Rupert Resources Reports Preliminary Economic Assessment for Ikkari Outlining After-Tax NPV of US$1.6B
Rupert Resources Ltd announces promising results from its Preliminary Economic Assessment (PEA) for the 100% owned Rupert Lapland Project in Finland. The PEA highlights an after-tax Net Present Value (NPV) of $1.6 billion and an Internal Rate of Return (IRR) of 46%, with a payback period of just 2 years. The project boasts a mine life of 22 years, aiming for an average annual gold production of 200,000 ounces. The Ikkari deposit’s updated estimate upgraded 84% to Indicated resources, indicating high-quality mineralization and optimized cash flow potential.
- After-tax NPV of $1.6 billion and IRR of 46%, indicating robust returns.
- Average annual gold production projected at 200,000 ounces over a 22-year mine life.
- Ikkari deposit shows significant resource upgrade, with 84% in the Indicated category.
- None.
Figure 1. Project production profile (Graphic: Business Wire)
{All figures are in US$ unless otherwise noted}
PEA Highlights:
-
High-confidence, de-risked resource: Flagship Ikkari deposit’s updated Mineral Resource Estimate upgrades
84% of ounces to the Indicated resource category, and defines a cohesive deposit with broad intervals of consistent high-grade gold. - Phased mine plan optimizing near-term cash flow: Open-pit operation at Ikkari in first 11 years, transitioning to Ikkari underground (years 10-23) and Pahtavaara concentrate (years 12 to 24).
-
Robust returns and fast-track to payback: After-tax Net Present Value (“NPV”) (
5% discount) of with unlevered Internal Rate of Return (“IRR”) of$1.6 billion 46% and payback after only two years, assuming a gold price of per troy ounce (“oz”).$1,650 - Long life: 22-year life of mine (“LOM”) includes recovered gold of 4.25 million ounces with average annual production of 200,000 ounces. Open pit operation is expected to support average annual production of 220,000 ounces in years one to 11.
-
High margin production profile: Expected lowest quartile all-in sustaining cost (“AISC”) of
/oz over LOM, and$759 /oz during open-pit operation. Low sensitivity to cut-off grade and low initial strip ratio.$596
“This PEA study indicates exceptionally high-margin and meaningful returns on a robust project. The results are a testament to both the quality of the asset and our technical team. In only three years, we’ve gone from discovery hole to a preliminary study outlining an after-tax NPV of
Study team and cautionary statement
The PEA study team was led by Tetra Tech, a global provider of consulting and engineering services for mining projects. Tetra Tech was supported by
The Mineral Resource estimate included in the PEA is reported according to the classification criteria set out in the
The results of the PEA will be set forth in an independent technical report prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) which will be filed on SEDAR under the Company’s profile within 45 days of the date of this news release.
Readers are cautioned that the PEA summarized in this press release is intended to provide only an initial high-level review of the project potential and that the PEA is preliminary in nature and is intended to provide an initial assessment of the project’s economic potential and development options. The PEA mine schedule and economic assessment includes numerous assumptions and is based on both Indicated and Inferred mineral resources. Inferred resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the project economic assessments described herein will be achieved or that the PEA results will be realized. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. Additional exploration will be required to potentially upgrade the classification of the Inferred Mineral Resources to be considered in future advanced studies.
