Jacobs Selected to Design UK's Uxbridge Moor Substation
Jacobs (NYSE: J) was selected by Murphy to serve as civil design partner for the Uxbridge Moor substation project in west London, under a multimillion-pound contract from National Grid Electricity Transmission dated October 22, 2025.
Project scope includes a new 400kV substation, a new 132kV substation, ancillary facilities, 132kV underground connection cables, underground cabling, and modification works to the 400kV overhead line network to connect new customers and meet rising electricity demand west of London.
The announcement highlights Jacobs' global energy infrastructure experience and cites approximately $12 billion in annual revenue and a team of almost 45,000.
Jacobs (NYSE: J) è stata selezionata da Murphy per fungere da partner di design civile per il progetto della sottostazione Uxbridge Moor a ovest di Londra, nell'ambito di un contratto multimilionario con National Grid Electricity Transmission datato 22 ottobre 2025.
Ambito del progetto comprende una nuova sottostazione da 400 kV, una nuova sottostazione da 132 kV, strutture ausiliarie, cavi di collegamento sotterranei da 132 kV, cavi sotterranei e lavori di modifica alla rete di linee aeree da 400 kV per collegare nuovi clienti e soddisfare la domanda crescente di energia elettrica a ovest di Londra.
La comunicazione evidenzia l'esperienza globale di Jacobs nel settore delle infrastrutture energetiche e cita circa $12 miliardi di entrate annue e un team di quasi 45.000.
Jacobs (NYSE: J) fue elegida por Murphy para actuar como socio de diseño civil para el proyecto de la subestación Uxbridge Moor en el oeste de Londres, conforme a un contrato multimillonario de National Grid Electricity Transmission fechado el 22 de octubre de 2025.
Alcance del proyecto incluye una nueva subestación de 400 kV, una nueva subestación de 132 kV, instalaciones auxiliares, cables subterráneos de conexión de 132 kV, cableado subterráneo y trabajos de modificación a la red de líneas aéreas de 400 kV para conectar nuevos clientes y satisfacer la creciente demanda de electricidad al oeste de Londres.
El anuncio destaca la experiencia global de Jacobs en infraestructuras energéticas y cita aproximadamente $12 mil millones en ingresos anuales y un equipo de casi 45,000.
Jacobs (NYSE: J)는 Murphy가 런던 서부의 Uxbridge Moor 변전소 프로젝트의 민간 설계 파트너로 선정되었으며, 2025년 10월 22일에 체결된 National Grid Electricity Transmission의 수백만 파운드 계약에 따라 시행됩니다.
프로젝트 범위에는 새로운 400kV 변전소, 새로운 132kV 변전소, 보조 시설, 132kV 지중 연결 케이블, 지중 케이블링, 새로운 고객 연결 및 런던 서부의 증가하는 전력 수요를 충족시키기 위한 400kV 가공지선 네트워크의 개정 작업이 포함됩니다.
이 발표는 Jacobs의 글로벌 에너지 인프라 경험을 강조하고 연간 매출 약 $12 billion 달러와 약 45,000명의 팀을 언급합니다.
Jacobs (NYSE: J) a été choisie par Murphy pour assurer le rôle de partenaire de conception civile pour le projet de sous-station Uxbridge Moor dans l'ouest de Londres, dans le cadre d'un contrat multicoûte avec National Grid Electricity Transmission daté du 22 octobre 2025.
Portée du projet comprend une nouvelle sous-station 400 kV, une nouvelle sous-station 132 kV, des installations auxiliaires, des câbles souterrains de raccordement 132 kV, un câblage souterrain et des travaux de modification du réseau aérien 400 kV pour connecter de nouveaux clients et répondre à la demande croissante d'électricité à l'ouest de Londres.
L'annonce met en évidence l'expérience mondiale de Jacobs dans les infrastructures énergétiques et cite environ $12 milliards de chiffre d'affaires annuel et une équipe de près de 45 000.
Jacobs (NYSE: J) wurde von Murphy ausgewählt, um als ziviler Designpartner für das Uxbridge Moor-Umspannwerkprojekt im Westen Londons zu fungieren, im Rahmen eines Mehrmillions-Pfund-Vertrags von National Grid Electricity Transmission vom 22. Oktober 2025.
Projektumfang umfasst ein neues 400-kV-Umspannwerk, ein neues 132-kV-Umspannwerk, begleitende Einrichtungen, unterirdische 132-kV-Verbindungskabel, Unterirdikabelung und Modernisierungsarbeiten am 400-kV-Übertragungsleitungsnetz, um neue Kunden anzubinden und die wachsende Nachfrage nach Elektrizität westlich von London zu decken.
Die Ankündigung hebt Jacobs' globale Erfahrung im Energiesektor hervor und nennt etwa $12 Milliarden Jahresumsatz und ein Team von fast 45.000.
