Endeavour Announces Wet Commissioning is Underway at Lafigué Project
Endeavour Mining announced that wet commissioning at the Lafigué project in Côte d'Ivoire is underway. The project is 94% complete, on budget, and ahead of schedule, with the first gold pour expected in late June. Ore stockpiles are at 1.6Mt grading 1.30 g/t gold, equating to 65koz. The Lafigué mine is expected to produce 90-110koz of gold in FY-2024 at an AISC of $900-975/oz. The mine's initial capital expenditure stands at $448 million, with 97% committed and 83% incurred. The project aims for an average annual production of 203koz at an AISC of $871/oz over its 13-year life. The workforce includes 92% local nationals, contributing to community employment and technical training.
- Wet commissioning underway and 94% project completion.
- Project remains on budget.
- First gold pour expected a quarter ahead of schedule in late June.
- Ore stockpiles at 1.6Mt grading 1.30 g/t gold for 65koz.
- Expected FY-2024 production of 90-110koz at an AISC of $900-975/oz.
- Initial growth capital expenditure at $448 million, with 97% committed.
- Annual production of 203koz at an AISC of $871/oz over 13 years.
- 92% of workforce are Ivorian nationals, promoting local employment.
- Remaining capital expenditure of $78.1 million to be incurred in Q2 and early Q3.
- High initial growth capital expenditure of $448 million.
ENDEAVOUR ANNOUNCES WET COMMISSIONING IS UNDERWAY AT LAFIGUÉ PROJECT
First gold expected in late-June · Project ahead of schedule and on budget ·
HIGHLIGHTS:
|
Abidjan, 30 May 2024 – Endeavour Mining plc (LSE:EDV, TSX:EDV, OTCQX:EDMF) (“Endeavour”, the “Group” or the “Company”) is pleased to announce that wet commissioning activities are now underway at the Lafigué project in Côte d’Ivoire. The project is on budget, with construction now
Ian Cockerill, Chief Executive Officer, commented: “We are pleased with our progress at the Lafigué project, as we begin wet commissioning, with construction on budget and a quarter ahead of schedule. Lafigué is set to become another cornerstone asset in Endeavour’s portfolio; with over 200koz of annual production at an all-in sustaining cost below
Lafigué is a great example of our strong track record of organic value creation. The project was discovered through our own ambitious exploration programme for a cost of
With the commissioning of the Lafigué project now underway and first gold production at the Sabodala-Massawa BIOX® expansion achieved in early Q2 this year, Endeavour is well positioned to successfully execute its growth strategy, completing the current phase of investment, and transitioning to a more cash flow generative phase. We will continue to support our operations, optimisation initiatives and exploration, while we re-focus our capital allocation priorities on de-levering our balance sheet and increasing our commitment to shareholder returns.”
Wet commissioning of the crushing, milling and CIL circuits at the Lafigué processing plant are underway, with first ore delivered to the crushing and milling circuits on 24 May. Mining equipment mobilisation has fully advanced and mining activities continue to accelerate according to schedule with 14.4Mt of material moved since mining activities commenced in Q4-2023. Ore stockpiles currently stand at 1.6Mt of ore grading 1.30 g/t gold containing 65koz.
Initial growth capital expenditure for the project is
The addition of the Lafigué mine to Endeavour’s portfolio, is expected to add average annual production of 203koz at an AISC of
Endeavour remains focussed on building local talent, and during the project construction, up to 3,000 employees and contractors were on site,
Figure 1: Lafigué processing plant overview with project construction
Please refer to Figure in the attached press release.
Figure 2: Primary crushing circuit with wet commissioning in progress
Please refer to Figure in the attached press release.
Figure 3: Wet commissioning of the ball mill is underway
Please refer to Figure in the attached press release.
Figure 4: Wet commissioning of HPGR is underway
Please refer to Figure in the attached press release.
Figure 5: Wet commissioning of the CIL circuit is underway
Please refer to Figure in the attached press release.
Figure 6: Completed elution circuit
Please refer to Figure in the attached press release.
Figure 7: Gold room construction is now largely complete
Please refer to Figure in the attached press release.
