Critical Elements Receives Amended Certificate of Authorization for the Rose Lithium-Tantalum Project in Quebec
Critical Elements Lithium (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) has received an amended certificate of authorization for the Rose Lithium-Tantalum project in Quebec. The amendments include the construction of a 250-person workers' camp, temporary provision for an additional 250 people during construction, and use of two borrow pits. The company is working on arranging a comprehensive financing package for the project's development.
Despite market challenges, Critical Elements has made significant progress in project preparation, including detailed engineering, environmental improvements, and obtaining major permits and agreements. The company has also made a new lithium discovery at Rose West and holds a 20% carried interest in Power Nickel's Nisk property.
Critical Elements Lithium (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) ha ricevuto un certificato di autorizzazione modificato per il progetto Rose Lithium-Tantalum in Quebec. Le modifiche includono la costruzione di un campo per 250 lavoratori, una fornitura temporanea per ulteriori 250 persone durante la costruzione e l'uso di due cave. L'azienda sta lavorando per organizzare un pacchetto di finanziamento completo per lo sviluppo del progetto.
Nonostante le sfide del mercato, Critical Elements ha fatto progressi significativi nella preparazione del progetto, inclusi ingegneria dettagliata, miglioramenti ambientali e ottenimento di importanti permessi e accordi. L'azienda ha anche fatto una nuova scoperta di litio a Rose West e detiene un interesse del 20% nel progetto Nisk di Power Nickel.
Critical Elements Lithium (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) ha recibido un certificado de autorización modificado para el proyecto Rose Lithium-Tantalum en Quebec. Las enmiendas incluyen la construcción de un campamento para 250 trabajadores, la provisión temporal de 250 personas adicionales durante la construcción y el uso de dos canteras. La empresa está trabajando en organizar un paquete de financiamiento integral para el desarrollo del proyecto.
A pesar de los desafíos del mercado, Critical Elements ha hecho progresos significativos en la preparación del proyecto, incluyendo ingeniería detallada, mejoras ambientales y obtención de permisos y acuerdos importantes. La empresa también ha realizado un nuevo descubrimiento de litio en Rose West y posee un 20% de interés en la propiedad Nisk de Power Nickel.
크리티컬 엘리먼츠 리튬 (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12)이 퀘벡의 로즈 리튬-탄탈륨 프로젝트에 대한 수정된 승인서를 받았습니다. 수정 사항에는 250명의 근로자 캠프 건설, 건설 기간 동안 추가로 250명의 임시 수용이 포함되며, 두 개의 대여석 사용이 포함됩니다. 회사는 프로젝트 개발을 위한 종합 자금 조달 패키지를 마련하고 있습니다.
시장 도전에도 불구하고, 크리티컬 엘리먼츠는 상세 엔지니어링, 환경 개선 및 주요 허가 및 계약 확보를 포함하여 프로젝트 준비에서 상당한 진전을 이루었습니다. 이 회사는 Rose West에서 새로운 리튬 발견을 했으며, Power Nickel의 Nisk 자산에서 20% 지분을 보유하고 있습니다.
Critical Elements Lithium (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) a reçu un certificat d'autorisation modifié pour le projet Rose Lithium-Tantalum au Québec. Les modifications incluent la construction d'un camp de travailleurs pour 250 personnes, la provision temporaire de 250 personnes supplémentaires pendant la construction et l'utilisation de deux carrières. L'entreprise travaille à l'organisation d'un plan de financement complet pour le développement du projet.
Malgré les défis du marché, Critical Elements a réalisé des progrès significatifs dans la préparation du projet, y compris l'ingénierie détaillée, les améliorations environnementales et l'obtention de permis et d'accords majeurs. L'entreprise a également fait une nouvelle découverte de lithium à Rose West et détient un intérêt de 20 % dans le projet Nisk de Power Nickel.
Critical Elements Lithium (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) hat ein geändertes Genehmigungszertifikat für das Rose Lithium-Tantalum Projekt in Quebec erhalten. Zu den Änderungen gehört der Bau eines Lagers für 250 Arbeiter, die vorübergehende Bereitstellung für weitere 250 Personen während der Bauphase und die Nutzung von zwei Abgrabungsstellen. Das Unternehmen arbeitet daran, ein umfassendes Finanzierungspaket für die Entwicklung des Projekts zu schnüren.
Trotz der Herausforderungen auf dem Markt hat Critical Elements erhebliche Fortschritte in der Projektvorbereitung erzielt, darunter detaillierte Ingenieurarbeiten, Umweltverbesserungen sowie den Erhalt wichtiger Genehmigungen und Vereinbarungen. Das Unternehmen hat auch eine neue Lithiumentdeckung bei Rose West gemacht und hält eine 20%ige Beteiligung an der Nisk-Liegenschaft von Power Nickel.
