Denison Reports Financial and Operational Results for 2024 Highlighted by Significant Advancement of the Phoenix Project
Denison Mines (TSX: DML, NYSE: DNN) reported significant progress in 2024 towards developing the Phoenix ISR uranium project. The company achieved ~65% completion of total engineering and secured key regulatory milestones, including CNSC's acceptance of the final Environmental Impact Statement. A two-part public hearing is scheduled for late 2025, potentially enabling project approvals and construction start in early 2026.
The company signed multiple agreements in 2024: a Mutual Benefits Agreement with Kineepik Métis Local #9, a Community Benefit Agreement with Pinehouse Lake, and a Sustainable Communities Investment Agreement with multiple northern municipalities. These agreements secured community support for Wheeler River development.
Notable developments include the planned restart of McClean Lake mining operations in 2025 using SABRE mining method, completion of ISR field testing at Midwest, and strategic partnerships with Foremost Clean Energy and Cosa Resources for exploration projects. The company maintains its target for Phoenix's first production by first half of 2028.
Denison Mines (TSX: DML, NYSE: DNN) ha riportato significativi progressi nel 2024 verso lo sviluppo del progetto di uranio Phoenix ISR. L'azienda ha raggiunto circa il 65% di completamento della progettazione totale e ha ottenuto importanti traguardi normativi, inclusa l'accettazione da parte della CNSC della Dichiarazione di Impatto Ambientale finale. Un'udienza pubblica in due parti è programmata per la fine del 2025, potenzialmente consentendo l'approvazione del progetto e l'inizio della costruzione all'inizio del 2026.
L'azienda ha firmato diversi accordi nel 2024: un Accordo di Benefici Reciproci con Kineepik Métis Local #9, un Accordo di Benefici per la Comunità con Pinehouse Lake e un Accordo di Investimento per Comunità Sostenibili con diversi comuni settentrionali. Questi accordi hanno garantito il supporto della comunità per lo sviluppo di Wheeler River.
Sviluppi notevoli includono la pianificazione della riapertura delle operazioni minerarie di McClean Lake nel 2025 utilizzando il metodo minerario SABRE, il completamento dei test sul campo ISR a Midwest e le partnership strategiche con Foremost Clean Energy e Cosa Resources per progetti di esplorazione. L'azienda mantiene il suo obiettivo per la prima produzione di Phoenix entro la prima metà del 2028.
Denison Mines (TSX: DML, NYSE: DNN) informó sobre avances significativos en 2024 hacia el desarrollo del proyecto de uranio Phoenix ISR. La empresa alcanzó aproximadamente el 65% de finalización del diseño total y aseguró hitos regulatorios clave, incluida la aceptación por parte de la CNSC de la Declaración de Impacto Ambiental final. Se ha programado una audiencia pública en dos partes para finales de 2025, lo que podría permitir la aprobación del proyecto y el inicio de la construcción a principios de 2026.
La empresa firmó múltiples acuerdos en 2024: un Acuerdo de Beneficios Mutuos con Kineepik Métis Local #9, un Acuerdo de Beneficios Comunitarios con Pinehouse Lake y un Acuerdo de Inversión en Comunidades Sostenibles con varios municipios del norte. Estos acuerdos aseguraron el apoyo de la comunidad para el desarrollo de Wheeler River.
Los desarrollos notables incluyen la reanudación planificada de las operaciones mineras de McClean Lake en 2025 utilizando el método de minería SABRE, la finalización de las pruebas de campo ISR en Midwest, y asociaciones estratégicas con Foremost Clean Energy y Cosa Resources para proyectos de exploración. La empresa mantiene su objetivo de iniciar la producción de Phoenix en la primera mitad de 2028.
Denison Mines (TSX: DML, NYSE: DNN)는 2024년 포닉스 ISR 우라늄 프로젝트 개발을 위한 중요한 진전을 보고했습니다. 회사는 전체 엔지니어링의 약 65%를 완료하였고, CNSC의 최종 환경 영향 보고서 수용을 포함한 주요 규제 이정표를 확보했습니다. 2025년 말에 예정된 두 부분의 공개 청문회는 프로젝트 승인 및 2026년 초 건설 시작을 가능하게 할 수 있습니다.
회사는 2024년에 여러 협약을 체결했습니다: Kineepik Métis Local #9와의 상호 이익 협약, Pinehouse Lake와의 지역 사회 혜택 협약, 그리고 여러 북부 지방 자치단체와의 지속 가능한 커뮤니티 투자 협약입니다. 이러한 협약은 Wheeler River 개발에 대한 지역 사회의 지원을 확보했습니다.
