Denison Reports CNSC Hearing Dates for Phoenix ISR Project
Denison Mines (TSX: DML, NYSE: DNN) has announced key dates for the Canadian Nuclear Safety Commission (CNSC) public hearing for its Wheeler River Uranium Project. The hearing is scheduled in two parts: October 8, 2025, and December 8-12, 2025, marking the final step in the federal approval process for both Environmental Assessment and License to Prepare and Construct.
Following successful completion of multiple regulatory milestones in late 2024, including technical review completion and acceptance of the final Environmental Impact Statement, construction of the Phoenix In-Situ Recovery project could begin in early 2026. The company maintains its target for first production by first half of 2028.
Denison Mines (TSX: DML, NYSE: DNN) ha annunciato le date chiave per l'udienza pubblica della Commissione canadese per la sicurezza nucleare (CNSC) relativa al suo progetto di uranio Wheeler River. L'udienza è programmata in due parti: l'8 ottobre 2025 e dal 8 al 12 dicembre 2025, segnando l'ultimo passo nel processo di approvazione federale per la Valutazione Ambientale e la Licenza per Preparare e Costruire.
Dopo il completamento con successo di molteplici traguardi normativi alla fine del 2024, inclusa la conclusione della revisione tecnica e l'accettazione della Dichiarazione di Impatto Ambientale finale, la costruzione del progetto Phoenix In-Situ Recovery potrebbe iniziare all'inizio del 2026. L'azienda mantiene il suo obiettivo per la prima produzione entro la prima metà del 2028.
Denison Mines (TSX: DML, NYSE: DNN) ha anunciado fechas clave para la audiencia pública de la Comisión Canadiense de Seguridad Nuclear (CNSC) para su Proyecto de Uranio Wheeler River. La audiencia está programada en dos partes: el 8 de octubre de 2025 y del 8 al 12 de diciembre de 2025, marcando el último paso en el proceso de aprobación federal tanto para la Evaluación Ambiental como para la Licencia para Preparar y Construir.
Tras la finalización exitosa de múltiples hitos regulatorios a finales de 2024, incluida la finalización de la revisión técnica y la aceptación de la Declaración de Impacto Ambiental final, la construcción del proyecto Phoenix In-Situ Recovery podría comenzar a principios de 2026. La empresa mantiene su objetivo de producción inicial para la primera mitad de 2028.
Denison Mines (TSX: DML, NYSE: DNN)는 캐나다 원자력 안전 위원회(CNSC)의 Wheeler River 우라늄 프로젝트에 대한 공청회 주요 날짜를 발표했습니다. 공청회는 두 부분으로 예정되어 있으며: 2025년 10월 8일과 2025년 12월 8일부터 12일까지 진행될 예정이며, 이는 환경 평가 및 준비 및 건설 허가를 위한 연방 승인 절차의 마지막 단계입니다.
2024년 말에 기술 검토 완료 및 최종 환경 영향 보고서 수용을 포함한 여러 규제 이정표를 성공적으로 완료한 후, Phoenix In-Situ Recovery 프로젝트의 건설은 2026년 초에 시작될 수 있습니다. 회사는 2028년 상반기까지 첫 생산 목표를 유지하고 있습니다.
Denison Mines (TSX: DML, NYSE: DNN) a annoncé des dates clés pour l'audience publique de la Commission canadienne de sûreté nucléaire (CNSC) concernant son projet d'uranium Wheeler River. L'audience est prévue en deux parties : le 8 octobre 2025 et du 8 au 12 décembre 2025, marquant la dernière étape du processus d'approbation fédérale pour l'évaluation environnementale et la licence de préparation et de construction.
Suite à l'achèvement réussi de plusieurs étapes réglementaires à la fin de 2024, y compris la conclusion de l'examen technique et l'acceptation de la déclaration d'impact environnemental finale, la construction du projet Phoenix In-Situ Recovery pourrait débuter début 2026. L'entreprise maintient son objectif de première production d'ici la première moitié de 2028.
Denison Mines (TSX: DML, NYSE: DNN) hat wichtige Termine für die öffentliche Anhörung der Canadian Nuclear Safety Commission (CNSC) zu seinem Wheeler River Uranprojekt bekannt gegeben. Die Anhörung ist in zwei Teile unterteilt: am 8. Oktober 2025 und vom 8. bis 12. Dezember 2025, was den letzten Schritt im föderalen Genehmigungsprozess sowohl für die Umweltbewertung als auch für die Lizenz zur Vorbereitung und zum Bau darstellt.
