U.S. Gold Corp. Completes Second of Three Mine Operating Permit Conditions for the CK Gold Project in Wyoming
U.S. Gold Corp. announced the acceptance of a $5.1 million Mine Reclamation Bond by the Wyoming Department of Environmental Quality (WDEQ), fulfilling two of the three requirements for the CK Gold Project's Mine Operating Permit. The company previously secured the Water Discharge Permit and is awaiting the Air Quality Permit, expected soon. This progression furthers the CK Gold Project's development, with updated economic forecasts and project financing in sight. The feasibility study update, paused in March 2023, is set to resume and conclude post the third quarter of 2024.
- Acceptance of $5.1 million Mine Reclamation Bond by WDEQ.
- Completion of two out of three required permits for CK Gold Project.
- Anticipation of Air Quality Permit issuance shortly.
- Feasibility study update and completion resumption by Q3 2024.
- Progress towards project financing and economic forecast updates.
- Suspension of feasibility study in March 2023 due to various disruptions.
- Remaining pending Air Quality Permit for unconditional approval of Mine Operating Plan.
Insights
U.S. Gold Corp.’s recent progress in securing the Mine Reclamation Bond and Water Discharge Permit for the CK Gold Project marks substantial strides in their journey toward operational readiness. The reclamation bond, which required posting
The anticipation of the Air Quality Permit, already deemed technically complete, suggests that the final hurdle might be cleared smoothly, keeping the project timeline intact. This adherence to schedule is important as delays can lead to increased costs and potential revenue losses. Investors should note that the completion of these permits will likely lead to the finalization of the feasibility study, providing more concrete data on the project’s economic viability.
Overall, the milestone achievements reflect the company’s capability in navigating regulatory landscapes, which is essential for project success. However, investors should remain vigilant regarding any potential hitches in the air quality permit approval process, as unexpected delays can still occur.
The advancement of the CK Gold Project is a promising development for U.S. Gold Corp. from a financial perspective. The company is updating its economic forecasts considering current market conditions, which is important given the volatile nature of commodity prices. An ideally located, fully permitted gold and copper project can significantly enhance the company’s financial outlook, especially with rising commodity prices. Investors should monitor the forthcoming feasibility study, as it will provide detailed insights into the project's financial metrics, including projected revenues, costs and profitability.
There’s a clear indication of management’s commitment to minimizing shareholder dilution, which is a positive sign for long-term investors. The current measures suggest a focus on preserving equity value, which is often a concern during capital-intensive project phases.
Receives Mine Reclamation Bond Acceptance for the Mine Operating Permit
In commenting on the acceptance, George Bee, President, CEO and Director of U.S. Gold said, "WDEQ's acceptance of the reclamation bond, along with the issuance of the Water Discharge Permit announced last week, satisfies two of the three conditions associated with the Mine Operating Permit, further cementing that major milestone, as U.S. Gold progresses along the pathway to development. The remaining condition, receipt of the Air Quality Permit, is anticipated shortly. We believe that the Air Quality Permit submission is technically complete having been through rigorous review. The application is with the WDEQ Air Quality Division following the remaining statutory steps prior to consideration for approval. We remain on track to receive unconditional approval of the Mine Operating Plan in hand, around mid-year, as per prior guidance."
Luke Norman, Executive Chairman of U.S. Gold, added, "The CK Gold Project continues to advance with the major permitting almost complete. The U.S. Gold team is finalizing updates to project economic forecasts, taking into consideration updates to pricing on both the cost and revenue sides of the equation. An ideally located, fully permitted gold and copper project positioned to leverage rising commodity prices is anticipated to be immensely accretive for our investors. As significant shareholders of the Company, we are committed to forging the pathway to project financing without undue dilution to our fellow shareholders."
Background
U.S. Gold Corp. pivoted from a purely exploration focus on its highly prospective assets in
In August 2020, U.S. Gold's management team engaged in the development of the CK Gold Project, previously known as Copper King, which had lain dormant for several years. While Copper King was recognized and explored on multiple occasions, following limited underground mining around one hundred years ago, the last study on the CK Gold Project was a Preliminary Economic Assessment authored by Mine Development Associates Inc. in 2012.
The Mine Reclamation Bond, a requirement under WDEQ statutes, involved posting
With the approval of the Mine Operating Permit, Water Discharge Permit and acceptance of the Mine Reclamation Bond, work on a prefeasibility study update and completion of the feasibility study has recommenced. The feasibility study work, awarded to Samuel Engineering Inc. ("Samuel") in April 2022, was suspended in March 2023. The decision to suspend Samuel's work on the feasibility study was made for three reasons: first, the Company did not want a "stale-dated" study in relation to the permit approval timeframe; second, price and supply disruption ensued following the COVID-19 pandemic; and third, there was a need to recognize some of the changes and additions that came about as a consequence of WDEQ's review of the CK Gold Project. Engineering work is well advanced with the process plant design largely complete, and updated bids for major equipment are now being solicited. We are on track to update the prefeasibility study by the third quarter of 2024 and finalize the feasibility study sometime thereafter. We are also working to incorporate project upside opportunities in the feasibility study.
About U.S. Gold Corp.
U.S. Gold Corp. is a publicly traded,
Cautionary Note Regarding Forward-Looking Statements
Certain statements in this press release are forward-looking within the meaning of the Private Securities Litigation Reform Act of 1995. These statements may be identified by the use of forward-looking words such as "anticipate," "believe," "forecast," "estimated," and "intend," among others. These forward-looking statements include statements relating to the CK Gold Project, including, our expected timing and receipt of the Air Quality Permit, the expected timing and receipt of unconditional approval to move forward with the Mine Operating Plan, the expected timing and completion of the update of the prefeasibility study, the expected timing and completion of the feasibility study, and the ultimate development of the CK Gold Project. There are a number of factors that could cause actual events to differ materially from those indicated by such forward-looking statements. These factors include, but are not limited to, risks arising from: market and other conditions, the prevailing market conditions for metal prices and mining industry cost inputs, environmental and regulatory risks, changes in interpretations of geological, geostatistical, metallurgical, mining or processing information, risks faced by junior companies generally engaged in exploration activities, whether U.S. Gold Corp. will be able to raise sufficient capital to develop the CK Gold Project and implement future drilling programs, the success or failure of future drilling programs, and other factors described in the Company's most recent Annual Report on Form 10-K, Quarterly Reports on Form 10-Q, and Current Reports on Form 8-K filed with the Securities and Exchange Commission, which can be reviewed at www.sec.gov. The Company has based these forward-looking statements on its current expectations and assumptions about future events. While management considers these expectations and assumptions to be reasonable, they are inherently subject to significant business, economic, competitive, regulatory, and other risks, contingencies, and uncertainties, most of which are difficult to predict and many of which are beyond the Company's control. The Company undertakes no duty to correct or update any information contained herein.
For additional information, please contact:
U.S. Gold Corp. Investor Relations
+1 800 557 4550
ir@usgoldcorp.gold
www.usgoldcorp.gold
View original content to download multimedia:https://www.prnewswire.com/news-releases/us-gold-corp-completes-second-of-three-mine-operating-permit-conditions-for-the-ck-gold-project-in-wyoming-302177465.html
SOURCE U.S. Gold Corp.
FAQ
What recent milestone did U.S. Gold Corp. reach for the CK Gold Project?
When did U.S. Gold Corp. receive acceptance of the Mine Reclamation Bond?
What permits has U.S. Gold Corp. secured for the CK Gold Project?
When is U.S. Gold Corp. expecting the Air Quality Permit for the CK Gold Project?