STOCK TITAN

Salazar Resources Announces Update on Construction Plan and Schedule for the Development of the El Domo Project

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

Salazar Resources (SRLZF) provides an update on the El Domo mine construction project, a joint venture with Silvercorp Metals (75% interest) where Salazar holds a 25% carried interest. The project targets production start by end of 2026 with an estimated cost of $240.4 million, slightly lower than the 2021 feasibility study estimate of $247.6 million.

The construction plan includes five key bid packages covering site preparation, open pit mining, processing plant construction, power line installation, and diesel generators. Major milestones include: stripping commencement in August 2025, processing plant construction starting September 2025, and commissioning in December 2026.

The project's direct costs have been reduced by $32.6 million to $159.4 million through unit cost contracting and detailed engineering. Once commercial production begins, Silvercorp will receive 95% of dividends until investment recovery, after which profits will be shared 75%/25% with Salazar.

Salazar Resources (SRLZF) fornisce un aggiornamento sul progetto di costruzione della miniera El Domo, una joint venture con Silvercorp Metals (con una partecipazione del 75%) in cui Salazar detiene una quota del 25% a carico. Il progetto prevede l'inizio della produzione entro la fine del 2026 con un costo stimato di 240,4 milioni di dollari, leggermente inferiore alla stima dello studio di fattibilità del 2021 di 247,6 milioni di dollari.

Il piano di costruzione include cinque pacchetti di gara principali che coprono la preparazione del sito, l'estrazione a cielo aperto, la costruzione dell'impianto di lavorazione, l'installazione della linea elettrica e i generatori diesel. Le tappe principali sono: l'inizio dello scavo ad agosto 2025, l'avvio della costruzione dell'impianto di lavorazione a settembre 2025 e la messa in funzione a dicembre 2026.

I costi diretti del progetto sono stati ridotti di 32,6 milioni di dollari, portandoli a 159,4 milioni, grazie a contratti a costo unitario e a un'ingegneria dettagliata. Una volta avviata la produzione commerciale, Silvercorp riceverà il 95% dei dividendi fino al recupero dell'investimento, dopodiché i profitti saranno divisi 75%/25% con Salazar.

Salazar Resources (SRLZF) ofrece una actualización sobre el proyecto de construcción de la mina El Domo, una empresa conjunta con Silvercorp Metals (con una participación del 75%) en la que Salazar posee un interés del 25% financiado. El proyecto apunta a iniciar la producción a finales de 2026 con un costo estimado de 240,4 millones de dólares, ligeramente inferior a la estimación del estudio de factibilidad de 2021 de 247,6 millones de dólares.

El plan de construcción incluye cinco paquetes clave de licitación que abarcan la preparación del sitio, la minería a cielo abierto, la construcción de la planta de procesamiento, la instalación de la línea eléctrica y los generadores diésel. Los hitos principales incluyen: inicio del desmonte en agosto de 2025, construcción de la planta de procesamiento a partir de septiembre de 2025 y puesta en marcha en diciembre de 2026.

Los costos directos del proyecto se han reducido en 32,6 millones de dólares a 159,4 millones mediante contratos por costo unitario y una ingeniería detallada. Una vez que comience la producción comercial, Silvercorp recibirá el 95% de los dividendos hasta recuperar la inversión, tras lo cual las ganancias se compartirán 75%/25% con Salazar.

Salazar Resources (SRLZF)는 Silvercorp Metals(75% 지분)와의 합작 투자인 El Domo 광산 건설 프로젝트에 대한 업데이트를 제공합니다. Salazar는 25%의 부담 지분을 보유하고 있습니다. 이 프로젝트는 2026년 말까지 생산 시작을 목표로 하며, 추정 비용은 2억 4,040만 달러로 2021년 타당성 조사에서 추정된 2억 4,760만 달러보다 다소 낮습니다.

건설 계획에는 부지 정비, 노천 채굴, 가공 공장 건설, 전력선 설치, 디젤 발전기 등 다섯 가지 주요 입찰 패키지가 포함됩니다. 주요 일정은 2025년 8월 스트리핑 시작, 2025년 9월 가공 공장 건설 착수, 2026년 12월 시운전입니다.

