Soluna Announces Monthly Business Update
Soluna Holdings (NASDAQ: SLNH) has released its December 2024 business update, highlighting significant achievements and project developments. The company reached a milestone of 100 GWh in curtailed energy monetization at Project Dorothy, equivalent to powering approximately 11,500 H100s annually.
Key developments include new AI partnerships with San Francisco Compute Company and Atlas Cloud, involving the deployment of Nvidia H100 GPUs. The company completed the final conversion and payoff of outstanding convertible notes and launched a partnership with Gynger for flexible AI financing.
Project updates include progress on Dorothy 1A and 1B (25MW each), with new customer deployments and resolved transformer issues. Dorothy 2 (48MW) continues construction with Phase 1 (16MW) advancement. The AI pipeline now exceeds 864 H100 GPUs, with Project Ada securing new commitments and Project Sophie operating at full capacity.
Soluna Holdings (NASDAQ: SLNH) ha pubblicato il suo aggiornamento aziendale di dicembre 2024, evidenziando risultati significativi e sviluppi nei progetti. L'azienda ha raggiunto un traguardo di 100 GWh in monetizzazione dell'energia curtailata presso il Progetto Dorothy, equivalente a fornire energia a circa 11.500 H100 all'anno.
Sviluppi chiave includono nuove collaborazioni AI con San Francisco Compute Company e Atlas Cloud, che comportano l'implementazione di GPU Nvidia H100. L'azienda ha completato la conversione finale e il rimborso delle note convertibili outstanding e ha avviato una partnership con Gynger per finanziamenti AI flessibili.
Gli aggiornamenti del progetto includono progressi su Dorothy 1A e 1B (25MW ciascuno), con nuove implementazioni per i clienti e la risoluzione di problemi con i trasformatori. Dorothy 2 (48MW) continua la costruzione con l'avanzamento della Fase 1 (16MW). Il pipeline AI ora supera le 864 GPU H100, con il Progetto Ada che ottiene nuovi impegni e il Progetto Sophie che opera a piena capacità.
Soluna Holdings (NASDAQ: SLNH) ha lanzado su actualización comercial de diciembre de 2024, destacando logros significativos y desarrollos de proyectos. La compañía alcanzó un hito de 100 GWh en monetización de energía restringida en el Proyecto Dorothy, lo que equivale a alimentar aproximadamente 11,500 H100 anualmente.
Los desarrollos clave incluyen nuevas asociaciones de IA con San Francisco Compute Company y Atlas Cloud, que implican el despliegue de GPUs Nvidia H100. La empresa completó la conversión final y el pago de notas convertibles pendientes y lanzó una asociación con Gynger para financiamiento flexible en IA.
Las actualizaciones del proyecto incluyen avances en Dorothy 1A y 1B (25MW cada uno), con nuevas implementaciones de clientes y problemas de transformadores resueltos. Dorothy 2 (48MW) continúa la construcción con el avance de la Fase 1 (16MW). La línea de AI ahora supera las 864 GPUs H100, con el Proyecto Ada asegurando nuevos compromisos y el Proyecto Sophie operando a plena capacidad.
솔루나 홀딩스 (NASDAQ: SLNH)는 2024년 12월 비즈니스 업데이트를 발표하며 주요 성과와 프로젝트 발전을 강조했습니다. 이 회사는 프로젝트 도로시에서 100GWh의 에너지 절감 수익화라는 이정표에 도달했으며, 이는 연간 약 11,500개의 H100을 가동할 수 있는 양입니다.
주요 발전 사항으로는 샌프란시스코 컴퓨트 컴퍼니 및 아틀라스 클라우드와의 새로운 AI 파트너십을 포함하며, Nvidia H100 GPU의 배포가 포함됩니다. 이 회사는 미불 조건부 채권의 최종 전환 및 상환을 완료하고, 유연한 AI 금융을 위한 Gynger와의 파트너십을 시작했습니다.
프로젝트 업데이트에는 도로시 1A 및 1B(각각 25MW)의 진행 상황이 포함되며, 새로운 고객 배치와 변압기 문제의 해결이 포함됩니다. 도로시 2(48MW)는 1단계(16MW)의 발전과 함께 건설을 계속하고 있습니다. AI 파이프라인은 현재 864개의 H100 GPU를 초과하며, 프로젝트 아다에서는 새로운 약속을 확보하고, 프로젝트 소피는 최대 용량으로 운영되고 있습니다.
Soluna Holdings (NASDAQ: SLNH) a publié sa mise à jour d'entreprise de décembre 2024, mettant en avant des réalisations significatives et des développements de projets. L'entreprise a atteint un cap de 100 GWh en monétisation de l'énergie réduite dans le Projet Dorothy, ce qui équivaut à alimenter environ 11 500 H100 par an.
Les développements clés comprennent de nouveaux partenariats avec San Francisco Compute Company et Atlas Cloud pour le déploiement de GPU Nvidia H100. L'entreprise a finalisé la conversion et le remboursement des notes convertibles en circulation et a lancé un partenariat avec Gynger pour un financement flexible en IA.
