.26 | 1.92 | 289 | 4.33 | 0.18 | |||
Chance | DV24-390 | NSV | ||||||
Chance | DV24-393 | 101.90 | 105.70 | 3.80 | 125 | NSV | ||
154.00 | 155.00 | 1.00 | 142 | NSV | ||||
Moose | DV24-389 | 277.30 | 277.80 | 0.50 | 16 | 1.15 | NSV | |
Moose | DV24-392 | 226.50 | 227.30 | 0.80 | 80 | 1.11 | 1.13 | |
Moose | DV24-394 | 136.28 | 137.48 | 1.20 | 418 | 0.62 | 0.29 | |
including | 136.28 | 136.80 | 0.52 | 704 | 1.16 | 0.44 | ||
Moose | DV24-397 | 66.87 | 67.37 | 0.50 | 286 | 0.20 | 0.24 | |
201.05 | 202.00 | 0.95 | 108 | 0.04 | 0.06 | |||
Moose | DV24-398 | NSV | ||||||
North Star | DV24-386 | NSV | ||||||
North Star | DV24-391 | 356.50 | 361.84 | 5.34 | 16 | 0.38 | 2.03 | |
North Star | DV24-423 | 293.63 | 316.41 | 22.78 | 124 | 0.50 | 2.83 | 0.13 |
including Zn | 294.70 | 305.60 | 10.90 | 162 | 0.92 | 4.73 | ||
including Ag | 297.72 | 300.76 | 3.04 | 432 | 1.39 | 5.28 | ||
including Au | 306.28 | 316.41 | 10.13 | 94 | 0.12 | 1.14 | 0.22 | |
North Star | DV24-424 | 296.50 | 320.20 | 23.70 | 29 | 0.10 | 0.82 | 0.09 |
including Zn | 296.50 | 303.09 | 6.59 | 28 | 0.08 | 2.48 | 0.12 | |
including Au | 303.09 | 309.80 | 6.71 | 17 | 0.04 | 0.06 | 0.18 | |
Red Point | DV24-395 | 6.35 | 48.00 | 41.65 | 0.18 | |||
65.16 | 124.25 | 59.09 | 0.50 | |||||
including | 111.69 | 114.80 | 3.11 | 2.99 | ||||
193.30 | 195.00 | 1.70 | 0.67 | |||||
259.75 | 262.00 | 2.25 | 0.40 | |||||
314.52 | 316.40 | 1.88 | 0.65 | |||||
404.10 | 405.00 | 0.90 | 1.25 | |||||
Red Point | DV24-400 | 3.35 | 36.75 | 33.40 | 0.25 | |||
97.85 | 133.00 | 35.15 | 0.23 | |||||
including | 97.85 | 98.53 | 0.68 | 1.33 | ||||
including | 114.23 | 114.75 | 0.52 | 1.10 | ||||
253.85 | 274.00 | 20.15 | 0.79 | |||||
including | 269.35 | 269.85 | 0.50 | 21.10 | ||||
391.38 | 405.80 | 14.42 | 0.14 | |||||
Silver Horde | DV24-399 | 152.50 | 153.00 | 0.50 | 108 | 3.88 | 0.35 | |
Silver Horde | DV24-422 | NSV |
*All intervals shown are core length. Estimated true widths vary depending on intersection angles and range from
Table 3: Drill hole collars for Wolf Vein holes reported in this release
Hole ID | Easting UTM83 (m) | Northing UTM83 (m) | Elev. (m) | Azimuth | Dip | Length (m) |
DV24-405* | 466839 | 6173616 | 449 | 130.5 | -63 | 702 |
DV24-406 | 467053 | 6173650 | 380 | 117 | -54 | 402 |
DV24-407 | 467053 | 6173650 | 380 | 125 | -74 | 739.7 |
DV24-411* | 466929 | 6173582 | 401 | 125 | -66 | 609 |
DV24-413* | 466839 | 6173616 | 449 | 130.5 | -63 | 801 |
DV24-415* | 466929 | 6173582 | 401 | 125 | -66 | 573 |
DV24-417* | 466929 | 6173582 | 401 | 125 | -66 | 666 |
DV24-418* | 466929 | 6173582 | 401 | 125 | -66 | 708 |
DV24-419 | 467464 | 6173723 | 524 | 150 | -60 | 159 |
DV24-420 | 467464 | 6173723 | 524 | 120 | -65 | 102 |
DV24-421 | 467265 | 6172994 | 372 | 299 | -58 | 816 |
DV24-425 | 467108 | 6173625 | 390 | 112 | -45 | 342 |
DV24-426 | 467108 | 6173625 | 390 | 112 | -52 | 348 |
*Directional drilling holes with orientation of "mother" hole collar and total length from collar; daughter holes directed off mother holes at variable orientations downhole to reach target locations.