단가 계약과 상세 엔지니어링을 통해 프로젝트 직접 비용이 3,260만 달러 줄어든 1억 5,940만 달러로 감소했습니다. 상업 생산이 시작되면 Silvercorp는 투자 회수 시까지 배당금의 95%를 받으며, 이후 이익은 Salazar와 75%/25%로 나눕니다.

Salazar Resources (SRLZF) fournit une mise à jour sur le projet de construction de la mine El Domo, une coentreprise avec Silvercorp Metals (intérêt de 75 %) dans laquelle Salazar détient une participation portée de 25 %. Le projet vise un démarrage de la production d'ici fin 2026 avec un coût estimé à 240,4 millions de dollars, légèrement inférieur à l'estimation de l'étude de faisabilité de 2021 à 247,6 millions de dollars.

Le plan de construction comprend cinq principaux lots d'appel d'offres couvrant la préparation du site, l'exploitation à ciel ouvert, la construction de l'usine de traitement, l'installation de la ligne électrique et les générateurs diesel. Les étapes clés incluent : le début du décapage en août 2025, le début de la construction de l'usine de traitement en septembre 2025, et la mise en service en décembre 2026.

Les coûts directs du projet ont été réduits de 32,6 millions de dollars à 159,4 millions grâce à des contrats au coût unitaire et à une ingénierie détaillée. Une fois la production commerciale lancée, Silvercorp recevra 95 % des dividendes jusqu'au recouvrement de l'investissement, après quoi les bénéfices seront partagés 75 %/25 % avec Salazar.

Salazar Resources (SRLZF) gibt ein Update zum Bauprojekt der El Domo-Mine, einem Joint Venture mit Silvercorp Metals (75% Beteiligung), bei dem Salazar einen getragenen Anteil von 25% hält. Das Projekt zielt auf Produktionsbeginn Ende 2026 ab, mit geschätzten Kosten von 240,4 Millionen US-Dollar, etwas niedriger als die Schätzung der Machbarkeitsstudie von 2021 mit 247,6 Millionen US-Dollar.

Der Bauplan umfasst fünf wichtige Ausschreibungspakete, die Standortvorbereitung, Tagebau, Bau der Aufbereitungsanlage, Installation der Stromleitung und Dieselgeneratoren abdecken. Wichtige Meilensteine sind: Beginn der Abraumarbeiten im August 2025, Baubeginn der Aufbereitungsanlage im September 2025 und Inbetriebnahme im Dezember 2026.

Die direkten Projektkosten wurden durch Einheitspreisverträge und detaillierte Planung um 32,6 Millionen US-Dollar auf 159,4 Millionen US-Dollar gesenkt. Sobald die kommerzielle Produktion startet, erhält Silvercorp 95% der Dividenden bis zur Investitionsrückzahlung, danach werden die Gewinne 75%/25% mit Salazar geteilt.

Positive
  • Construction cost reduced by $32.6 million in direct costs through optimization
  • Project remains on schedule for production by end of 2026
  • Detailed engineering and construction planning completed with experienced contractors
  • 550,000 cubic metres of ore ready to support three years of production
Negative
  • Climate change impacts requiring additional diesel power generators
  • Increased contingency costs by $9.9 million
  • Owner's costs increased by $20 million from original estimate

Vancouver, British Columbia--(Newsfile Corp. - April 23, 2025) - SALAZAR RESOURCES LIMITED (TSXV: SRL) (OTCQX: SRLZF) (FSE: CCG) ("Salazar" or the "Company") provides an update on El Domo Construction.

Silvercorp Metals Inc. ("Silvercorp") and the Company are in a joint venture ("Joint Venture") for the development of the El Domo mine with Silvercorp holding a 75% interest and the Company a 25% carried interest. Silvercorp (TSX: SVM) (NYSE American: SVM) is operator of the Joint Venture and has been moving forward with construction of the El Domo mine. Silvercorp has recently provided an update to the Company on the development plans as the Joint Venture moves to bring El Domo into production.