Summary
Table 1. Project production summary
Years 1 to 11 |
LOM (22 years) |
||
Milled tonnes |
Million tonnes |
37.9 |
71.6 |
Mill throughput |
Million tonnes per annum |
3.5 |
3.5 |
Strip ratio |
Waste : Ore |
3.6 |
4.6 |
Average processed grade |
Grams per tonne (gold) |
2.1 |
1.9 |
Average metallurgical recovery |
% |
95 |
95 |
Average annual gold production |
000 troy ounces |
220 |
200 |
Recovered gold |
Million troy ounces |
2.4 |
4.2 |
Total Cash Cost |
$ / troy ounce |
501 |
667 |
Sustaining capital |
$ / troy ounce |
95 |
93 |
All in Sustaining Cost (AISC) |
$ / troy ounce |
596 |
759 |
As per the World Gold guidance (Gold All in Sustaining Costs | Gold AISC |
Table 2. Project economics
Life of mine |
Years |
22 |
Net Present Value ( |
USD million |
1,600 |
Internal rate of return (unlevered) |
% |
46 |
Payback |
Years |
2.0 |
Capital expenditure (Initial) |
USD million |
405 |
Capital expenditure (Sustaining) |
USD million |
395 |
Revenue |
USD million |
6,955 |
Operating cost |
USD million |
2,775 |
Free cash (after tax) |
USD million |
2,710 |
Table 3. Project operating cost
Life of mine operating cost |
USD / tonne milled |
USD / oz |
Mining |
18.1 |
333 |
Water treatment |
1.4 |
26 |
Concentrate freight |
0.1 |
2 |
Processing |
10.9 |
204 |
Tailings |
1.6 |
28 |
Closure fund |
0.8 |
15 |
G&A |
2.4 |
44 |
Freight/Refining |
0.1 |
3 |
Royalty |
0.7 |
12 |
Total Cash Costs |
36.1 |
667 |
Table 4. Project capital costs
Initial capex |
USD millions |
Mining o/p pre-production |
16.6 |
Process Plant |
131.0 |
Civils and infrastructure |
29.5 |
Water treatment |
96.4 |
Tailings |
20.4 |
First fills & spares |
10.0 |
Owner’s Costs |
20.0 |
Closure bond |
37.2 |
Contingency |
43.5 |
Total initial capex |
404.6 |
Sustaining capex |
USD millions |
Pahtavaara initial capex |
41.0 |
Underground mining |
178.8 |
Water treatment |
34.0 |
Tailings & waste dump |
34.9 |
Plant sustaining |
101.0 |
Pahtavaara closure bond |
5.0 |
Total |
394.7 |
Table 5. Model inputs
Assumption |
Unit |
Value |
Gold price |
USD / troy ounce |
1650 |
Exchange rate |
EUR / USD |
1:1 |
Corporate tax rate |
% |
20 |
Mining
- 11 year open pit operation at Ikkari, followed by an 11 year underground operation
- ROM feed supplemented by Pahtavaara 11g/t Au concentrate from year 12
- Low initial strip ratio of 1.6, 3.6 average over life of Ikkari open pit.
The PEA considers that Ikkari will be initially developed as an open pit with a target production rate of 3.5 Mtpa of plant feed. As the open pit reaches the end of its life (after 11 years) the underground development will be completed so that the underground operation can continue as the open pit is depleted. The transition point between open pit and underground operations was determined by operating costs as well as the limitation of the current exploration permit boundary. Open pit mining at Ikkari is expected to utilise a conventional shovel and truck configuration (140 tonne medium sized haul trucks matched with 300 tonne hydraulic excavators). Underground mining at Ikkari was modelled assuming the sub-level caving method. The mine at Pahtavaara will be re-developed as an open pit and underground mine (employing the long hole open stoping method) to produce a high-grade concentrate which will then be hauled by road to the Ikkari plant for final processing.
Table 6. PEA Ikkari open pit strip ratios
OP stage |
Strip ratio (waste : ore) |
1 |
1.6 |
2 |
2.7 |
3a |
5 |
3b |
5.5 |
Total |
3.6 |
Metallurgy and processing
- 3.5Mtpa mill capacity with conventional flow sheet
-
Testwork supports overall recovery of
95% - P80 grind size of 175 micron and grinding energy of 15.5kwh/t indicating ore is moderately hard
A new plant was envisaged by the study to process 3.5Mtpa of run-of-mine (ROM) ore from the Ikkari open pit and underground at an average grade of 1.82g/t Au (including processing low grade stockpiles towards the end of life of mine). Testwork showed the gold at Ikkari is non-refractory and occurs in the native form or associated with pyrite. The process considered comprises crushing and grinding to reduce the RoM material to a characteristic grind (P80) of 175 microns (µ), and a gravity circuit to recover the native gold. The pyrite associated gold will be recovered by flotation and fed, with the re-pulped concentrate from Pahtavaara, into the leach circuit where lime and cyanide are added in the presence of air to extract the gold. The gold will be then recovered in an adsorption, desorption, and recovery (ADR) circuit. The leach tails will be treated to remove cyanide and filtered for co-disposal with waste rock. The liquor recovered from the filtration is treated prior to re-use. See flowsheet (Figure 4).