Nach erfolgreichem Abschluss mehrerer regulatorischer Meilensteine Ende 2024, einschließlich des Abschlusses der technischen Überprüfung und der Annahme des endgültigen Umweltverträglichkeitsberichts, könnte der Bau des Phoenix In-Situ Recovery-Projekts Anfang 2026 beginnen. Das Unternehmen hält an seinem Ziel fest, die erste Produktion bis zur ersten Hälfte des Jahres 2028 zu erreichen.
- Regulatory approval process advancing on schedule
- Clear timeline for construction start in early 2026
- First production timeline maintained for H1 2028
- Successful completion of key regulatory milestones
- Project still pending final regulatory approval
- Construction cannot commence until early 2026
Insights
The CNSC's scheduling of public hearings for Denison's Wheeler River Project represents a critical de-risking event in the regulatory pathway for what could become Canada's first new conventional uranium mine in decades. With hearings set for October and December 2025, Denison now has a clear timeline toward potential construction beginning in early 2026 and production by H1 2028.
The Phoenix deposit at Wheeler River is particularly significant as it contains some of the highest-grade uranium mineralization globally (averaging 19.1% U3O8), with the potential to produce approximately 6 million pounds of U3O8 annually over a 10-year mine life at exceptionally low operating costs (estimated below $8/lb).
The In-Situ Recovery (ISR) mining method planned for Phoenix represents innovative technology for the Athabasca Basin, offering potential environmental and economic advantages over conventional mining. ISR typically has lower capital intensity, smaller surface footprint, and reduced waste compared to open pit or underground methods.
This regulatory progress comes amid a strengthening uranium market, with spot prices around $90/lb and growing recognition of nuclear power's role in clean energy transitions. The Phoenix project's timeline positions Denison to potentially bring new production online during a period of projected supply deficits as utilities seek to secure long-term supplies.
While the regulatory pathway appears positive, investors should note that public hearings still present opportunities for stakeholder intervention, and final approval isn't guaranteed. However, the successful completion of technical reviews and EIS acceptance suggests significant progress toward eventual approval.
Based on this schedule, if the CNSC makes a prompt decision to approve the Project following the completion of the Hearing, the Company expects to be able to commence site preparation and construction activities for the Phoenix In-Situ Recovery ("ISR") project in early 2026.
The announcement of the Hearing schedule follows the successful completion of multiple key regulatory milestones in late 2024, including (i) completion of the technical review phase of the federal EA approval process in November, (ii) acceptance by the CNSC of the Company's final Environmental Impact Statement ("EIS") for the Project in December, and (iii) the CNSC's determination of the sufficiency of Denison's Licence application, also in November. These accomplishments indicate that the CSNC staff support the advancement of the Project and are transitioning their efforts to prepare an evidence-based summary report for the Commission members that will govern the Hearing and render their decision on the EA and Licence once the Hearing is complete.
David Cates, President and CEO of Denison commented, "The scheduling of the Hearing and acceptance of the final federal EIS by the CNSC represent significant additional achievements for Denison in our efforts to obtain the regulatory approvals necessary to commence construction of the Phoenix ISR uranium mining operation. Importantly, obtaining clarity on the Hearing schedule significantly reduces uncertainty regarding the timeline for Federal project approvals and allows our operations team to finalize our construction planning efforts with greater precision. With the potential to commence construction in early 2026, we expect to be able to maintain our target of achieving first production from
About Denison
Denison is a leading uranium mining, development, and exploration company with interests focused in the
Denison's interests in
Additionally, through its
In 2024, Denison celebrated its 70th year in uranium mining, exploration, and development, which began in 1954 with Denison's first acquisition of mining claims in the
Follow Denison on Twitter @DenisonMinesCo
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS
Certain information contained in this press release constitutes 'forward-looking information', within the meaning of the applicable
In particular, this press release contains forward-looking information pertaining to the Company's expectations with respect to the Hearing and the EA and Licensing process, development plans for Wheeler River and the proposed ISR operation for the
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the results of the Hearing may not be as anticipated. In addition, Denison may decide or otherwise be required to discontinue development work if it is unable to maintain or otherwise secure the necessary approvals or resources (such as testing facilities, capital funding, etc.). Denison believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the factors discussed in the Company's Annual Information Form dated March 28, 2024 under the heading 'Risk Factors'. These factors are not, and should not be, construed as being exhaustive.
Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this press release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.
View original content to download multimedia:https://www.prnewswire.com/news-releases/denison-reports-cnsc-hearing-dates-for-phoenix-isr-project-302387197.html
SOURCE Denison Mines Corp.
FAQ
When are the CNSC hearing dates for Denison's Wheeler River Project (DNN)?
What is the expected construction start date for Denison's Phoenix ISR project (DNN)?
When does Denison Mines (DNN) expect first production from the Phoenix ISR project?