STOCK TITAN

AEP Ohio Files Plan to Secure Grid Resources for Data Centers, Protect Residential Customers

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

Rhea-AI Summary

AEP Ohio filed a proposal to create a new rate category for data center customers and cryptocurrency mining operations, aiming to address the increasing demand for electricity fueled by new technologies like artificial intelligence. The proposal requires data centers to commit to paying for a minimum of 90% of the energy they need each month over a 10-year period, even if they use less. The plan also highlights the need for investments in new transmission lines to accommodate the growing electricity demand in Central Ohio. This initiative provides clarity for long-term planning and obligations for data center and cryptocurrency mining customers.

Loading...
Loading translation...

Positive

  • AEP Ohio is responding to the increasing demand for electricity from data centers and cryptocurrency mining operations with a proposal to create a new rate category to ensure proper planning and investment in the electric grid.

  • The proposal requires data centers to commit to paying for a minimum of 90% of the energy they need each month over a 10-year period, providing stability and certainty for both AEP Ohio and its customers.

  • The plan emphasizes the need for investments in new extra-high voltage transmission lines to accommodate the electricity demand in Central Ohio, attracting new jobs and investment to the region.

Negative

  • The development of data centers in AEP Ohio's service territory may lead to challenges in maintaining grid reliability and ensuring that customers are not overburdened with the costs of unused infrastructure.

  • The proposal's requirement for data centers to pay for a minimum of 90% of the energy they need each month, even if they use less, could potentially pose financial challenges for data center operators in the long run.

  • The construction of new transmission lines to support the increasing demand for electricity in Central Ohio can be a time-consuming process, taking 7-10 years to plan and construct, potentially leading to delays in meeting customer needs.

News Market Reaction 1 Alert

-0.10% News Effect

On the day this news was published, AEP declined 0.10%, reflecting a mild negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

GAHANNA, Ohio, May 13, 2024 /PRNewswire/ -- AEP Ohio, an American Electric Power (Nasdaq: AEP) company, today filed with the Public Utilities Commission of Ohio in docket 24-508-EL-ATA a proposal that would create a new rate category for data center customers and cryptocurrency mining/mobile data center operations. The proposed rate structure would require new data centers with loads greater than 25 megawatts (MW) and cryptocurrency mining operations/mobile data centers with loads greater than 1 MW to agree to meet certain requirements before facilities are constructed to serve them.

"Demand for computing power from data centers, which require enormous amounts of electricity, is being fueled by artificial intelligence and other new technologies. AEP Ohio is seeing unprecedented demand from data center customers, especially in the Central Ohio area. While we see no concerns serving current or new residential and existing commercial or industrial customers, we need to ensure that the right long-term investments are made to the electric grid," said Marc Reitter, AEP Ohio president and chief operating officer. "We need accurate plans and solid commitments from large data center customers so the right facilities are built at the right time. This will help us keep Ohio open for business for all industries, while making sure customers aren't paying for unused infrastructure."

Under the proposal, data centers would be required to make a 10-year commitment to pay for a minimum of 90% of the energy they say they need each month – even if they use less.

Data center development has rapidly expanded in AEP Ohio's service territory, especially in the Central Ohio region. Electricity demand in Central Ohio, driven largely by data centers, is already expected to more than double by 2030 making demand in the region roughly equal to that of Manhattan. Adding additional large users will require investment in new extra-high voltage transmission lines to bring more power into the region. These lines can take 7-10 years to plan and construct.

"AEP Ohio has helped the state of Ohio attract thousands of new jobs and billions of dollars in investment because over the decades, AEP has built an extensive network of transmission lines to deliver the power these customers need," Reitter added. "This is one of the reasons data center developers targeted Central Ohio, and they continue to request large amounts of power. We need to ensure they can follow through with their commitments as significant new investments are made to serve them."

The new rate structure provides AEP Ohio and its customers with the certainty needed to develop long-term plans and offers data center and cryptocurrency mining customers a clear understanding of their obligations as customers.

AEP Ohio is based in Gahanna, Ohio, and is a unit of American Electric Power. AEP Ohio provides electricity to 1.5 million customers. News and information about AEP Ohio can be found at AEPOhio.com.

At American Electric Power, based in Columbus, Ohio, we understand that our customers and communities depend on safe, reliable and affordable power. Our nearly 17,000 employees operate and maintain more than 40,000 miles of transmission lines, the nation's largest electric transmission system, and more than 225,000 miles of distribution lines to deliver power to 5.6 million customers in 11 states. AEP also is one of the nation's largest electricity producers with approximately 29,000 megawatts of diverse generating capacity, including nearly 6,000 megawatts of renewable energy. AEP is investing $43 billion over the next five years to make the electric grid cleaner and more reliable. We are on track to reach an 80% reduction in carbon dioxide emissions from 2005 levels by 2030 and have a goal to achieve net zero by 2045. AEP is recognized consistently for its focus on sustainability, community engagement and inclusion. AEP's family of companies includes utilities AEP Ohio, AEP Texas, Appalachian Power (in Virginia and West Virginia), AEP Appalachian Power (in Tennessee), Indiana Michigan Power, Kentucky Power, Public Service Company of Oklahoma, and Southwestern Electric Power Company (in Arkansas, Louisiana, east Texas and the Texas Panhandle). AEP also owns AEP Energy, which provides innovative competitive energy solutions nationwide. For more information, visit aep.com.

(PRNewsfoto/American Electric Power)

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/aep-ohio-files-plan-to-secure-grid-resources-for-data-centers-protect-residential-customers-302143900.html

SOURCE AEP Ohio

FAQ

What did AEP Ohio file with the Public Utilities Commission of Ohio?

AEP Ohio filed a proposal to create a new rate category for data center customers and cryptocurrency mining operations.

What commitment is required from data centers under the proposal?

Data centers are required to commit to paying for a minimum of 90% of the energy they need each month over a 10-year period.

What is the expected impact of data center development in Central Ohio?

The electricity demand in Central Ohio, driven by data centers, is projected to more than double by 2030, equivalent to that of Manhattan.

What investments are needed to support the electricity demand in Central Ohio?

New extra-high voltage transmission lines are required to bring more power into the region, attracting new jobs and investment.

Where is AEP Ohio based?

AEP Ohio is based in Gahanna, Ohio, and is a unit of American Electric Power.

How many customers does AEP Ohio provide electricity to?

AEP Ohio provides electricity to 1.5 million customers.

What is the goal of AEP in terms of carbon dioxide emissions reduction?

AEP aims to achieve an 80% reduction in carbon dioxide emissions from 2005 levels by 2030 and reach net zero by 2045.
Americn Electric

NASDAQ:AEP

AEP Rankings

AEP Latest News

AEP Latest SEC Filings

AEP Stock Data

61.59B
532.71M
0.03%
85.27%
4.26%
Utilities - Regulated Electric
Electric Services
Link
United States
COLUMBUS