주요 발전 사항으로는 2025년에 SABRE 채굴 방법을 사용하여 McClean Lake 채굴 작업을 재개할 계획, Midwest에서 ISR 현장 테스트 완료, 그리고 탐사 프로젝트를 위한 Foremost Clean Energy 및 Cosa Resources와의 전략적 파트너십이 포함됩니다. 회사는 2028년 상반기 내에 포닉스의 첫 생산 목표를 유지하고 있습니다.
Denison Mines (TSX: DML, NYSE: DNN) a rapporté des progrès significatifs en 2024 dans le développement du projet d'uranium Phoenix ISR. L'entreprise a atteint environ 65 % d'achèvement de l'ingénierie totale et a sécurisé des jalons réglementaires clés, y compris l'acceptation par la CNSC de la déclaration d'impact environnemental finale. Une audience publique en deux parties est prévue pour la fin de 2025, ce qui pourrait permettre l'approbation du projet et le début de la construction au début de 2026.
L'entreprise a signé plusieurs accords en 2024 : un Accord de Bénéfices Mutuels avec Kineepik Métis Local #9, un Accord de Bénéfices Communautaires avec Pinehouse Lake, et un Accord d'Investissement pour des Communautés Durables avec plusieurs municipalités du nord. Ces accords ont sécurisé le soutien de la communauté pour le développement de Wheeler River.
Les développements notables comprennent la réouverture prévue des opérations minières de McClean Lake en 2025 en utilisant la méthode d'extraction SABRE, l'achèvement des tests sur le terrain ISR à Midwest, et des partenariats stratégiques avec Foremost Clean Energy et Cosa Resources pour des projets d'exploration. L'entreprise maintient son objectif de production pour Phoenix au cours de la première moitié de 2028.
Denison Mines (TSX: DML, NYSE: DNN) berichtete 2024 über erhebliche Fortschritte bei der Entwicklung des Phoenix ISR-Uranprojekts. Das Unternehmen erreichte einen Abschluss von etwa 65% der gesamten Ingenieurarbeiten und sicherte sich wichtige regulatorische Meilensteine, einschließlich der Genehmigung des endgültigen Umweltverträglichkeitsberichts durch die CNSC. Eine zweigeteilte öffentliche Anhörung ist für Ende 2025 geplant, was möglicherweise die Genehmigung des Projekts und den Baubeginn Anfang 2026 ermöglichen könnte.
Das Unternehmen unterzeichnete im Jahr 2024 mehrere Vereinbarungen: eine gegenseitige Nutzenvereinbarung mit Kineepik Métis Local #9, eine Gemeinwohlvereinbarung mit Pinehouse Lake und eine Vereinbarung über nachhaltige Gemeinschaftsinvestitionen mit mehreren nördlichen Gemeinden. Diese Vereinbarungen sicherten die Unterstützung der Gemeinde für die Entwicklung des Wheeler River.
Bemerkenswerte Entwicklungen umfassen die geplante Wiederaufnahme der Bergbauaktivitäten in McClean Lake im Jahr 2025 unter Verwendung der SABRE-Bergbaumethode, den Abschluss der ISR-Feldtests in Midwest und strategische Partnerschaften mit Foremost Clean Energy und Cosa Resources für Explorationsprojekte. Das Unternehmen hält an seinem Ziel fest, die erste Produktion von Phoenix bis zur ersten Hälfte des Jahres 2028 zu erreichen.
- Achieved 65% completion of Phoenix project engineering
- Secured key regulatory approvals and CNSC hearing dates
- Obtained community support through multiple benefit agreements
- Planned restart of McClean Lake mining operations in 2025
- Strong debt-free balance sheet to support development plans
- Project construction and production timeline dependent on regulatory approvals
- Additional $60 million in equipment purchases required for Phoenix project
- Exposure to volatile uranium spot market prices
Insights
Denison Mines has made significant regulatory progress on its flagship Phoenix ISR uranium project, with CNSC hearings scheduled for late 2025 potentially enabling construction start in early 2026 and first production by H1 2028. The project has reached approximately 65% completion of total engineering, supported by finalized process designs and equipment selection. This progress aligns with the company's timeline for bringing online Saskatchewan's next major uranium mine.
The company has secured critical community support through multiple agreements, including with Kineepik Métis Local #9 and the Village of Pinehouse Lake, removing potential social license obstacles to development. The planned restart of uranium mining at McClean Lake in 2025 using their patented SABRE method should generate near-term cash flow while the company develops Phoenix.
The successful ISR field test program at Midwest validated key technical assumptions for this mining approach, particularly confirming hydraulic conductivity values consistent with their previous conceptual study. The strategic MaxPERF Tool Systems acquisition strengthens Denison's technical capabilities for ISR mining.
