Talisker Resources (TSX: TSK, OTCQX: TSKFF) has announced progress in mining operations at its Bralorne Gold Project in British Columbia. The company initiated development work at the Mustang Mine on March 19th, beginning with the blasting of a diamond drill bay on the 1120 ramp and starting vein access development on the 1075 level.
The company has completed 31.6m of 3x3 metre development for vein zone access and auxiliary development. Parallel development will soon commence on the 1105 level, providing multiple extraction headings on the Alhambra vein. Talisker anticipates reaching mineralized vein material by the third week in April.
Talisker Resources (TSX: TSK, OTCQX: TSKFF) ha annunciato progressi nelle operazioni minerarie presso il suo Bralorne Gold Project nella Columbia Britannica. L'azienda ha avviato i lavori di sviluppo presso la Mustang Mine il 19 marzo, iniziando con l'esplosione di una baia per perforazioni a diamante sulla rampa 1120 e avviando lo sviluppo dell'accesso alla vena al livello 1075.
L'azienda ha completato 31,6 metri di sviluppo 3x3 metri per l'accesso alla zona vena e per lo sviluppo ausiliario. Lo sviluppo parallelo inizierà presto al livello 1105, fornendo molteplici aperture di estrazione sulla vena Alhambra. Talisker prevede di raggiungere il materiale mineralizzato della vena entro la terza settimana di aprile.
Talisker Resources (TSX: TSK, OTCQX: TSKFF) ha anunciado avances en las operaciones mineras en su Bralorne Gold Project en Columbia Británica. La compañía inició trabajos de desarrollo en la Mustang Mine el 19 de marzo, comenzando con la voladura de una bahía de perforación de diamante en la rampa 1120 y comenzando el desarrollo de acceso a la veta en el nivel 1075.
La empresa ha completado 31.6 metros de desarrollo de 3x3 metros para el acceso a la zona de veta y desarrollo auxiliar. El desarrollo paralelo comenzará pronto en el nivel 1105, proporcionando múltiples frentes de extracción en la veta Alhambra. Talisker anticipa alcanzar material mineralizado de la veta para la tercera semana de abril.
탈리스커 리소스 (TSX: TSK, OTCQX: TSKFF)는 브리티시컬럼비아의 브랄론 금 프로젝트에서 채굴 작업의 진전을 발표했습니다. 이 회사는 3월 19일 머스탱 광산에서 개발 작업을 시작했으며, 1120 경사면에서 다이아몬드 드릴 베이 폭파를 시작하고 1075 레벨에서 광맥 접근 개발을 시작했습니다.
회사는 광맥 구역 접근 및 보조 개발을 위해 3x3 미터 개발을 31.6미터 완료했습니다. 평행 개발은 곧 1105 레벨에서 시작되어 알람브라 광맥에서 여러 채굴 출구를 제공할 것입니다. 탈리스커는 4월 셋째 주에 광맥의 광물화된 물질에 도달할 것으로 예상하고 있습니다.
Talisker Resources (TSX: TSK, OTCQX: TSKFF) a annoncé des progrès dans les opérations minières de son Bralorne Gold Project en Colombie-Britannique. La société a commencé les travaux de développement à la Mustang Mine le 19 mars, en commençant par le dynamitage d'une baie de forage diamant sur la rampe 1120 et en lançant le développement de l'accès à la veine au niveau 1075.
La société a complété 31,6 mètres de développement en 3x3 mètres pour l'accès à la zone de veine et le développement auxiliaire. Un développement parallèle commencera bientôt au niveau 1105, offrant plusieurs fronts d'extraction sur la veine Alhambra. Talisker prévoit d'atteindre le matériau de veine minéralisée d'ici la troisième semaine d'avril.
