STOCK TITAN

Transmission Line Upgrades to Help Enhance Reliability for West Penn Power Customers

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary

West Penn Power, a FirstEnergy subsidiary, is upgrading the 17.3-mile Springdale-Kittanning transmission line to improve electric service reliability in Allegheny, Armstrong, and Westmoreland Counties. This project, part of FirstEnergy's multi-year 'Energizing the Future' initiative, involves replacing aging hardware to reduce outage frequency. Aerial construction techniques were employed to minimize environmental disruption. The Springdale-Kittanning line has been operational since 1923 and serves approximately 725,000 customers in central and southwestern Pennsylvania.

Positive
  • Completion of transmission line upgrades aimed at enhancing reliability.
  • Utilization of aerial construction methods to minimize disruption and environmental impact.
  • Project is part of a multi-year investment initiative, indicating ongoing commitment to infrastructure improvement.
Negative
  • None.

GREENSBURG, Pa., May 5, 2021 /PRNewswire/ -- West Penn Power, a subsidiary of FirstEnergy Corp. (NYSE: FE), is completing transmission line upgrades to help enhance electric service reliability for customers in Allegheny, Armstrong, and Westmoreland Counties. The work includes the replacement of hardware across the 17.3-mile transmission line to help reduce the frequency of equipment-related outages.

The Springdale-Kittanning 138-kilovolt transmission line transports high-voltage electricity to substations that serve customers across western Pennsylvania. The replacement of aging hardware will help increase reliability of the line, which was first constructed around 1923.

"Projects like this one are critical to helping ensure reliable power keeps flowing to our customers," said Carl Bridenbaugh, vice president, Transmission. "In addition to boosting performance, reinforcing the system helps reduce the risk of power outages in the future."

Crews were able to complete most of the upgrades by helicopter, minimizing the disruption for customers and the impact on the environment. In conventional construction, crews build access roads and drive trucks to the work site, but aerial construction transports workers, equipment, and materials by flying them into place with the aid of a long, synthetic rope suspended beneath the helicopter.

Aerial construction on the Springdale-Kittanning transmission line began in January 2021. The project is part of Energizing the Future, FirstEnergy's multi-year investment initiative aimed at upgrading transmission facilities with advanced equipment and technology.  

West Penn Power serves approximately 725,000 customers within 24 counties in central and southwestern Pennsylvania. Follow West Penn Power on Twitter @W_Penn_Power and on Facebook at www.facebook.com/WestPennPower 

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its 10 electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Follow FirstEnergy online at www.firstenergycorp.com and on Twitter @FirstEnergyCorp.

Editor's Note: Photos of crews completing the aerial work are available for download on Flickr.

Cision View original content to download multimedia:http://www.prnewswire.com/news-releases/transmission-line-upgrades-to-help-enhance-reliability-for-west-penn-power-customers-301284783.html

SOURCE FirstEnergy Corp.

FAQ

What is the purpose of the transmission line upgrades by FirstEnergy's West Penn Power?

The upgrades aim to enhance electric service reliability and reduce the frequency of equipment-related outages for customers.

When did the aerial construction for the Springdale-Kittanning transmission line begin?

Aerial construction began in January 2021.

How many customers does West Penn Power serve?

West Penn Power serves approximately 725,000 customers across 24 counties.

What initiative is the transmission line upgrade part of?

The upgrade is part of FirstEnergy's multi-year investment initiative called 'Energizing the Future'.

How long is the Springdale-Kittanning transmission line?

The Springdale-Kittanning transmission line is 17.3 miles long.

FirstEnergy Corp.

NYSE:FE

FE Rankings

FE Latest News

FE Stock Data

24.28B
575.60M
0.12%
89.57%
1.79%
Utilities - Regulated Electric
Electric Services
Link
United States of America
AKRON