Denison has prudently monetized non-core exploration assets through option agreements with Foremost Clean Energy and Cosa Resources, potentially generating
The uranium market context remains supportive, with the long-term price indicator rising
The engineering progress at Phoenix represents a critical technical milestone, with detailed design engineering reaching 65% completion by year-end 2024. The finalization of process design, piping and instrumentation diagrams (P&IDs), and HAZOP studies indicates the project is transitioning from conceptual to execution phase. The selection of major process equipment and electrical distribution infrastructure means Denison can now proceed with procurement of long-lead items.
The ISR field test results at Midwest provide technical validation for potential application of this mining method beyond Phoenix. Confirmation of hydraulic conductivity and successful permeability enhancement testing are particularly significant, as these are essential parameters for ISR mining viability. The acquisition of MaxPERF Tool Systems provides Denison with proprietary technology for enhancing permeability in uranium deposits, giving them a competitive technical advantage in developing ISR mines.
The planned restart of McClean Lake mining operations using the patented SABRE mining method deserves attention. SABRE is an innovative non-entry mining method that combines elements of surface mining and underground mining. The completion of the Pod 1 East SABRE pad and drilling of four access holes demonstrates tangible progress toward near-term production.
With Phoenix detailed engineering on track for substantial completion by Q3 2025, Denison appears well-positioned to commence construction in early 2026 following regulatory approvals. The
David Cates, President and CEO of Denison commented, "The Denison team was active across all aspects of our business in 2024, and owing to several important achievements during the year, we are well-positioned to execute on our objective to build and operate the next new large-scale uranium mine in northern Saskatchewan.
We significantly advanced the regulatory approvals process for our Phoenix In-Situ Recovery ('ISR') project, culminating in the Canadian Nuclear Safety Commission ('CNSC') scheduling a two-part public hearing ('Hearing') for the project to occur in late 2025, which could allow for project approvals and start of construction in early 2026 and for first production to be achieved, in line with our previous guidance, by the first half of 2028.
In anticipation of this timeline, our operations team has progressed our detailed design engineering efforts for
We also announced the signing of a Mutual Benefits Agreement with Kineepik Métis Local #9, a Community Benefit Agreement with the northern
Beyond Wheeler River, there were notable developments from our McClean Lake and Midwest joint ventures with Orano Canada Inc. ('Orano Canada') and our exploration project portfolio. At McClean Lake, development work progressed at the McClean North deposit in preparation for the restart of mining in 2025, which will use the joint venture's patented Surface Access Borehole Resource Extraction ('SABRE') mining method. At Midwest, an inaugural ISR field test program was completed, which validated key assumptions and advanced our evaluation of the potential use of ISR mining at Midwest. In an effort to amplify our exposure to exploration discovery, we also entered into agreements with each of Foremost Clean Energy (Nasdaq: FMST) and Cosa Resources (TSX-V: COSA) to collaborate on the exploration of several of Denison's non-core exploration properties.
Our diverse portfolio of
Looking ahead, we entered 2025 with a strong debt-free balance sheet that can support Denison's ambitious plans for this year and beyond. While we continue to invest in exploration and evaluation programs at our pipeline properties, we remain laser focused on readying
- Significant Progress Achieved in the Regulatory Approvals Process for the Phoenix ISR Project
Multiple key regulatory milestones were achieved in late 2024, including (i) completion of the technical review phase of the federal EA approval process in November, (ii) acceptance by the CNSC of the Company's final Environmental Impact Statement ('EIS') for the Project in December, and (iii) the CNSC's determination of the sufficiency of Denison's Licence to Prepare and Construct a Uranium Mine and Mill ('Licence') application, also in November.
These accomplishments indicate that the CSNC staff support the advancement of the Project. Accordingly, the CNSC Registrar has set the schedule for the Hearing for the Wheeler River Uranium Project ('Wheeler River'). The Hearing is scheduled to be held in two parts (October 8, 2025, and December 8 to 12, 2025) and represents the final step in the federal approval process for the Project's Environmental Assessment ('EA') and Licence.
Additionally, in October 2024, Denison submitted a final EIS to the Saskatchewan Ministry of Environment ('MOE'), in substantially the same form as the EIS that has been submitted to the CNSC. The province completed a public and Indigenous review period on the EIS in November and December 2024, of which the comments received will be considered in the issuance of a Ministerial Decision for the EA.
