Cypress Development Update on Lithium Extraction Pilot Plant
Cypress Development Corp. (CYDVF) has announced progress on its pilot plant construction in Nevada, with equipment deliveries on track and assembly expected by month-end. The plant aims to extract lithium from the Clayton Valley Lithium Project, anticipated to be operational by July 2021. Cypress has partnered with Chemionex for expertise in direct lithium extraction technology, enhancing their pilot plant capabilities. The project follows recommendations from a prefesability study, with operations supervised by Continental Metallurgical Services.
- Pilot plant construction on schedule with operational targets set for July 2021.
- Partnership with Chemionex enhances direct lithium extraction capabilities, potentially improving project outcomes.
- Leased industrial site in Nevada to support administrative needs for lithium project.
- None.
VANCOUVER, British Columbia, May 20, 2021 (GLOBE NEWSWIRE) -- Cypress Development Corp. (TSX-V: CYP) (OTCQB: CYDVF) (Frankfurt: C1Z1) (“Cypress” or “the Company”) is pleased to provide an update on its ongoing pilot plant construction in Nevada. Equipment deliveries are on track and plant assembly is expected to commence by month end at the leased facility in Amargosa Valley. The plant remains on schedule is expected to be fully operational in July 2021.
The Company has entered into a services agreement with Chemionex Inc. (“Chemionex”), an Ontario based company and innovator in hydrometallurgical process development and direct lithium extraction technology (“DLE”) to advise on the DLE section of the pilot plant. Chemionex’s owner, Craig Brown, is an internationally recognized expert on aqueous-based chemical separations in the field of ion exchange, with extensive experience in electrochemistry, adsorption, filtration, membranes, evaporation and crystallization.
“We are pleased to have access to Chemionex and their considerable expertise in chemical processing in support of our pilot plant,” said Cypress CEO, Bill Willoughby. “Along with the invaluable contributions from our other contractors, we look forward to advancing our concepts to develop a unique opportunity in lithium.”
Program Objectives
The pilot plant is intended to confirm the extraction of lithium from the Company’s Clayton Valley Lithium Project, in accordance with the recommendations outlined in the Company’s Prefeasibility Study (Effective Date August 5, 2020 and Amended March 15, 2021). The initial operation of the pilot plant will focus on chloride-based leaching to confirm the previously announced results.
The plant at the Amargosa Valley site (owned and operated by del Sol Refinery Inc) will be configured into three primary sections: leaching, tailings handling and DLE. Offsite testing of product and stripped leach solutions will be conducted at NORAM Engineering and Construction Ltd’s BC Research laboratory in Richmond Canada. The overall plant operation will be supervised by Continental Metallurgical Services LLC in conjunction with Cypress and del Sol Refining personnel.
del Sol Refinery Facilities, Nevada photo:
https://www.cypressdevelopmentcorp.com/site/assets/files/3573/cyp_del_sol_refining_facility_photo_5.jpg
del Sol Refinery Facilities, Nevada photo:
https://www.cypressdevelopmentcorp.com/site/assets/files/3573/cyp_del_sol_refining_facility_photo_8.jpg
del Sol Refinery Facilities, Nevada photo:
https://www.cypressdevelopmentcorp.com/site/assets/files/3573/cyp_del_sol_refining_facility_photo_7.jpg
Each section in the plant will have specific objectives. The leaching section will work to optimize leach conditions and confirm lithium extraction into pregnant leach solution.
The tailings handling section will utilize a counter current decantation arrangement of thickener settlers and flocculant mixing determined by Pocock Industrial with the objective of determining materials handling, moisture content and water consumption.
Chemionex, under a separate purchase agreement, will provide the equipment for the DLE section of the pilot plant. Additionally, Cypress will be granted an option upon completion of the pilot plant program to license Chemionex’s proprietary Lionex DLE technology for commercial use at its Clayton Valley Lithium Project. Both the purchase and option agreements are at advanced stage of preparation.
The work conducted by NORAM Engineering will treat the concentrated lithium solution from the DLE portion of the pilot plant to produce lithium hydroxide and test the stripped leach solution for compatibility in recycling to the leaching portion of the plant.
Other Activities
The Company is proceeding with the due diligence work with respect to its recently announced letter agreement for water rights with Nevada Sunrise Gold Corp. The parties are working towards completion of a purchase agreement on or before June 7, 2021.
The Company also recently leased a 20-acre industrial site near Tonopah, Nevada. The location is at the site of a previous gold milling operation. Cypress is renovating the site which it intends to use for administrative purposes in conjunction with the Clayton Valley Lithium Project.
About Cypress Development Corp.:
Cypress Development Corp. is a publicly traded exploration company focused on developing the Company’s
Clayton Valley Lithium Project, Nevada claims map:
https://www.cypressdevelopmentcorp.com/site/assets/files/3573/cyp_cypress_-_albemarle_properties_map.jpg
To find out more about Cypress Development Corp. (TSX-V: CYP), visit our website at www.cypressdevelopmentcorp.com.
CYPRESS DEVELOPMENT CORP.
“Dr. Bill Willoughby”
_____________________________
WILLIAM WILLOUGHBY, PhD., PE
Chief Executive Officer
For further information contact myself or:
Don Myers
Cypress Development Corp.
Director, Corporate Communications
Telephone: 604-639-3851
Toll Free: 800-567-8181
Facsimile: 604-687-3119
Email: info@cypressdevelopmentcorp.com
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.
This release includes certain statements that may be deemed to be "forward-looking statements". All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.
FAQ
What is the current status of Cypress Development Corp.'s pilot plant construction?
Who is Chemionex and what role do they play in Cypress Development Corp.'s pilot plant?
When is the pilot plant expected to be operational?
What are the objectives of the pilot plant at Cypress Development Corp.?