The Joint Venture is targeting the start of production for the Project by the end of 2026 at an estimated cost of $240.4 million, comparable to the $247.6 million estimate in the feasibility study (NI 43-101 Technical Report - Feasibility Study - Curipamba El Domo Project, Central Ecuador) published in 2021 ("2021 Feasibility Study").

The Company holds a 25% free carried interest on the Project and, once commercial production is achieved, Silvercorp will receive 95% of the dividends from the Project until its aggregate investment, has been recouped minus the approximate Salazar carrying value of US$ 20 million, after which dividends will be shared on a 75%/25% pro-rata basis with Salazar. The payback time is estimated to be 2.6 years according to the 2021 Feasibility Study, which is bound to improve with this updated plan and budget.

The Company is thrilled to see the advances in the construction of the Project and is committed to continue supporting Silvercorp with its local expertise.

As discussed in its January 7, 2025 Press Release, the Joint Venture has been building upon the 2021 Feasibility Study, with work to date focusing on:

  1. Advanced Detailed Engineering for: a) Optimized design with Klohn Crippen Berger ("KCB") for the Tailings Storage Facilities ("TSF"), Saprolite Waste Dump ("SWD"), and non-contact water channels; b) Optimized open pit mine design for mining, stripping, and scheduling, and coordinated the mining schedule with ongoing tailings dam construction by internal mining engineers; and c) by Yantai Jinpeng Mining Machinery Co. Ltd and Yantai Orient Metallurgical Design and Research Institute Co., Ltd (together "Jinpeng"), a China certified Engineering Design, Manufacture and Construction Group which has provided design, equipment, and construction for mining process plants in China and internationally.
  1. Advanced Project Infrastructure for: a) Optimized designs for a new public bypass road and internal operational haul roads; b) Executed a powerline contract with the Ecuadorian state-owned power company (CNEL EP) including initiating bidding process for contractor selection; and c) permitting and sourcing for standby diesel power generators for the dry season, as climate change has impacted the power supply situation in Ecuador.
  1. Produced Project Materials Balance for: a) Bid Package 1: Construction of temporary camp, TSF to starter dam phase, SWD, non-contact water channels, internal haul roads, and preparation of the process plant site and permanent camp site; b) Bid Package 2: Open Pit Mining, stripping and ongoing tailings dam raises using stripped waste rocks; c) Bid Package 3: Construction of the process plant, tailings discharge and reclaim back water systems, water treatment plants, permanent camp, and other site infrastructures; d) Bid Package 4 for the construction of the Power line; and e) Bid Package 5 for the diesel power generators.

Capital Cost Estimate Details

The table below summarizes the schedule and costs to construct the El Domo Project:



Fiscal 2026Fiscal 2027Total


($ Million)($ Million)($ Million)
1Package #1 - Site preparation/Roads/Channel/TSF/SWD$29.2$18.2$47.4
2Package #2 - Open Pit Mining and Stripping7.032.039.0
3Package #3 - Processing Plant Construction and Equipment14.019.033.0
4Temporary and Permanent Camps2.05.07.0
5Packages #4,5 -Site Infrastructure (bypass roads, powerline, standby diesel generators, water treatment plant)16.017.033.0

Direct costs sub-total$68.2$91.2$159.4
6Owner's Contingency 13.618.331.9
7Owner's Cost12.018.030.0
8Value added tax (VAT)8.210.919.1

Total $102.0$138.4$240.4

 

Package #1 - Site Preparation/Roads/Channel/TSF

The commercial contract for Package #1 was awarded in January 2025 to CRCC 14 Bureau Group Co. Ltd. ("CRCC 14"), a company with a regional headquarters in Quito, and over ten years operating experience in Ecuador building infrastructure in open pit mines and in the heavy civil construction sector. CCRC 14 has been on-site conducting various earthworks since January 2025.

The estimated capital costs for Package #1 are based on the unit prices as indicated in the contract multiplied by the design quantities of each activity. The table below summarizes the estimated schedule and costs for Package #1.