Les mises à jour de projet incluent des progrès sur Dorothy 1A et 1B (25MW chacun), avec de nouvelles installations pour les clients et des problèmes de transformateurs résolus. Dorothy 2 (48MW) continue sa construction avec l'avancement de la phase 1 (16MW). Le pipeline AI dépasse maintenant 864 GPU H100, avec le Projet Ada sécurisant de nouveaux engagements et le Projet Sophie opérant à pleine capacité.
Soluna Holdings (NASDAQ: SLNH) hat sein Geschäftsupdate für Dezember 2024 veröffentlicht und dabei bedeutende Erfolge und Entwicklungen in Projekten hervorgehoben. Das Unternehmen hat einen Meilenstein von 100 GWh an monetarisierter, reduzierter Energie beim Projekt Dorothy erreicht, was etwa 11.500 H100s jährlich entspricht.
Wichtige Entwicklungen umfassen neue KI-Partnerschaften mit San Francisco Compute Company und Atlas Cloud, die den Einsatz von Nvidia H100 GPUs beinhalten. Das Unternehmen hat die endgültige Umwandlung und Rückzahlung ausstehender wandelbarer Schuldverschreibungen abgeschlossen und eine Partnerschaft mit Gynger für flexible KI-Finanzierungen gestartet.
Projekt-Updates umfassen Fortschritte bei Dorothy 1A und 1B (jeweils 25 MW), mit neuen Kundeninstallationen und gelösten Transformatorproblemen. Dorothy 2 (48 MW) wird weiterhin gebaut, wobei die Phase 1 (16 MW) voranschreitet. Die KI-Pipeline übersteigt jetzt 864 H100 GPUs, wobei Projekt Ada neue Verpflichtungen sichert und Projekt Sophie mit voller Kapazität arbeitet.
- Achieved 100 GWh milestone in curtailed energy monetization
- Secured new AI partnerships with SF Compute Company and Atlas Cloud
- Completed payoff of outstanding convertible notes
- AI GPU pipeline exceeds 864 H100 units
- Project Sophie operating at full capacity
- Expanding customer relationships with Bit Digital and Bitmine Immersion Technologies
- Transformer failure caused 3 weeks downtime for 2 MDCs at Project Dorothy 1B
- Planned 1-week outages for Dorothy 1A and 1B in January for substation work
Insights
The monthly update reveals several significant operational developments and strategic expansions. The milestone of 100 GWh in curtailed energy monetization at Project Dorothy demonstrates substantial operational scale, equivalent to powering 11,500 H100 GPUs annually. This achievement validates Soluna's business model of utilizing curtailed energy for computing applications.
The company's expansion into AI infrastructure through deals with San Francisco Compute Company and Atlas Cloud, involving 64 Nvidia H100 GPUs with potential for scaling, represents a strategic pivot toward higher-margin AI computing services. The AI pipeline exceeding 864 H100 GPUs indicates strong market demand and potential revenue growth.
The completion of convertible notes payoff strengthens the balance sheet, while the Gynger partnership provides flexible financing options for AI enterprises, potentially accelerating customer acquisition. However, operational challenges like the transformer failure at Dorothy 1B and planned outages could temporarily impact near-term revenue.
The diversification strategy from pure Bitcoin mining to include AI computing infrastructure marks a pivotal technological transition. The partnership with HPE GreenLake and the deployment of Nvidia H100 GPUs - currently the most advanced AI accelerators - positions Soluna at the forefront of sustainable AI infrastructure providers.
The development progress across multiple projects, particularly Project Dorothy 2 (48 MW) and Project Grace's microgrid concept, demonstrates scalable infrastructure deployment capabilities. The integration of next-generation S21 Bitcoin mining units indicates technological competitiveness in the mining segment.
The expanding AI pipeline and customer base, including Fluidstack's intent to reserve 512 H100 GPUs, suggests strong market validation of Soluna's hybrid computing infrastructure model. This technological diversification reduces dependency on volatile Bitcoin mining revenues while capitalizing on the growing AI computing demand.
Achieves Milestone of 100 GWh in Curtailed Energy Monetization
The Company has provided the following Corporate and Site Updates.
Key Company Metrics:
The monthly metrics are now available here.
Corporate Highlights:
- AI Deal Signed with San Francisco Compute Company: Soluna will deliver custom AI cloud solutions to its first customer following strategic collaboration with Hewlett Packard Enterprise (HPE) GreenLake. Learn more here.
- AI Deal Signed with Atlas Cloud: Soluna will provide Atlas with 64 Nvidia H100 GPUs and potentially scale to more to support Atlas’ advanced AI video processing workloads. Learn more here.
- Convertible Notes, Final Convert, and Payoff: Soluna announced the completion of a final conversion and payoff of outstanding convertible notes. Learn more here.
- Flexible Financing for Sustainable AI: Soluna launched its partnership with Gynger to offer flexible financing options for AI enterprises. Get started here.