The Pahtavaara ROM ore would be processed through a 0.5Mtpa gravity and flotation concentration facility that is envisaged to be expanded to 0.75Mtpa after 7 years of operation. The resulting high-grade concentrate product would be fed in to the Ikkari CIL circuit for gold recovery to dore.
Access and infrastructure
-
All infrastructure located on
100% Rupert held property - Co-disposal of waste rock and tailings
- Access to renewable power
Access
Ikkari is well supported by existing infrastructure and is accessed by tarmac and a 5km gravel road from the towns of Kittilä (50km west) and Sodankylä (40km east) both of which provide support services and labour to two existing mines in the area.
Co-disposal of mine waste and tailings
Mine waste and tailings are planned to be combined and disposed of together to increase physical and chemical stability of the waste. Initial studies suggest that the potential for acid generation could be significantly reduced by the buffering effect on acid solutions by carbonates present in the Ikkari rock and lime in the leach tails. Detailed waste material characterisation studies are underway for optimization of the long-term storage facility design parameters for construction, operation and eventual closure.
Hydrogeology & Water treatment
Initial hydrogeological studies have been undertaken at the Ikkari project site to formulate a management plan. To reduce contact water, surface water flows will be diverted where possible to avoid the open pit, plant site and waste facilities and a series of dewatering bores would be installed to reduce water flows into the mining operation. All water that comes in contact with the operation will be collected in lined storage dam structures and treated in a water treatment facility to remove potential contaminants before discharge via pipelines to nearby water courses. Further hydrogeological studies are being undertaken as part of data collection for future studies.
The plant design envisages water to be recirculated within the plant to minimize water consumption with water recovered from the cyanide destruction filtration to be treated in the water treatment area. Treated water is to be used for the re-pulping of the Pahtavaara concentrate and for reagent make-up. Brine produced by the water treatment plant will be added to the cyanide destruction tailings.
Power
A 220kV power transformer substation is located 9km from Ikkari that can be used as a connection point to the national grid for a 110 kV power line to the Ikkari minesite. A power surplus is envisaged in Lapland towards the end of the decade, with a significant contribution expected from renewables.
Permitting & Stakeholder Engagement
Resource
The updated Ikkari Mineral Resource Estimate is based on 73,000 metres of drilling to
The consolidated global resource includes Ikkari, Pahtavaara and a maiden gold Mineral Resource Estimate from Heinä Central. The Heinä Central resource is not included in the PEA mining inventory. Our global consolidated resource now comprises 48.3 Mt at 2.5g/t Au for 3.86 million ounces in the Indicated category and 20Mt at 1.9g/t Au for 1.26 million Inferred ounces (see table 7).
Upside and optimisation
The PEA results provide a high-level initial estimate of the potential economic value of the mineral resources discovered to date. As per the press release dated
Work programmes either already underway or to be completed over the coming year also include condemnation drilling, auger drilling to better define the bedrock-till interface, soil testing, expanded geotechnical data collection for pit slope and underground mine optimisation, waste characterisation testwork, stage 4 metallurgical testwork, stage 2 hydrogeological studies and completion of our third continuous year of extensive environmental surveys.
Table 7.