- Achieved Approximately
65% Completion of Total Engineering forPhoenix
In January 2024, Denison awarded a contract for approximately
Total engineering completion at end of 2024 was approximately
- Signing of Wheeler River Benefit Agreements with Kineepik Métis Local #9 and the
Village of Pinehouse Lake
In early July 2024, Denison announced the signing of a Mutual Benefits Agreement ('MBA') with Kineepik Métis Local #9 ('KML'), and a Community Benefit Agreement ('CBA') with the northern
The MBA acknowledges that Wheeler River is located within KML's Land and Occupancy Area in northern
The CBA acknowledges that
- Signing of Sustainable Communities Investment Agreement
In March 2024, Denison signed a Sustainable Communities Investment Agreement with the municipalities of the
The agreement with the Communities establishes commitments of Denison in support of community development initiatives, with consideration towards contributing to the current and future economic prosperity and sustainability of the Communities by promoting economic development and investments in capital projects, job creation and training, housing, education, and other initiatives.
As part of the agreement, the Communities have provided their consent and support for Wheeler River and have committed, amongst other things, to support all regulatory approvals issued for the project related to exploration, evaluation, development, operation, reclamation, and closure activities.
- Announcement of Planned Restart of McClean Lake Mining Operations
In January 2024, Orano Canada and Denison announced the planned restart of uranium mining operations on the McClean Lake property. Mining is expected to be carried out using the McClean Lake Joint Venture's ('MLJV') patented SABRE mining method and is planned to commence at the McClean North deposit in 2025. Activities during 2024, included the completion of the Pod 1 East SABRE pad, drilling four access holes at Pod 1 East, and associated procurement activities. A further four access holes are planned to be completed in the second quarter of 2025.
- Completion of Inaugural ISR Field Test Program at Midwest
In June 2024, Denison announced the completion of an ISR field test program at the Company's
Denison carried out the Program in collaboration with Orano Canada, as operator and owner of
- Confirmation of Hydraulic Conductivity: Pump and injection tests validated hydraulic connectivity in the test wells within the mineralized zone and achieved hydraulic conductivity values (a measure of permeability) consistent with the Concept Study. Sufficient permeability within the mineralized zone is a key criterion for the successful deployment of the ISR mining method.
- Demonstrated the Effectiveness of Permeability Enhancement: One method of permeability enhancement was successfully deployed within two wells, demonstrating the suitability of the method to the Midwest Main deposit. The efficiency of permeability enhancement was verified by comparison of pre- and post-permeability enhancement hydraulic testing.
- Metallurgical Samples Defined and Collected for Leaching Characteristics: Core samples representative of the Midwest Main deposit were collected during the program for use in future metallurgical tests to assess leaching characteristics.
- Acquisition of MaxPERF Tool Systems
In February 2024, the Company announced an acquisition of fixed and mobile MaxPERF Tool Systems from Penetrators Canada Inc. ('Penetrators'). The MaxPERF Tool Systems have been successfully deployed several times as a method of permeability enhancement in ISR field studies conducted on the Company's potential ISR mining projects, including at
- Option of Non-Core Exploration Projects to Foremost Clean Energy Ltd.
In September 2024, Denison executed an option agreement with Foremost Clean Energy Ltd ('Foremost'), which grants Foremost a multi-phase option to acquire up to
- Formation of Exploration Joint Ventures with Cosa Resources Corp.
In November 2024, Denison executed an acquisition agreement with Cosa Resources Corp. ('Cosa') for Cosa to acquire a
- Appointment of New Board Chair
In May 2024, following the results of the Annual General Meeting of Shareholders ('AGM') held in
Denison Mines Corp. was formed under the laws of
Denison is a uranium mining, exploration and development company with interests focused in the
Denison's interests in
Additionally, through its
The technical information contained in this press release has been reviewed and approved by Chad Sorba, P.Geo., Denison's Vice President Technical Services & Project Evaluation, and Andy Yackulic, P.Geo., Denison's Vice President Exploration, who are both Qualified Persons in accordance with the requirements of NI 43-101.
Certain information contained in this press release constitutes 'forward-looking information', within the meaning of the applicable
In particular, this press release contains forward-looking information pertaining to the following: projections with respect to exploration, development and expansion plans and objectives, including the scope, objectives and interpretations of the FS, PFS and the Wheeler River technical de-risking process for the proposed ISR operation for the
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the results and underlying assumptions and interpretations of the FS and PFS may not be maintained after further testing or be representative of actual conditions within the applicable deposits. In addition, Denison may decide or otherwise be required to discontinue testing, evaluation, engineering, and development work if it is unable to maintain or otherwise secure the necessary approvals or resources (such as testing facilities, capital funding, etc.). Denison believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the MD&A dated March 13, 2025 under the heading 'Risk Factors'. These factors are not, and should not be, construed as being exhaustive.
Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this press release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.
View original content to download multimedia:https://www.prnewswire.com/news-releases/denison-reports-financial-and-operational-results-for-2024-highlighted-by-significant-advancement-of-the-phoenix-project-302401624.html
SOURCE Denison Mines Corp.