- Advisory Board: Soluna announced the appointment of data center expert Ernest Popescu to the Advisory Board. Learn more here.
- New Podcast: Soluna’s new limited series explores the intersection of AI and sustainability. Listen to it here.
- Curtailed Energy Milestone: As of November, Project Dorothy reached a milestone of over 100GWh of curtailed energy monetization. This is equivalent to powering approximately 11,500 H100s for a year.
- New Video: CEO John Belizaire shares Soluna’s story and the future of Renewable Computing from the grounds of Project Dorothy. Watch it here.
Key Project Updates:
Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy 1B (25 MW, Bitcoin Prop-Mining):
- Two new customer deployments totaling 20 MW of upgraded equipment are nearing completion at Project Dorothy 1A.
- Transformer failure impacted self-mining hashrate, incurring 3 weeks of downtime for 2 MDCs at Project Dorothy 1B. This issue has been resolved.
- Project Dorothy 1A and 1B will each incur a 1-week outage in mid-January to support the substation interconnection work planned and required for Project Dorothy 2.
Project Dorothy 2 (48 MW, Bitcoin Hosting):
- The substation interconnection planning is complete with the electrical tie-in scheduled for mid-January.
- Phase 1 construction – the first 16 MW – continues to progress as major electrical equipment for each MDC is in the process of being set.
- Phase 1 commissioning preparation is underway with the core network installation planned for mid-January and the interviewing of full-time staff in process.
- The latest photos of the construction progress can be found here.
Project Grace (2 MW at Dorothy 2, AI Cloud/Hosting):
- Microgrid concept design, Phase 1 is nearing completion. This will inform timelines and layout.
- Helix Phase 1 concept design is nearing completion.
Project Ada (1 MW, AI Cloud with HPE):
- Fluidstack signed a Letter of Intent to reserve 512 H100 GPUs by the end of January or early February.
- SFCompute usage continued to ramp through the holidays, and the first revenue report is due in mid-January.
- 128 additional H100 GPUs are slated for a new serverless offering with Atlas Cloud. We are negotiating terms.
- Proposals were sent to several new prospects for over 544 GPUs with 3, 6, and 12-month terms.
- The AI pipeline now conservatively exceeds 864 H100 GPUs.
Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI Hosting):
- Site operations remain very strong and at full capacity.
Project Kati (166 MW, Bitcoin Hosting and AI):
- Requests for quotes (RFQ) have been sent on long-lead electrical infrastructure.
- The design scope is being finalized for the first 83 MW of Bitcoin Hosting with an EPC bid process to be facilitated in February.
- Final round of negotiations are underway with the landowner and expect to complete by the end of January.
Customer Success:
- Agreement reached and in the process of deploying a 3rd expansion request with customer Bit Digital.
- Deploying the first batch of next-generation units (S21s) with upgraded site infrastructure at Project Dorothy.
- Agreement reached and in the process of deploying a 2nd expansion request with customer Bitmine Immersion Technologies.
- Request for proposals for Dorothy 2 Bitcoin Hosting launched.
View Soluna’s recent AMA here.
View Soluna 2024 Earnings Power Presentation here.
Safe Harbor Statement
This announcement contains forward-looking statements. These statements are made under the "safe harbor" provisions of the
Non-GAAP Measures
In addition to figures prepared in accordance with GAAP, Soluna from time to time presents alternative non-GAAP performance measures, e.g., EBITDA, adjusted EBITDA, adjusted net profit/loss, adjusted earnings per share, free cash flow, both on a company basis and on a project-level basis. Project-level measures may not take into account a full allocation of corporate expenses. These measures should be considered in addition to, but not as a substitute for, the information prepared in accordance with GAAP. Alternative performance measures are not subject to GAAP or any other generally accepted accounting principle. Other companies may define these terms in different ways. See our annual report on Form 10-K for the year ended December 31, 2023, for an explanation of how management uses these measures in evaluating its operations.
About Soluna Holdings, Inc (SLNH)
Soluna is on a mission to make renewable energy a global superpower using computing as a catalyst. The company designs, develops, and operates digital infrastructure that transforms surplus renewable energy into global computing resources. Soluna’s pioneering data centers are strategically co-located with wind, solar, or hydroelectric power plants to support high-performance computing applications including Bitcoin Mining, Generative AI, and other compute-intensive applications. Soluna’s proprietary software MaestroOS(™) helps energize a greener grid while delivering cost-effective and sustainable computing solutions, and superior returns. To learn more visit solunacomputing.com. Follow us on X (formerly Twitter) at @SolunaHoldings.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250108118322/en/
Sam Sova
Partner and CEO
SOVA
Sam@letsgosova.com
Source: Soluna Holdings, Inc.
FAQ
What milestone did Soluna (SLNH) achieve in curtailed energy monetization?
How many Nvidia H100 GPUs is Soluna (SLNH) providing to Atlas Cloud?
What is the current capacity of Soluna's (SLNH) Project Dorothy 2?
How large is Soluna's (SLNH) current AI GPU pipeline?