Fiscal 2026Fiscal 2027Total

($ Million)($ Million)($ Million)
Package #1


Site Preparation10.4-10.4
TSF2.88.411.2
Roads5.73.08.7
Channels6.26.412.6
Other (SWD)4.10.44.5
Package #1$29.2$18.2$47.4

 

Package #2 - Open pit Mining and Stripping

The cost estimates are based on the optimized mine plan, which is based on the 2021 Feasibility Study, and the initial quotations received from interested contractors on a "Unit Cost" basis, that is the cost of drilling blasting and removing each cubic metre of rock a certain distance. The Company has not yet awarded the commercial contract for Package #2. The table below summarizes the estimated schedule and costs for Package #2.


Fiscal 2026Fiscal 2027Total

($ Million)($ Million)($ Million)
Package #2


Stripping5.524.029.5
Ore Mining-0.10.1
Other1.57.99.4
Package #2 - Open pit Mining and Stripping$7.0$32.0$39.0

 

The Joint Venture expects to commence stripping of the open pit in August 2025, and a total of 5.4 million cubic metres of sediments and waste rocks will be stripped among this 3.5 million cubic metres of non-acid generation (NAG) waste rocks will be stripped and used to build the starter dam and Stage 2 dam of the TSF, and 43,000 tonnes of ore to be produced by the end of 2026. With this stripping of waste rocks, ore in pit, ready to be mined, is expected to be 550,000 cubic metres to support three years of ore production.

Package #3 - Processing Plant Construction and Equipment

The Company has engaged Jinpeng to complete the detailed engineering design of the processing plant based on the 2021 Feasibility Study. Jinpeng is also finalizing the detailed flowsheet, equipment selection and cost estimates for the processing plant construction and equipment. The improvements from the design of the 2021 Feasibility Study are to build a steel-framed building to cover run of ore to avoid tropical storm leaching, and to cover all equipment and operational facilities with steel-framed building. The cost estimates are based on the engineering design, initial bidding price for major equipment from international vendors, market prices for minor equipment in China plus shipping cost, current construction cost in Ecuador.


Fiscal 2026Fiscal 2027Total

($ Million)($ Million)($ Million)
Package #3


Run of Mine Platform/Shack + Crushing 1.40.82.2
Grinding and Cyclone Facilities2.13.25.3
Flotation Workshop Facilities3.35.38.6
Concentrate/Tailings Dewatering Facility1.42.13.5
Process Water Supply/TSF Water Reclaim System1.01.62.6
Laboratory /Maintenance/Electrical/Automation1.92.54.4
General Layout Engineering0.50.71.2
Other 2.42.85.2
Package #3 - Processing plant construction and equipment$14.0$19.0$33.0

 

The total cost for the processing plant and equipment is estimated at $33.0 million. The major equipment bid process and ordering are expected to be completed by the end of May 2025. Construction of the main plant and auxiliary facilities are expected to commence in September 2025, with major equipment installation expected to commence in May 2026. The Joint Venture expects to complete construction and equipment installation by November 2026, with commissioning of the process plant occurring in December 2026.

Power line construction and Stand-by Diesel Power Generators

The Joint Venture is currently updating the engineering work for the power line construction and is in the process of selecting contractors to construct the power line. The construction of the power line is expected to be initiated in May 2025 and completed in 13-17 months. The Joint Venture has also sourced diesel power generators as standby and emergency power to satisfy Ecuador market conditions. The standby diesel generators are expected to be in operation before completion of the process plant.

Cost estimates comparison

Compared to the cost estimate of $247.6 million in the 2021 Feasibility Study, differences are:

  • Direct costs reduced by $32.6 million to $159.4 million from $192 million, due to savings by employing a Unit Cost contract and detailed engineering.
  • VAT reduced by $5.9 million to $19.1 million from $25 million due to reduction of direct costs; offset by,
  • Contingency increased by $9.9 million to $31.9 million from $22.0 million; and,
  • Owner's costs and burn rates increased by $20.0 million to $30.0 million from $10 million.