Table 4: Drill hole collars for Dolly Varden Property Exploration Drill holes reported in this release
Area | Hole ID | Easting UTM83 (m) | Northing UTM83 (m) | Elev. (m) | Azimuth | Dip | Length (m) |
Ace Galena | DV24-401 | 466917 | 6176263 | 630 | 90 | -45 | 150 |
Ace Galena | DV24-403 | 467021 | 6176650 | 736 | 135 | -50 | 252 |
Chance | DV24-390 | 467674 | 6175858 | 881 | 170 | -55 | 300 |
Chance | DV24-393 | 467520 | 6175605 | 799 | 355 | -55 | 315 |
Moose | DV24-389 | 467141 | 6174889 | 750 | 160 | -62 | 297 |
Moose | DV24-392 | 467141 | 6174889 | 750 | 190 | -65 | 294 |
Moose | DV24-394 | 467050 | 6174879 | 681 | 160 | -55 | 255 |
Moose | DV24-397 | 467050 | 6174879 | 681 | 190 | -30 | 207 |
Moose | DV24-398 | 467050 | 6174879 | 681 | 215 | -55 | 261 |
North Star | DV24-386 | 467538 | 6171307 | 554 | 165 | -60 | 402 |
North Star | DV24-391 | 467538 | 6171307 | 554 | 160 | -68 | 399 |
North Star | DV24-423 | 467573 | 6171328 | 537 | 110 | -53 | 354 |
North Star | DV24-424 | 467573 | 6171328 | 537 | 158 | -64 | 400.35 |
Red Point | DV24-395 | 467004 | 6172120 | 617 | 205 | -50 | 450 |
Red Point | DV24-400 | 466858 | 6172228 | 676 | 220 | -63 | 411 |
Silver Horde | DV24-399 | 466834 | 6174627 | 399 | 175 | -65 | 201 |
Silver Horde | DV24-422 | 466724 | 6174704 | 380 | 182 | -65 | 468 |
Quality Assurance and Quality Control
The Company adheres to CIM Best Practices Guidelines for exploration related activities conducted on its property. Quality Assurance and Quality Control (QA/QC) procedures are overseen by the Qualified Person.
Dolly Varden QA/QC protocols are maintained through the insertion of certified reference material (standards), blanks and field duplicates within the sample stream. Drill core is cut in-half with a diamond saw, with one-half placed in sealed bags and shipped to the laboratory and the other half retained on site. Third party laboratory checks on
Analytical testing was performed by ALS Canada Ltd. in North Vancouver, British Columbia. The entire sample is crushed to
Qualified Person
Rob van Egmond, P.Geo., Vice-President Exploration for Dolly Varden Silver, the "Qualified Person" as defined by NI43-101 has reviewed, validated and approved the scientific and technical information contained in this news release and supervises the ongoing exploration program at the Dolly Varden Project.
About Dolly Varden Silver Corporation
Dolly Varden Silver Corporation is a mineral exploration company focused on advancing its
Forward-Looking Statements
This release may contain forward-looking statements or forward-looking information under applicable Canadian securities legislation that may not be based on historical fact, including, without limitation, statements containing the words "believe", "may", "plan", "will", "estimate", "continue", "anticipate", "intend", "expect", "potential", and similar expressions. Forward-Looking statements involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance, or achievements of Dolly Varden to be materially different from any future results, performance, or achievements expressed or implied by the forward-looking statements. Forward-Looking statements or information in this release relates to, among other things, the 2022 drill program at the Kitsault Valley Project, the results of previous field work and programs and the continued operations of the current exploration program, interpretation of the nature of the mineralization at the project and that that the mineralization on the project is similar to Eskay and Brucejack, results of the mineral resource estimate on the project, the potential to grow the project, the potential to expand the mineralization and our beliefs about the unexplored portion of the property.
These forward-looking statements are based on management's current expectations and beliefs and assume, among other things, the ability of the Company to successfully pursue its current development plans, that future sources of funding will be available to the company, that relevant commodity prices will remain at levels that are economically viable for the Company and that the Company will receive relevant permits in a timely manner in order to enable its operations, but given the uncertainties, assumptions and risks, readers are cautioned not to place undue reliance on such forward-looking statements or information. The Company disclaims any obligation to update, or to publicly announce, any such statements, events or developments except as required by law.
For additional information on risks and uncertainties, see the Company's most recently filed annual management discussion & analysis ("MD&A") dated March 27, 2024, and management information circular dated May 28, 2024 (the "Circular"), both of which are available on SEDAR at www.sedarplus.ca. The risk factors identified in the MD&A and the Circular are not intended to represent a complete list of factors that could affect the Company.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX-V) accepts responsibility for the adequacy or accuracy of this news release.
For further information: Shawn Khunkhun, CEO & Director, 1-604-609-5137, www.dollyvardensilver.com;
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/236263
FAQ
What were the key silver grades reported in Dolly Varden's (DOLLF) latest Wolf Vein drilling results?
How much did Dolly Varden (DOLLF) expand its 2024 drilling program?
What is the current plunge extent of the Wolf Vein after the 2024 drilling program?