STOCK TITAN

Cerrado Gold Announces Q4 and Annual 2023 Gold Production Results for Its Minera Don Nicolas Mine in Argentina

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary
Cerrado Gold Inc. reports Q4 2023 production results, with 15,202 ounces of gold equivalent (GEO) produced, annual GEO production of 51,688 ounces for 2023, and a delayed commercial production of the Las Calandrias heap leap project. The company also announces the completion of major capital programs at Minera Don Nicolas Mine in Argentina and the impact of fiscal policies on operations. The Monte Do Carmo project in Brazil reveals an updated After-Tax NPV5% of US$390 Million and IRR of 34%.
Positive
  • None.
Negative
  • Delayed commercial production of the Las Calandrias heap leap project impacting financial performance, hyper-inflation from fiscal policies in Argentina affecting operations, and limited gold production from the heap leach in the 4th quarter due to irrigation pause.

TORONTO, ON / ACCESSWIRE / January 24, 2024 / Cerrado Gold Inc. (TSX.V:CERT)(OTCQX:CRDOF) ("Cerrado" or the "Company") announces production results for the fourth quarter of 2023 ("Q4 2023") from the Minera Don Nicolas Mine in Santa Cruz Province, Argentina ("MDN"). Full financial results are expected to be released in late April 2024.

Q4 Operating Highlights

  • Q4 2023 GEO production of 15,202 ounces and annual GEO production of 51,688 ounces for 2023.
  • Ramp-up of production from the Las Calandrias heap leap project continues; commercial production delayed to end of Q1 2024.
  • Pre-strip at Calandrias Norte largely complete and higher-grade ore beginning to feed the mill.
  • Major capital programs at MDN complete, with current focus on delivering cashflow, rebuilding the balance sheet and longer-term exploration and mine life extension.

Operational results presented for Q4 2023 continued to be impacted by the slower than expected ramp-up of the Calandrias Heap Leach project during the quarter while a new crushing system was installed. The crushing unit is now operational, and mining rates are reaching planned capacity. Production is set to ramp-up over the first quarter of 2024 and achieve nameplate production rates from April thereafter. At Calandrias Norte, stripping activities were largely completed during the quarter and the pit is now beginning to deliver ore to the CIL plant at Martinetas. Ore is expected to fill the mill by mid-February onward. Head grades from Calandrias Norte are reconciling well with the model and grades are expected to increase as early benches are mined and deeper, higher grade levels accessed.

While production levels have begun to improve, the delay in the ramp up of the heap leach operations, the costs associated with stripping at Calandrias Norte and debt repayment associated with capital projects have had an impact on the financial performance at MDN. Newly introduced fiscal policies that have resulted in hyper-inflation have also had a significant impact on the operations of the business particularly as suppliers react to the new fiscal regime in Argentina.

Mark Brennan, CEO and Chairman commented, "While the second half of the year has been challenging starting with unusually harsh winter conditions in August resulting in a slower ramp up at the heap leach, we see operations at MDN positioned to turn the corner in February as we access higher grade ore from Calandrias Norte and the leach cycle at Las Calandrias normalizes. That said, recent changes to fiscal policies in Argentina have resulted in a highly inflationary environment, impacting operations as costs have increased and suppliers have reduced payment terms. The focus at MDN will move to generating cashflow from our capital investments in 2023 that allow us to rebuild the balance sheet and refocus our efforts on exploration and increasing the overall life of mine at MDN."

Stripping at Calandrias Norte continued during the quarter. The Pre-Strip is now largely complete allowing for fresh ore to fully feed the mill.

Ore milled increased during the fourth quarter as operations normalized. Production rates improved in Q4 as the operating environment returned to normal. However, additional gold production expected from the heap leach has been limited in the 4th quarter as irrigation was paused to allow for the completion of the installation of the new crushing circuit. Total production from the heap leach in the 4th quarter was 531 ounces. Please see Table 1. for a summary of key highlights for the fourth quarter and full year 2023. Sales for the quarter were slightly higher than production due to timing differences.

Ongoing work to optimize mine sequencing and exploration work to upgrade and define new sources of resources remains the key focus of development at MDN. The operations team is focused on numerous new growth projects aside from expanding current open pit resources, including the completion of the ramp up of Las Calandrias Heap Leach operation and the review of a potential new Heap Leach operation at Martinetas.

Table 1. Key Operating Information

Monte Do Carmo Update
At the Company's Monte Do Carmo ("MDC") project in Brazil, as announced on December 15th, Cerrado filed its 43-101 Updated Feasibility Study Technical Report for MDC ("FS") with an updated After-Tax NPV5% of US$390 Million and IRR of 34%. A Summary of the results of the FS are summarized in Table 1. Below. The License of Installation/Construction ("LI") is expected to be granted during the Q1 2024.