Guoliang Ma, P. Geo., Manager of Exploration and Resource of Silvercorp , is the Qualified Person for the Joint Venture and for the purposes of National Instrument 43-101 - Standards of Disclosure for Mineral Projects (''NI 43-101'') and has reviewed and approved the technical information contained in this news release.

About Salazar
Salazar Resources Limited is focused on creating value and positive change through discovery, exploration, and development in Ecuador. The team has an unrivalled understanding of the geology in-country and has played an integral role in the discovery of many of the major projects in Ecuador, including the two newest operating gold and copper mines. Salazar Resources has a wholly owned pipeline of copper-gold exploration projects across Ecuador with a strategy to make another commercial discovery and farm-out non-core assets. The Company actively engages with Ecuadorian communities and together with the Salazar family it co-founded The Salazar Foundation, an independent non-profit organization dedicated to sustainable progress through economic development. At its maiden discovery, Curipamba, Salazar Resources has a 25% stake fully carried through to production. The Company is in process of acquiring 100% of two copper-gold porphyry projects, Pijili and Santiago. For further information from Salazar Resources, please contact Nick DeMare, Director, at ndemare@chasemgt.com or at 604-685-9316. Please also visit the Salazar Resources website at www.salazarresources.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Forward-Looking Statements

This news release includes certain "forward-looking information" ("forward-looking statements") within the meaning of applicable Canadian securities legislation, including: the consummation and timing of the Transaction; and the anticipated benefits of the Transaction to Salazar and its shareholders.

All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as "expect", "plan", "anticipate", "estimate", "intend" or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.

Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond Salazar's control, including risks associated with or related to: the risks of not achieving all or any of the anticipated benefits of the proposed Transaction, or the risk that the anticipated benefits of the proposed Transaction may not be fully realized or take longer to realize than expected; the occurrence of any event, change or other circumstances that could give rise to the termination of the agreement between Silvercorp and Adventus; the risk that the proposed Transaction will not be consummated within the expected time period, or at all; the volatility of metal prices and Salazar's common shares; changes in tax laws; the dangers inherent in exploration, development and mining activities; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; environmental regulations or hazards and compliance with complex regulations associated with mining activities; the availability of financing; operations in Ecuador and the compliance with Ecuadorian laws, including risks related to changes in such laws and changing policies related to mining and local ownership requirements or resource nationalization generally; remote operations and the availability of adequate infrastructure; fluctuations in price and availability of energy and other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof; the reliance upon contractors, third parties and joint venture partners; challenges to title or surface rights; the dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or uninsured loss; adverse climate and weather conditions; litigation risk; community support for Salazar's operations, including risks related to strikes and the halting of such operations from time to time; conflicts with small scale miners; as well as other factors identified and as described in more detail in Salazar's filings with Canadian securities regulators, which may be viewed at www.sedarplus.ca.

Salazar's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. These assumptions and factors include, but are not limited to, assumptions and factors related to: Silvercorp and Adventus's ability to achieve timely satisfaction of conditions precedent to the Transaction; development and exploration activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; the availability and cost of inputs; the price and market for outputs; foreign exchange rates; taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions; and other assumptions and factors generally associated with the mining industry.

Salazar's forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. Salazar does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities Salazar will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/249445

FAQ

When will the El Domo mine project (SRLZF) begin production?

The El Domo mine project is targeting production start by the end of 2026, with plant commissioning scheduled for December 2026.

What is the total construction cost for SRLZF's El Domo project?

The total construction cost is estimated at $240.4 million, lower than the 2021 feasibility study estimate of $247.6 million.

How will profits be distributed between Silvercorp and Salazar Resources (SRLZF)?

Silvercorp will receive 95% of dividends until investment recovery, then profits will be shared 75% Silvercorp and 25% Salazar.

What is the expected payback period for the El Domo project (SRLZF)?

The payback period is estimated at 2.6 years according to the 2021 Feasibility Study, with potential for improvement under the updated plan.
Salazar Res Ltd

OTC:SRLZF

SRLZF Rankings

SRLZF Latest News

SRLZF Stock Data

16.18M
200.12M
19.58%
8.13%
Other Industrial Metals & Mining
Basic Materials
Link
Canada
Vancouver