- Received amended certificate of authorization for Rose Lithium-Tantalum project
- Detailed engineering for key project elements 100% complete for permitting
- 56% reduction in annual greenhouse gas emissions to 37,314 tonnes CO2EQ
- Major permits and agreements in place, including Mining Lease and Industrial Occupancy Leases
- New lithium discovery at Rose West, potentially enhancing project mine life and economics
- 20% carried interest in Power Nickel's Nisk property with promising nickel-copper PGM exploration results
- Global lithium market sentiment remains negative, affecting share price and valuation
- Uncertainty in timing and outcome of project financing process
- Competitive mining human resources market in Quebec
MONTRÉAL, QC / ACCESSWIRE / August 14, 2024 / Critical Elements Lithium Corporation (the "Corporation" or "Critical Elements") (TSX.V:CRE)(US OTCQX:CRECF)(FSE:F12) is pleased to announce that it has received the amended certificate of authorization ("CA") for the Rose Lithium-Tantalum project ("Rose" or the "Project") from the Ministère de l'Environnement, de la Lutte contre les changements climatiques, de la Faune et des Parcs du Québec. The amendments to the original CA issued on October 31, 2022, include the addition of the following points:
- The construction and development of the permanent workers' camp with a capacity of 250 people;
- The temporary provision of an additional 250 people at the camp during the construction phase;
- The use of two (2) borrow Pit.
This will allow for the Project to submit its Construction permit applications for the Early Earth Works and the Workers' Camp.
The Corporation is also pleased to provide a Project and activities update. While global Electric Vehicle and Energy Storage System sales have continued to grow to record levels, the overall lithium market sentiment and media coverage remains negative as seen through the material share price and valuation challenges experienced by producers through to developers and explorers since April 2022. Critical Elements has not been immune to this correction phase.
Critical Elements management and board of directors continue work in preparation for the completion of a financing package for the Project that allows for a final investment decision while maintaining an attractive capital structure and mitigating risk. Critical Elements is working to arrange a comprehensive financing package to fully fund the development of Rose. Shareholders will be updated as the financing package progress and timelines will be updated as the project financing package is assembled.
The Corporation recognizes the intricacy of these negotiations and due diligence required. At this time, there can be no guarantees as to the timing and outcome of this process. Management is committed to securing an optimal outcome for Rose's development and appreciates the continued support and patience of its investors as the Corporation works to secure the required capital in its stated objective to become a significant and responsible supplier of high-quality lithium to the global supply chain.
Further, it is crucial to note this process is progressing in tandem with the overall development of Rose, as management continues to be proactive with other risk reduction measures. The Corporation's balance sheet has sufficient resources to continue working towards a final investment decision. In the face of Québec's extremely competitive mining human resources market, Critical Elements has assembled a highly-skilled engineering and construction team under Yves Perron, Vice President Engineering, Construction and Operations.
To be ready, Critical Elements is well-advanced in detailed engineering for the key elements required early in construction. These elements include mining pit, the co-disposal, ore and overburden stockpile, infrastructure (pads & road) and water management (including ditches, accumulation storage pond & three (3) water treatment plants for potable, domestic and mine site water) and camp are
IT systems and worker policies, like Health and Safety, Environment, Supplier and others have also been established in preparation for a "go" decision.
Yves Perron, Vice-President Engineering, Construction and Operations and Nancy Duquet-Harvey, Senior Director of Sustainable Development and Environment, supported by the Project owner's team have been instrumental in advancing environmental monitoring, permitting and in meeting required commitments and conditions in advance of Project construction. The Project's major permits and agreements are in place, making it one of the most advanced lithium projects in North America. These include:
The Pikhuutaau Agreement, an impact and benefits agreement for the development and operation of Rose, signed with the Cree Nation of Eastmain, the Grand Council of the Crees (Eeyou Istchee) and the Cree Nation Government (July 2019);
Federal Approval of Environmental Impact Assessment and favorable decision from the Minister of Environment and Climate Change (August 2021);
Approval by the Québec Minister of Natural Resources and Forests of the rehabilitation and restoration plan (May 2022);
Provincial Certificate of Authorization pursuant to section 164 of Quebec's Environment Quality Act from the Quebec Minister of the Environment, the Fight against Climate Change, Wildlife and Parcs (November 2022);
Mining Lease from the Québec Minister of Natural Resources and Forests, granted under the Québec Mining Act (September 2023);
Obtained an order from the Minister of Transport of Canada exempting the Corporation from the prohibition to dewater navigable waters under the Canadian Navigable Waters Act (October 2023); and
Three industrial occupancy leases (storage and mining infrastructure) and tailings management facility leases granted by the Ministère des Ressources naturelles et des Forêts under the Act respecting lands in the domain of the State (Québec) (February 2024).