Classification |
Target Area |
Mining
|
Cut-off
|
Tonnage
|
Gold grade |
Gold contained |
|
Au (g/t) |
Kg |
Ounces |
|||||
Indicated |
|
0.5 |
30,000,000 |
2.5 |
75,000 |
2,400,000 |
|
Ikkari |
Underground |
1.0 |
16,500,000 |
2.4 |
40,000 |
1,280,000 |
|
Total |
46,400,000 |
2.5 |
110,000 |
3,680,000 |
|||
|
0.5 |
900,000 |
2.2 |
1,900 |
60,000 |
||
Pahtavaara |
Underground |
1.5 |
1,000,000 |
3.7 |
3,700 |
120,000 |
|
Total |
1,900,000 |
3.0 |
5,600 |
180,000 |
|||
Indicated Total |
48,300,000 |
2.5 |
120,000 |
3,860,000 |
|||
Inferred |
|
0.5 |
3,100,000 |
1.5 |
4,800 |
150,000 |
|
Ikkari |
Underground |
1.0 |
8,700,000 |
2.0 |
17,000 |
550,000 |
|
Total |
11,800,000 |
1.9 |
22,000 |
710,000 |
|||
Pahtavaara |
|
0.5 |
3,700,000 |
1.6 |
5,900 |
190,000 |
|
Underground |
1.5 |
2,200,000 |
3.1 |
6,800 |
220,000 |
||
Total |
5,900,000 |
2.1 |
13,000 |
410,000 |
|||
Heinä Central
|
|
0.5 |
2,200,000 |
1.7 |
3,800 |
120,000 |
|
Underground |
1.2 |
400,000 |
2.1 |
900 |
30,000 |
||
Total |
2,700,000 |
1.8 |
4,700 |
150,000 |
|||
Inferred Total |
20,400,000 |
1.9 |
39,000 |
1,260,000 |
The Mineral Resource estimate included in the Preliminary Economic Assessment (“Study” or “PEA” is reported according to the classification criteria set out in the
Table 8a. Ikkari Mineral Resource Estimate Sensitivity Tables
Classification |
|
Cut-off |
Tonnage |
Grade |
Gold |
|
Au (g/t) |
(Mt) |
Au (g/t) |
Kg |
Ounces |
||
Indicated |
|
0.3 |
33 300 000 |
2.3 |
75 900 |
2 440 000 |
0.4 |
31 700 000 |
2.4 |
75 300 |
2 420 000 |
||
0.5 |
30 000 000 |
2.5 |
74 500 |
2 400 000 |
||
0.6 |
28 100 000 |
2.6 |
73 500 |
2 360 000 |
||
0.7 |
26 400 000 |
2.7 |
72 400 |
2 330 000 |
||
Underground |
0.6 |
24 700 000 |
1.9 |
46 200 |
1 490 000 |
|
0.8 |
19 900 000 |
2.2 |
42 900 |
1 380 000 |
||
1 |
16 500 000 |
2.4 |
39 800 |
1 280 000 |
||
1.2 |
13 900 000 |
2.7 |
37 000 |
1 190 000 |
||
Inferred |
|
0.3 |
3 900 000 |
1.3 |
5 100 |
160 000 |
0.4 |
3 500 000 |
1.4 |
5 000 |
160 000 |
||
0.5 |
3 100 000 |
1.5 |
4 800 |
150 000 |
||
0.6 |
2 700 000 |
1.7 |
4 600 |
150 000 |
||
0.7 |
2 400 000 |
1.8 |
4 300 |
140 000 |
||
Underground |
0.6 |
14 900 000 |
1.5 |
22 000 |
710 000 |
|
0.8 |
11 100 000 |
1.7 |
19 300 |
620 000 |
||
1 |
8 700 000 |
2 |
17 200 |
550 000 |
||
1.2 |
6 800 000 |
2.2 |
15 100 |
490 000 |
Table 8b. Pahtavaara Mineral Resource Estimate Sensitivity Table
Classification |
|
Cut-off |
Tonnage |
Grade |
Gold |
|
Au (g/t) |
(Mt) |
Au (g/t) |
Kg |
Ounces |
||
Indicated |
|
0.3 |
1 100 000 |
1.8 |
2 000 |
64 000 |
0.4 |
1 000 000 |
2 |
2 000 |
63 000 |
||
0.5 |
900 000 |
2.2 |
1 900 |
62 000 |
||
0.6 |
800 000 |
2.3 |
1 900 |
60 000 |
||
0.7 |
700 000 |
2.5 |
1 800 |
59 000 |
||
Underground |
1 |
1 500 000 |
2.8 |
4 400 |
140 000 |
|
1.5 |
1 000 000 |
3.7 |
3 700 |
120 000 |
||
2 |
700 000 |
4.6 |
3 200 |
100 000 |
||
2.5 |
500 000 |
5.5 |
2 800 |
90 000 |
||
Inferred |
|
0.3 |
4 700 000 |
1.3 |
6 300 |
200 000 |
0.4 |
4 200 000 |
1.5 |
6 100 |
200 000 |
||
0.5 |
3 700 000 |
1.6 |
5 900 |
190 000 |
||
0.6 |
3 300 000 |
1.7 |
5 700 |
180 000 |
||
0.7 |
3 000 000 |
1.8 |
5 500 |
180 000 |
||
Underground |
1 |
3 900 000 |
2.3 |
8 900 |
290 000 |
|
1.5 |
2 200 000 |
3.1 |
6 800 |
220 000 |
||
2 |
1 400 000 |
3.9 |
5 400 |
170 000 |
||
2.5 |
900 000 |
4.8 |
4 400 |
140 000 |
