Test Run of Paradine Mill Facility Yields Promising Results
Winston Gold Corp. announced successful testing of the Paradine Mill Facility, processing 338 tons over six days with gold recovery rates exceeding 80%. Improvements were made in the float circuit after adjusting the chemical mix and mill feed size. The facility aims to become a turnkey mineral processing plant, supported by planned upgrades and the recruitment of new employees. Additionally, a joint venture with Bond Resources is underway to explore the Hard Cash Mine, which is close to the mill site, enhancing future cash-flow prospects.
- Achieved over 80% gold recovery rate after mill adjustments.
- Successful testing resulted in processing of 338 tons within six days.
- Improvements in mill operations with ongoing upgrades planned.
- Formation of joint venture with Bond Resources to explore Hard Cash Mine.
- None.
WINNIPEG, MB / ACCESSWIRE / June 29, 2021 / Winston Gold Corp. ("Winston Gold" or the "Corporation") (CSE:WGC) (OTCQB:WGMCF) is pleased to announce that the Paradine Mill Facility, near Radersburg Montana., was tested over a one week shift ending on June 21st.
About 338 tons were processed over the six-day shift and a notable improvement in float circuit recovery was recorded. Gold recoveries in this circuit were in the
"We achieved our goal of transforming the Paradine mill into reliable and efficient operation on June 16, 2021, well ahead of the June 21 deadline," commented Mr. Murray Nye, CEO and Director of Winston Gold Mines."Work is now focused on procuring and installing the last key upgrades in time for the next shift rotation."
During the last test run of the Mill, a few additional improvements were identified. Specifically, the electrical starter boxes for the Sub A Cleaner Cells will be replaced as well as a new 3-ply mine belt for the hopper feeder belt. In addition, the tail pulley and associated bearing will also be replaced before the mill will be restarted.
- Despite a few hiccups, the mill is performing exceptionally well. The following points summarize the achievements to date:
- Re-configured float circuit showed improved recoveries in the
80% range - Tailings line extended to the north side of Pond #1
- Re-manufactured Pinion bearing performed flawlessly
- Pressure switch for Knelson concentrator installed
- Ball mill ran smoothly at
50% charge with minus ¾ inch feed - Two new employees were hired and are being trained to MSHA (Mine Safety & Health Administration) standards and task trained
The Paradine mill facility is being developed into a turn-key mineral processing plant," stated Mr. Joseph Carrabba, Executive Chairman of Winston Gold. "The mill lies in the heart of a region blessed with precious metal endowment, and the future value opportunities are significant."
Towards that end, Winston Gold recently formed a joint venture with Bond Resources (CSE:BJB) to test the near-term cash-flow viability of another past producer, the Hard Cash Mine. (Refer to news release dated May 13th 2021). The Hard Cash property is located just 4.3 miles from the Paradine Mill and an initial drilling, trenching and bulk samplingprogram should commence shortly.
About the Paradine Mill Facility
The Paradine mill located just 35 miles (56 km) by paved road from the Company's wholly owned Winston Gold project which is situated near Helena, Montana. The Mill has a nameplate capacity of 150 tons per day and hosts a ball milling circuit as well as both a gravity and flotation circuit. A new lined settling pond has been constructed for tailings disposal with a 35,000-ton capacity and two additional ponds are also being built.
Qualified Person
The scientific and technical content and interpretations contained in this news release have been reviewed, verified and approved by Dr. Criss Capps PhD. P.Geol., an independent consultant to Winston Gold Corp. Dr. Capps is a Qualified Person as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects.
About Winston Gold
Winston Gold is a junior mining company focused on advancing high-grade, low-cost mining opportunities into production. Towards that end, the Corporation has acquired the under-explored and under-exploited Winston Gold project near Helena, Montana.
The CSE has neither approved nor disapproved the information contained herein. This news release does not constitute an offer to sell or a solicitation of an offer to buy any of the securities in the United States. The securities have not been and will not be registered under the United States Securities Act of 1933, as amended (the "U.S. Securities Act"), or any state securities laws and may not be offered or sold within the United States or to U.S. Persons unless registered under the U.S. Securities Act and applicable state securities laws or an exemption from such registration is available.
Forward-Looking Information
This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address events or developments that Winston Gold Mining Corp. (the "Company") expects to occur, are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in the forward-looking statements. Factors that could cause the actual results to differ materially from those in forward-looking statements include regulatory actions, market prices, exploitation and exploration successes, and continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made. Except as required by applicable securities laws, the Company undertakes no obligation to update these forward-looking statements in the event that management's beliefs, estimates or opinions, or other factors, should change.
For more information, please visit www.winstongoldmining.com; or contact:
Murray Nye,
Chief Executive Officer and a Director of Winston Gold
Suite 201-919 Notre Dame Avenue
Winnipeg, Manitoba, R3E 0M8
Telephone: (204) 989-2434
E-mail: murray@winstongold.com
SOURCE: Winston Gold Corp.
View source version on accesswire.com:
https://www.accesswire.com/653469/Test-Run-of-Paradine-Mill-Facility-Yields-Promising-Results
FAQ
What were the results of the test run at Paradine Mill Facility by Winston Gold Corp.?
What is the significance of the joint venture between Winston Gold Corp. and Bond Resources?
When was the test run at the Paradine Mill Facility conducted?
What is the future plan for the Paradine Mill Facility?