Table 1.

Summary of Key Results and Overall Project Economics Production

Units

Value

Steady State Throughput

Mtpa

1.92

Average Annual Production

K oz per annum

95,212

Life of Mine

Years

9.0

Life of Mine Au Recovery

%

95.64

Total Ore Mined - Open Pit

Mt

14.3

LOM Average Stripping Ratio

x

7.84

Total Ore Mined - Underground

Mt

2.5

Total Recovered Gold (Payable)

Ounces

856,905

Operating Costs

Units

Value

Mining

US$/tonne

17.01

Processing

US$/tonne

9.11

Water and Tailings Management

US$/tonne

1.45

G&A

US$/tonne

2.21

Total Cash Costs

US$/oz

583.7

AISC

US$/oz

686.6

Capital Expenditure

Units

Value

Initial Capital

US$ M

165.6

Contingency

US$ M

15.8

Total Upfront Capital

US$ M

181.4

Sustaining Capital

US$ M

66.0

Closure Costs

US$ M

15

Total Capital

US$ M

262.4

Financial Results

Units

Value

Pre-Tax NPV

US$ M

466

Pre-Tax IRR

%

37

Pre-Tax Payback Period

Years

2.0

After Tax NPV

US$ M

390

After Tax IRR

%

34

After Tax Payback Period

Years

2.1

Assumptions

Units

Value

Gold Price

US$/oz

1,750

Discount Rate

%

5.0


Review of Technical Information
The scientific and technical information in this press release has been reviewed and approved by Sergio Gelcich, P.Geo., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person as defined in National Instrument 43-101.

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused on gold projects in South America. The Company is the 100% owner of both the producing Minera Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina, and the highly prospective Monte Do Carmo development project, located in Tocantins State, Brazil. In Canada, Cerrado Gold is developing it's 100% owned Mont Sorcier Iron Ore and Vanadium project located outside of Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through continued operational optimization and is growing production through its operations at the Las Calandrias Heap Leach project. An extensive campaign of exploration is ongoing to further unlock potential resources in our highly prospective land package in the heart of the Deseado Masiff.

In Brazil, Cerrado is rapidly advancing the Serra Alta deposit at its Monte Do Carmo Project, through feasibility and into production. Serra Alta is expected to be a high-margin and high-return project with significant exploration potential on an extensive and highly prospective 82,542 hectare land package.

In Canada, Cerrado holds a 100% interest in the Mont Sorcier Iron Ore and Vanadium Project, which has the potential to produce a premium iron ore concentrate over a long mine life at low operating costs and low capital intensity. Furthermore, its high grade and high purity product facilitates the migration of steel producers from blast furnaces to electric arc furnaces contributing to the decarbonisation of the industry and the achievement of SDG goals.

For more information about Cerrado please visit our website at: www.cerradogold.com.

Mark BrennanMike McAllister
CEO and ChairmanVice President, Investor Relations
Tel: +1-647-805-5662
mmcallister@cerradogold.com

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute "forward-looking information" (collectively, "forward-looking statements") within the meaning of the applicable Canadian securities legislation, all statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements regarding the business and operations of Cerrado. In making the forward- looking statements contained in this press release, Cerrado has made certain assumptions, including, but not limited to the ramp-up of the Calandrias Heal Leach project, stripping activities and head grades at Calandrias Norte, expectations regarding MDN operations and financial performance generally, and expectations regarding permitting at Monte Do Carmo including granting of the LI. Although Cerrado believes that the expectations reflected in forward-looking statements are reasonable, it can give no assurance that the expectations of any forward-looking statements will prove to be correct. Known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Such factors include, but are not limited to general business, economic, competitive, political and social uncertainties. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this press release. Except as required by law, Cerrado disclaims any intention and assumes no obligation to update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking statements or otherwise.

SOURCE: Cerrado Gold Inc.



View the original press release on accesswire.com

FAQ

What were Cerrado Gold Inc.'s Q4 2023 GEO production results?

Cerrado Gold Inc. reported 15,202 ounces of gold equivalent (GEO) produced in Q4 2023.

What is the impact of fiscal policies on Cerrado Gold Inc.'s operations?

Fiscal policies in Argentina have resulted in hyper-inflation, impacting operations as costs have increased and suppliers have reduced payment terms.

What are the financial results of Cerrado Gold Inc.'s Monte Do Carmo project?

The updated After-Tax NPV5% of Cerrado Gold Inc.'s Monte Do Carmo project is US$390 Million with an IRR of 34%.

CERRADO GOLD INC

OTC:CRDOF

CRDOF Rankings

CRDOF Latest News

CRDOF Stock Data

25.43M
53.10M
19.01%
5.96%
Gold
Basic Materials
Link
United States of America
Toronto