Please refer to Cautionary Note regarding forwards looking statement for the Mineral Resource cut-off assumptions
Qualified Person Statement
The PEA was prepared by Tetra Tech for
About
About Tetra Tech
Tetra Tech is a leading provider of high-end consulting and engineering services for projects globally. With 21,000 associates and 450 offices worldwide, Tetra Tech provides clear solutions to complex problems in water, environment, infrastructure, resource management, energy, and international development. For more information about Tetra Tech, please visit www.tetratech.com
Neither the
Cautionary Note Regarding Forward Looking Statements
This press release contains statements which, other than statements of historical fact constitute “forward-looking statements” within the meaning of applicable securities laws, including statements with respect to: results of exploration activities and mineral resources. The words “may”, “would”, “could”, “will”, “intend”, “plan”, “anticipate”, “believe”, “estimate”, “expect” and similar expressions, as they relate to the Company, are intended to identify such forward-looking statements. Investors are cautioned that forward-looking statements are based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. These factors include the general risks of the mining industry, as well as those risk factors discussed or referred to in the Company's annual Management's Discussion and Analysis for the year ended
The Mineral Resource estimate included in the Preliminary Economic Assessment (“Study” or “PEA” is reported according to the clarification criteria set out in the
The results of the PEA will be set forth in an independent technical report prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) which will be filed on SEDAR under the Company’s profile within 45 days of the date of this news release.
Readers are cautioned that the PEA is preliminary in nature and is intended to provide an initial assessment of the project’s economic potential and development options. The PEA mine schedule and economic assessment includes numerous assumptions and is based on both Indicated and Inferred Mineral Resources. Inferred Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA results will be realized. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. Additional exploration will be required to potentially upgrade the classification of the Inferred Mineral Resources to be considered in future advanced studies.
The Mineral Resource estimate for the Project is reported in accordance with National Instrument 43-101 (“NI 43-101”) and has been estimated using the
The effective date of the 2022 Mineral Resource Estimate for Ikkari is
The effective date of the 2022 Mineral Resource Estimate for Pahtavaara is
The effective date of the 2022 Mineral Resource Estimate for Heinä Central is
View source version on businesswire.com: https://www.businesswire.com/news/home/20221128005144/en/
Chief Executive Officer
jwithall@rupertresources.com
Head of Corporate Development
tcredland@rupertresources.com
Tel: +1 416-304-9004
Web: http://rupertresources.com/
Source:
FAQ
What are the PEA highlights for Rupert Resources Ltd's project RUPRF?
How long is the mine life for Rupert Resources' Rupert Lapland Project?
What is the production target for the Ikkari gold discovery?