جاكوبس (NYSE: J) اختارتها مورفي لتكون شريكاً في التصميم المدني لمشروع المحطة الفرعية Uxbridge Moor في غرب لندن، بموجب عقد منNational Grid Electricity Transmission بملايين الجنيهات، والمشار إليه بتاريخ 22 أكتوبر 2025.
نطاق المشروع يشمل محطة فرعية جديدة 400 كV، محطة فرعية جديدة 132 كV، مرافق مساندة، كابلات توصيل تحت الأرض 132 كV، الكابلات الأرضية، وأعمال تعديل لشبكة خطوط النقل الجوية 400 كV لربط عملاء جدد وتلبية الطلب المتزايد على الكهرباء غرب لندن.
الإعلان يبرز خبرة Jacobs العالمية في بنى التحتية للطاقة ويشير إلى حوالي $12 مليار من الإيرادات السنوية وفريق من قرابة 45,000.
Jacobs (NYSE: J) 被 Murphy 选为西伦敦乌克斯布里奇莫尔变电站项目的民用设计合伙人,依据国家电网电力传输于2025年10月22日签署的数百万英镑合同。
项目范围 包括一个新的400kV变电站、一个新的132kV变电站、辅助设施、132kV地下连接电缆、地下布线,以及对400kV高压线路网络的改造工程,以连接新客户并满足伦敦西部日益增长的电力需求。
公告强调了 Jacobs 在全球能源基础设施方面的经验,并引用约$12 billion 的年收入以及一个由约45,000人组成的团队。
- Contract award: Selected as civil design partner on a multimillion-pound Uxbridge Moor project
- Technical scope: Delivery of new 400kV and 132kV substations plus underground cabling
- Scale and capability: Company reports $12 billion annual revenue and nearly 45,000 staff
- Contract value not specified beyond the term multimillion-pound, limiting visibility into financial impact
Insights
Jacobs wins a multimillion-pound design role on a new Uxbridge Moor substation, expanding its transmission and distribution backlog.
As civil design partner to Murphy for National Grid Electricity Transmission (NGET), Jacobs will deliver design services for a new 400kV substation, a 132kV substation, underground cabling and related works, under a multimillion-pound contract announced on
Key dependencies and risks are explicitly operational and contractual: timely coordination with NGET and Murphy for design milestones, underground cable delivery and the modification works to the 400kV overhead network. The release notes the contract value only as "multimillion-pound" and flags standard forward-looking uncertainties, so contract margin and schedule risk remain unspecified in the disclosed facts.
Concrete items to watch in the near term are completion of design milestones, any disclosed contract value detail or amendments, and notices from NGET or Murphy about construction start and commissioning dates; these will clarify cashflow timing and program risk within a typical multi-year transmission project horizon.
Project to enhance
The multimillion-pound contract from National Grid Electricity Transmission (NGET) will see the construction of a new substation at Uxbridge Moor, which borders NGET's existing Iver substation in
Jacobs Executive Vice President
Fiachra Ó Cléirigh said: "Jacobs has a proven track record of delivering complex infrastructure built for evolving challenges. This project strengthens the resilience and reliability of
Project scope includes construction of a new 400kV substation, a new 132kV substation, ancillary facilities, underground cabling and associated modification works to the 400kV overhead line network to the new 400kV substation. Connection to the new 132kV substation will be via 132kV underground cables.
Jacobs' role in the Uxbridge Moor substation project reflects the company's industry-leading position, consistently recognized by Engineering News-Record. Jacobs ranks among the top firms globally in power, transmission and distribution and overall design, underscoring its ability to deliver complex energy infrastructure at scale.
Around the globe, Jacobs is advancing global energy infrastructure, shaping resilient and secure systems for communities and economies. Projects include Suedlink in
At Jacobs, we're challenging today to reinvent tomorrow – delivering outcomes and solutions for the world's most complex challenges. With approximately
Certain statements contained in this press release constitute forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are statements that do not directly relate to any historical or current fact. When used herein, words such as "expects," "anticipates," "believes," "seeks," "estimates," "plans," "intends," "future," "will," "would," "could," "can," "may," and similar words are intended to identify forward-looking statements. We base these forward-looking statements on management's current estimates and expectations, as well as currently available competitive, financial and economic data. Forward-looking statements, however, are inherently uncertain. There are a variety of factors that could cause business results to differ materially from our forward-looking statements including, but not limited to, uncertainties as to, the timing of the award of projects and funding and potential changes to the amounts provided for under the Infrastructure Investment and Jobs Act and other legislation and executive orders related to governmental spending, including any directive to federal agencies to reduce federal spending or the size of the federal workforce, and changes in
For press/media inquiries:
media@jacobs.com
View original content to download multimedia:https://www.prnewswire.com/news-releases/jacobs-selected-to-design-uks-uxbridge-moor-substation-302590115.html
SOURCE Jacobs