ABOUT THE LAFIGUÉ PROJECT
The Lafigué permit is located towards the northern end of the Birimian aged Oumé-Fetekro greenstone belt, in north-central Côte d’Ivoire, approximately 500km from Abidjan by road. The Lafigué deposit is located in the northeast part of the Fetekro exploration permit, adjacent to existing infrastructure, including sealed paved roads and high voltage grid power. Endeavour has an
Endeavour began exploration on the Fetekro property in March 2017, following a strategic assessment of its exploration tenements which identified the project as a top priority target. To date, only a limited portion of the Fetekro property has been explored, as the priority has been the delineation of the Lafigué deposit. A maiden Mineral Resource Estimate for the Lafigué deposit was published on 29 October 2018 and subsequently updated on 3 September 2019, 18 August 2020, and 15 May 2022. A Preliminary Economic Assessment (“PEA”) was published on 18 August 2020 and a Preliminary Feasibility Study (“PFS”) was completed with the effective date 31 December 2020.
Construction of the Lafigué project in Côte d'Ivoire was launched in early Q4-2022, following the completion of a Definitive Feasibility Study (“DFS”) which confirmed Lafigué’s potential to be a cornerstone asset for Endeavour. The 2022 DFS contemplates a 12.8 year LOM with average annual production of 203koz at a low AISC of
As at 31 December 2023, Proven and Probable reserves totalled 49.9Mt at 1.69 g/t containing 2.7Moz of gold and Measured and Indicated resources (inclusive of reserves) totalled 46.2.1Mt at 2.04 g/t containing 3.0Moz of gold.
Given the strong exploration potential, Endeavour is targeting the discovery of 1.5 – 2.0 Moz of Indicated resources across the Lafigué mining permit and the wider Fetekro exploration permit area over the 2021 to 2025 period at a discovery cost of
QUALIFIED PERSONS
Mark Morcombe, COO of Endeavour Mining PLC., a Fellow of the Australasian Institute of Mining and Metallurgy, is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and approved the technical information in this news release.
CONTACT INFORMATION
Jack Garman Vice President, Investor Relations +44 203 011 2723 jackgarman@endeavourmining.com | Brunswick Group LLP in London Carole Cable, Partner +44 207 404 5959 ccable@brunswickgroup.com |
ABOUT ENDEAVOUR MINING CORPORATION
Endeavour Mining is one of the world’s senior gold producers and the largest in West Africa, with operating assets across Senegal, Côte d’Ivoire and Burkina Faso and a strong portfolio of advanced development projects and exploration assets in the highly prospective Birimian Greenstone Belt across West Africa.
A member of the World Gold Council, Endeavour is committed to the principles of responsible mining and delivering sustainable value to its employees, stakeholders and the communities where it operates. Endeavour is listed on the London and Toronto Stock Exchanges, under the symbol EDV.
For more information, please visit www.endeavourmining.com.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION
This news release contains "forward-looking statements" within the meaning of applicable securities laws. All statements, other than statements of historical fact, are "forward-looking statements". Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "expected", "budgeted", "forecasts", and "anticipates".
Forward-looking statements, while based on management's best estimates and assumptions, are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the successful integration of acquisitions; risks related to international operations; risks related to general economic conditions and credit availability, actual results of current exploration activities, unanticipated reclamation expenses; changes in project parameters as plans continue to be refined; fluctuations in prices of metals including gold; fluctuations in foreign currency exchange rates, increases in market prices of mining consumables, possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; delays in the completion of development or construction activities, changes in national and local government regulation of mining operations, tax rules and regulations, and political and economic developments in countries in which Endeavour operates. Although Endeavour has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Please refer to Endeavour's most recent Annual Information Form filed under its profile at www.sedar.com for further information respecting the risks affecting Endeavour and its business.
Attachment
FAQ
What is the current status of the Lafigué project?
When is the first gold pour expected at the Lafigué project?
What are the ore stockpile details at the Lafigué project?
What is the expected gold production for FY-2024 at the Lafigué project?
What is the AISC for the Lafigué project in FY-2024?
How much initial growth capital expenditure has Endeavour committed to the Lafigué project?
What is the annual production and AISC expected over the life of the Lafigué mine?