The major milestones outlined are essential for the Project's progress, as are the remaining permits and commitments to be addressed.
The Corporation has also substantially completed its pre-construction commitments as defined under the COMEX Authorization and Federal Decision Statement. One of the commitments required is the establishment of a Fisheries Compensation Plan, which is being finalized in conjunction with the Cree Nation Government and Oceans and Fisheries Canada. Scores of community engagement and committee meetings have and are taking place along with meetings with Ministries of the Québec Government, the Cree Nation Government, Société du Plan Nord, Société d'énergie de la Baie James and Hydro-Québec, as well as with the Eastmain, Nemaska, Waskaganish and Waswanipi communities and Tallymen. Constant communication is essential in maintaining the Corporation's strong relationship with stakeholders.
Mr. Perron said: "I'm proud and grateful for the work done by the Project owner's team. We are very well positioned with our team, which is highly experienced in mine project development, construction and commissioning. This experience will be very important for risk management during construction and commissioning of the Rose Lithium-Tantalum project."
Exploration remains an important value driver in terms of resource expansion and mine life extension. As outlined in the news release of April 22, 2024, Critical Elements has made an important new discovery of lithium mineralization at Rose West, situated within the Rose Lithium-Tantalum and Rose South property blocks, which constitute 395 km2, or only
We are also cognizant of the exploration success of Power Nickel Inc. ("Power Nickel") on the Nisk property. Power Nickel has earned an
Qualified persons
Yves Perron, Eng. MBA, Vice-President Engineering, Construction and Operations is the qualified persons that have reviewed and approved the technical contents of this news release on behalf of the Corporation.
About Critical Elements Lithium Corporation
Critical Elements aspires to become a large, responsible supplier of lithium to the flourishing electric vehicle and energy storage system industries. To this end, Critical Elements is advancing the wholly owned, high-purity Rose Lithium-Tantalum project in Québec, the Corporation's first lithium project to be advanced within a land portfolio of over 1,050 km2. On August 29, 2023, the Corporation announced results of a new Feasibility Study on Rose for the production of spodumene concentrate. The after-tax internal rate of return for the Project is estimated at
For further information, please contact:
Jean-Sébastien Lavallée, P. Géo.
Chief Executive Officer
819-354-5146
jslavallee@cecorp.ca
www.cecorp.ca
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is described in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary statement concerning forward-looking statements
This news release contains "forward-looking information" within the meaning of Canadian Securities legislation. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "scheduled", "anticipates", "expects" or "does not expect", "is expected", "scheduled", "targeted", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information contained herein include, without limitation, statements relating to expectations regarding Rose project-level activities including (i) completion of the permitting process, (ii) securing a strategic partnership and project financing leading to a Final Investment Decision and (iii) respecting the Rose project ramp up and commissioning timeline, expectations regarding potential value creation from ongoing and future exploration activities on the Corporation's projects, and the Corporation's ongoing business plan. Such forward-looking information and statements are based on numerous assumptions, including that general business and economic conditions will not change in a material adverse manner, that fundamentals of lithium / spodumene demand and EV market growth and capacity will continue to be strong, that project financing will be available on reasonable terms, and that governmental and other approvals required to conduct the Company's development activities and planned exploration will be available on reasonable terms and in a timely manner. Although the assumptions made by the Corporation in providing forward-looking information or making forward-looking statements are considered reasonable by management at the time, there can be no assurance that such assumptions will prove to be accurate.
Although Critical Elements has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. Factors that may cause actual results to differ materially from expected results described in forward-looking information include, but are not limited to: negative operating cash flow and dependence on third party financing, uncertainty of additional financing, reliance on key management and other personnel, potential downturns in (i) general economic conditions, (ii) demand for lithium / spodumene and (iii) EV market growth, capacity and demand, actual results of exploration activities being different than anticipated, changes in exploration programs based upon results, risks generally associated with the mineral exploration industry, environmental risks, changes in laws and regulations, community relations and delays in obtaining governmental or other approvals, as well as those risk factors set out in the Corporation's Management Discussion and Analysis for its most recent quarter ended May 31, 2024 and other disclosure documents available under the Corporation's SEDAR+ profile (www.sedarplus.ca).
Forward-looking information contained herein is made as of the date of this news release. Although the Corporation has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information or implied by forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking statements or information. The Company undertakes no obligation to update or reissue forward-looking information as a result of new information or events except as required by applicable securities laws.
SOURCE: Critical Elements Lithium Corp.
View the original press release on accesswire.com
FAQ
What amendments were made to the Rose Lithium-Tantalum project's certificate of authorization?
How has Critical Elements Lithium (CRECF) addressed environmental concerns in the Rose project?
What major permits has Critical Elements Lithium (CRECF) secured for the Rose project?