Talisker Resources (TSX: TSK, OTCQX: TSKFF) hat Fortschritte bei den Bergbauarbeiten an seinem Bralorne Gold Project in British Columbia bekannt gegeben. Das Unternehmen hat am 19. März mit den Entwicklungsarbeiten in der Mustang Mine begonnen, indem es eine Sprengung einer Diamantbohrbucht an der Rampe 1120 durchführte und mit der Entwicklung des Zugangs zur Gang auf der Ebene 1075 begann.
Das Unternehmen hat 31,6 m von 3x3 Metern für den Zugang zur Gangzone und für Hilfsentwicklungen abgeschlossen. Parallelentwicklungen werden bald auf der Ebene 1105 beginnen, was mehrere Abbaufronten an der Alhambra-Gang ermöglichen wird. Talisker rechnet damit, in der dritten Aprilwoche mineralisiertes Gangmaterial zu erreichen.
- Development work at Mustang Mine commenced on schedule
- Multiple extraction headings being established on Alhambra vein
- Mining operations progressing with 31.6m of development completed
- None.
TORONTO, March 26, 2025 (GLOBE NEWSWIRE) -- Talisker Resources Ltd. (“Talisker” or the “Company”) (TSX: TSK, OTCQX: TSKFF) is pleased to provide an operational update on mining activities from its Bralorne Gold Project located in British Columbia. Talisker commenced development work as planned at the Mustang Mine on March 19th with blasting of a diamond drill bay on the 1120 ramp followed with the initiation of vein access development the 1075 level. To date, 31.6m of 3x3 metre development has been completed for vein zone access and auxiliary development. Parallel development is soon to begin on the 1105 level providing multiple extraction headings on the Alhambra vein. Talisker expects to reach mineralized vein material by the third week in April.
Terry Harbort, CEO of Talisker stated, “We are pleased with the smooth start to mining operations at Mustang and excited to be developing on the 1075 level and soon the 1105 level towards the Alhambra vein.”
For further information, please contact:
Terry Harbort
President and CEO
terry.harbort@taliskerresources.com
+1 416 357 0227
About Talisker Resources Ltd.
Talisker (taliskerresources.com) is a junior resource company involved in the exploration and development of gold projects in British Columbia, Canada. Talisker’s flagship asset is the high-grade, fully permitted Bralorne Gold Project where the Company is currently transitioning into underground production at the Mustang Mine. Talisker projects also include the Ladner Gold Project, an advanced stage project with significant exploration potential from an historical high-grade producing gold mine and the Spences Bridge Project where the Company has a significant landholding in the emerging Spences Bridge Gold Belt, and several other early-stage Greenfields projects.
Caution Regarding Forward Looking Statements
Certain statements contained in this press release constitute forward-looking information. These statements relate to future events or future performance. The use of any of the words “could”, “intend”, “expect”, “believe”, “will”, “projected”, “estimated” and similar expressions and statements relating to matters that are not historical facts are intended to identify forward-looking information and are based on Talisker’s current belief or assumptions as to the outcome and timing of such future events. Various assumptions or factors are typically applied in drawing conclusions or making the forecasts or projections set out in forward-looking information. Those assumptions and factors are based on information currently available to Talisker. Although such statements are based on reasonable assumptions of Talisker’s management, there can be no assurance that any conclusions or forecasts will prove to be accurate.
Forward looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined, risks relating to variations in grade or recovery rates, risks relating to changes in mineral prices and the worldwide demand for and supply of minerals, risks related to increased competition and current global financial conditions, access and supply risks, reliance on key personnel, operational risks regulatory risks, including risks relating to the acquisition of the necessary licenses and permits, financing, capitalization and liquidity risks, title and environmental risks and risks relating to the failure to receive all requisite shareholder and regulatory approvals.
The forward-looking information contained in this release is made as of the date hereof, and Talisker is not obligated to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by applicable securities laws. Because of the risks, uncertainties and assumptions contained herein, investors should not place undue reliance on forward-looking information. The foregoing statements expressly qualify any forward-looking information contained herein.