Ameren Transmission Company of Illinois (ATXI), a subsidiary of Ameren Corporation (NYSE: AEE), has received approval from the Missouri Public Service Commission (PSC) for its Limestone Ridge Project. This initiative includes the construction of a 15-mile, 138,000-volt transmission line and substation in southeast Missouri, connecting substations in Perry and Cape Girardeau counties. The project aims to enhance energy reliability and economic growth in the region, with an investment of $40 million and a proposed completion date of December 2023.

Positive
  • Approval for the Limestone Ridge Project enhances southeast Missouri's energy grid.
  • The project will improve energy reliability and support economic growth in the region.
  • Investment of $40 million demonstrates ATXI's commitment to infrastructure development.
Negative
  • None.

ST. LOUIS, Jan. 26, 2022 /PRNewswire/ -- Ameren Transmission Company of Illinois (ATXI), a wholly owned subsidiary of Ameren Corporation (NYSE: AEE), received approval from the Missouri Public Service Commission (PSC) to proceed with the construction of the Limestone Ridge Project, a 15-mile, 138,000-volt transmission line and substation to be built in southeast Missouri. The PSC granted ATXI a certificate of convenience and necessity (CCN) for the project, which will connect two substations in Perry and Cape Girardeau counties, providing additional capacity for the region's energy infrastructure.   

"Approval of the Limestone Ridge Project is a significant step toward strengthening southeast Missouri's energy grid and delivering customer benefits," said Jim Jontry, project manager of the Limestone Ridge Project. "This project will deliver greater energy reliability, economic growth, and improved access to clean energy sources for southeast Missouri and its residents."

ATXI will construct, operate and maintain the new transmission line. The route will run through Perry and Cape Girardeau counties in Missouri and will include the construction of state-of-the-art substations to improve energy reliability for local communities. ATXI is collaborating with Wabash Valley Power Alliance (WVPA) to co-locate 65% of the new transmission line along WVPA's existing rights of way.

ATXI expects to invest $40 million in the Limestone Ridge Project. Construction of the project is planned to begin this year with a proposed in-service date of December 2023.

Additional information is available on the project's website at limestoneridgeproject.com, by emailing LimestoneRidgeProject@ameren.com, or by calling the project hotline at 573-232-3003.

About Ameren Corporation
St. Louis-based Ameren Corporation powers the quality of life for 2.4 million electric customers and more than 900,000 natural gas customers in a 64,000-square-mile area through its Ameren Missouri and Ameren Illinois rate-regulated utility subsidiaries. Ameren Illinois provides electric transmission and distribution service and natural gas distribution service. Ameren Missouri provides electric generation, transmission and distribution services, as well as natural gas distribution service. Ameren Transmission Company of Illinois operates a rate-regulated electric transmission business in the Midcontinent Independent System Operator, Inc. For more information, visit Ameren.com, or follow us on Twitter at @AmerenCorp, Facebook.com/AmerenCorp, or LinkedIn.com/company/Ameren.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/atxi-receives-final-approval-to-construct-the-limestone-ridge-project-in-southeast-missouri-301468805.html

SOURCE Ameren Corporation

FAQ

What is the Limestone Ridge Project approved by Ameren Corporation?

The Limestone Ridge Project is a 15-mile, 138,000-volt transmission line and substation in southeast Missouri, approved by the Missouri PSC.

How much will Ameren invest in the Limestone Ridge Project?

Ameren Transmission Company of Illinois plans to invest $40 million in the Limestone Ridge Project.

When is the proposed completion date for the Limestone Ridge Project?

The proposed in-service date for the Limestone Ridge Project is December 2023.

What benefits will the Limestone Ridge Project provide?

The project aims to enhance energy reliability and support economic growth in southeast Missouri.

Which counties will the Limestone Ridge Project affect?

The Limestone Ridge Project will connect substations in Perry and Cape Girardeau counties in Missouri.

Ameren Corporation

NYSE:AEE

AEE Rankings

AEE Latest News

AEE Stock Data

23.63B
265.98M
0.27%
81.33%
1.27%
Utilities - Regulated Electric
Electric & Other Services Combined
Link
United States of America
ST LOUIS