O3 Mining Releases Outlook 2023
O3 Mining Inc. (TSXV: OIII, OTCQX: OIIIF) has outlined its strategic outlook for 2023 along with a review of 2022's achievements. Key highlights include a 29% increase in the measured and indicated (M&I) open-pit resource at the Marban Engineering Project, totaling 2.3 million ounces of gold. The company is set to commence a Feasibility Study (FS) in H1 2023 and plans to execute 26,000 metres of drilling to extend mine life. The corporation is committed to sustainable mining practices, continuing its collaboration with First Nations, and enhancing stakeholder engagement.
- 29% increase in M&I open-pit resource at Marban to 2.3 million oz.
- Initiation of Feasibility Study planned for H1 2023.
- 26,000 metres of drilling planned for 2023 to enhance project value.
- Robust post-tax NPV of C$463 million and IRR of 23.2% from the PFS.
- None.
TSXV:OIII | OTCQX:OIIIF -
"In 2022 our team set very ambitious goals to maximize the value for our shareholders and stakeholders and show that Marban can be a profitable standalone project. The team's tireless efforts to deliver on all milestones highlighted in 2022, show our commitment to our shareholders and our belief in this project. With a positive market outlook for 2023, we look forward to starting the Feasibility Study ("FS"), as well as unveiling Marban's growth potential by engaging in exploration activities over our 8,500-hectare property. We will continue to deploy our participatory approach with the authorities and stakeholders in the development of the
- Updated resource at Marban Engineering – Increase in M&I open-pit resource by 520,000 oz (+
29% ), bringing the total M&I open-pit mineral resource to 2.3 million ounces gold at an average grade of 1.07 g/t Au (Press Release –March 1, 2022 ). - Secured prospective ground near the
Marban Engineering Project and consolidated the Corporation's position in the district - Acquisition of the East-West property from Emgold, located 200 metres from the Marban PEA pit edge, allows for amplification of brownfield exploration and potential for new discoveries (Press Release –March 15, 2022 ). - Completion of Pre-Feasibility Study ("PFS") at Marban Engineering – Demonstrating a standalone project with robust economics and room for growth, using a long-term gold price of
US oz gold, the project has a post-tax unlevered IRR of$1,700 23.2% and a post-tax NPV ofC , an NPV/CAPEX ratio of 1.1x, with an AISC of$463M US per ounce, and an average annual production of 161,000 oz Au (Press Release –$882 September 6, 2022 ). - Maiden mineral resource at Bulldog and Kappa (Alpha) – Total inferred resource of 318,000 oz at 3.2 g/t Au (Press Release –
November 10, 2022 ). - Environmental Permitting – Filing of the Initial Project Description for the Marban Engineering project with the
Impact Assessment Agency of Canada ("IAAC") at the federal level and the Project Notice with the Ministère de l'Environnement, de la Lutte contre les Changements Climatiques, de la Faune et des Parcs ("MELCCFP") at the provincial level (Press Release –November 22, 2022 ). - Completion of 77,855 metres of drilling – Including 55,286 metres at Marban and 22,569 metres at Alpha.
- Completion of several environmental baseline studies – Baseline studies necessary to the environmental and social impact studies.
Feasibility Study
- Bridging activities from the PFS initiated in Q4-2022 will continue during Q1-2023 with metallurgical, geotechnical & geomechanical field and test work.
- Mining optimization studies are underway and will be completed in Q1-2023, which will define the technology scenario for the FS.
- The kick-off for the FS is planned for H1-2023, with completion expected in Q1-2024.
Growth Potential at Marban – 26,000 Metres of Planned Drilling
In 2023, exploration efforts will be focused on expanding the life of mine ("LOM") of the Marban project with a total of 26,000 metres of planned drilling. The drilling contract was assigned to a joint venture between
- Marban Engineering near pit expansion – Adding value in Years 0 to 10
- Resource and reserve update as part of the FS.
- Marban Engineering resource growth – Adding value in Years 10 and over
- Resource growth near surface and for underground potential.
- Initial maiden resource estimate expected by Q2-2023.
Marban Regional – Testing gold and Volcanogenic Massive Sulphide ("VMS") targets- Regional exploration for gold and base metal targets.
Table 1: Summary of Planned Drilling at Marban
Areas | Metres Planned | Targets |
Marban Engineering near pit | 2,000 | Norlartic, North and Kierens |
Marban Engineering resource | 14,700 | Malartic H, Hygrade Fold, North North |
Marban Regional | 9,300 | Gold: Low mag features along the Marbenite |
Figure 1: 2023 Planned Drilling at Marban
The Corporation will thus continue its dialogue with the First Nations and the various stakeholders, including but not limited to, citizens, host communities, municipal, provincial, and federal representatives, etc.
4,000 metres of planned drilling
- Follow up on Centremaque intrusion intercepts which remain open in many directions:
- 2,200 metres planned
- Test near surface targets in the vicinity of the Akasaba deposit, located adjacent to Agnico Eagle's Akasaba West mine:
- 1,800 metres planned
Figure 2: 2023 Planned Drilling for Alpha
Wydee and
The 10,300-hectare,
Date and Time:
Registration: O3 Mining Outlook 2023
Details: Participants will be able to submit questions. A recording of the webinar will be made available on o3mining.com following the webinar. If you have any technical difficulties, please email info@o3mining.com
Neither the
View original content to download multimedia:https://www.prnewswire.com/news-releases/o3-mining-releases-outlook-2023-301721883.html
SOURCE
FAQ
What is O3 Mining's outlook for 2023?
What were the 2022 highlights for O3 Mining?
What is the significance of the Feasibility Study for O3 Mining?
What drilling plans does O3 Mining have for 2023?