United States Antimony Corporation (UAMY) reported a stable antimony price of $6.26 per pound and achieved zero lost time incidents during May and June 2022, alongside no environmental spills. The company mined 6,726 tons of zeolite, with 2,795 tons sold. The Montana smelter sold 148.38 tons of antimony trioxide and 1.65 tons of antimony metal. Production upgrades at Bear River Zeolite are ongoing, including warehouse completion and operational enhancements. The company is investigating additional ore sources in Mexico and Guatemala.
- Achieved zero lost time incidents and environmental spills in May-June 2022.
- Mined 6,726 tons of zeolite and sold 2,795 tons during the same period.
- Montana smelter sold a total of 148.38 tons of antimony trioxide, indicating robust production.
- Operational upgrades at Bear River Zeolite include a new warehouse and ongoing improvements.
- Skilled labor shortages persist, affecting operational efficiency.
THOMPSON FALLS, MT / ACCESSWIRE / July 13, 2022 / United States Antimony Corporation (NYSE American:UAMY) (USAC-the Company) provides the following bi-monthly (May & June 2022) update.
Antimony Price
Safety and Environmental
All Company operations reported zero lost time or serious injury accidents during the May-June Period.
There were zero environmental spills, discharges, or incidents during the period. The previously announced (see NR- Jan. 15, 2022, March 15, 2022, May 15, 2022) pro-active program of legacy slag clean-up at the Madero Smelter continued and is now
Production (Unless otherwise specified, tons = metric tons)
Bear River Zeolite ("BRZ"): | May | June | Total |
Mined Tons: | 3,060 | 3,666 | 6,726 |
Crushed Tons: | 966 | 728 | 1,694 |
Tons Sold: | 1431 | 1364 | 2795 |
Montana Smelter: | May | June | Total |
Antimony Trioxide sold (tons): | 49.15 | 99.23 | 148.38 |
Antimony Metal Sold (tons) | 0 | 1.65 | 1.65 |
Antimony Trisulfide produced (lbs.): | 6,173 | 6,667 | 12,840 |
Operation Upgrades
BRZ
The new 50' x 100' warehouse has been completed. The new 40' x 60' service shop is
The recently purchased CAT 740 articulated haul truck and CAT 992 loader are both operating reliably in the mine pit. The experimental testing program of comparing dozer ripping to drilling & blasting of ore continued. An alternative ripping procedure has shown that ripping is superior in reducing the quantity of oversize in the crusher feed. Primary production will now be focused on ripping with drilling and blasting capabilities maintained in the event of dozer downtime.
Montana Antimony Metal and Antimony Oxide
The operating team continues to achieve production goals. Skilled labor shortages continue to be a problem but have improved over the last few months.
Ambri Inc.
Shipment of pure antimony metal to Ambri Inc. totaled 3,306 pounds.
Antimony Trisulphide Montana
Modifications, including the design and installation of a low volume air cleaning system have eliminated the previous problem of out-gassing entering the chamber between the crucible and the electric heating elements resulting in corrosion of the elements. Concerns with short life of the silicon carbide crucibles have been addressed by sourcing crucibles with a different material and adjusting charge weight sizes. Crucible life has now doubled. Delivery of the two additional furnaces (we are presently operating two furnaces) is expected in Q3 in anticipation of additional supplies of antimony trisulphide concentrate from Mexico.
Processing of the original 35 metric ton truckload of antimony trisulphide powder (provided 4 years ago) has been completed. An additional 20 metric tons was delivered to our Montana smelter in late June.
Antimony Trisulphide Supply Mexico, et al.
Two flotation tests have been conducted on ore from the company's mines in the Soyatal district of Mexico. Eighty (80) metric tons of ore were delivered to and treated in our Puerto Blanco flotation facility, yielding 2.7 metric tons of dry concentrate averaging
US Antimony is looking at the same model for additional sources of feed for the production of trisulphide from several mines that we have an agreement with in Guatemala. We are also investigating sources of trisulphide feed and antimony feed from Alaska, Eastern Canada, Australia, and Mexico.
Los Juarez Property
Our geologist in Mexico has completed a 1km x 3 km grid survey of the Los Juarez property. A total of 236 rock and soil samples from this grid have been collected and are being sent to the SGS lab in Durango (ISO/IEC 17025 accredited) for analysis of Sb, Au, Ag, and other trace elements. A geophysical company has been selected and local labor will assist on the completion of the geophysical survey which is anticipated to commence in Q3. The geologist has mapped mineralized intrusions in proximity to the jasperoid areas. The relationship between intrusive bodies and jasperoids will be further evaluated to assist in defining and modelling drilling targets over this extensive area of mineralization.
Forward Looking Statements: This Press Release contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934 that are based upon current expectations or beliefs, as well as a number of assumptions about future events, including matters related to the Company's operations, pending contracts and future revenues, ability to execute on its increased production and installation schedules for planned capital expenditures and the size of forecasted deposits. Although the Company believes that the expectations reflected in the forward-looking statements and the assumptions upon which they are based are reasonable, it can give no assurance that such expectations and assumptions will prove to have been correct. The reader is cautioned not to put undue reliance on these forward-looking statements, as these statements are subject to numerous factors and uncertainties. In addition, other factors that could cause actual results to differ materially are discussed in the Company's most recent filings, including Form 10-KSB with the Securities and Exchange Commission.
CONTACT:
United States Antimony Corp.
PO Box 643 47 Cox Gulch Rd.
Thompson Falls, Montana 59873-0643
E-Mail: info@unitedstatesantimony.com Phone: 928 234 5227
SOURCE: United States Antimony Corp.
View source version on accesswire.com:
https://www.accesswire.com/708358/US-Antimony-Provides-May--June-Operations-Details
FAQ
What was the antimony price reported by UAMY for May and June 2022?
How much zeolite did UAMY mine in May and June 2022?
What production milestones did UAMY achieve in the Montana smelter during this period?
What are the ongoing operational improvements at UAMY's Bear River Zeolite?