Torex Gold Provides Q3 2024 Update on Media Luna Project and Increases 2024 Production Guidance
Torex Gold reports its Media Luna Project is 87% complete and announces increased 2024 production guidance. The company has rescheduled plant tie-in from November 2024 to February 2025, with first copper concentrate expected in Q1 2025. The revised schedule allows for increased 2024 gold production to 450,000-470,000 ounces, up from previous guidance of 400,000-450,000 ounces. Project expenditures of $840 million have been incurred, with $110 million remaining. The company maintains strong liquidity of $345 million, providing a $235 million funding buffer.
Torex Gold riporta che il suo progetto Media Luna è completo al 87% e annuncia una guida aumentata per la produzione del 2024. L'azienda ha riprogrammato il collegamento dell'impianto da novembre 2024 a febbraio 2025, con il primo concentrato di rame previsto nel primo trimestre del 2025. Il programma rivisto consente un aumento della produzione di oro nel 2024 a 450.000-470.000 once, rispetto alla precedente guida di 400.000-450.000 once. Sono state sostenute spese per il progetto di 840 milioni di dollari, restando 110 milioni. L'azienda mantiene una solida liquidità di 345 milioni di dollari, fornendo un buffer di finanziamento di 235 milioni di dollari.
Torex Gold informa que su proyecto Media Luna está completo en un 87% y anuncia una guía de producción incrementada para 2024. La compañía ha reprogramado la conexión de la planta de noviembre de 2024 a febrero de 2025, con el primer concentrado de cobre esperado en el primer trimestre de 2025. El cronograma revisado permite aumentar la producción de oro para 2024 a 450,000-470,000 onzas, por encima de la guía anterior de 400,000-450,000 onzas. Se han incurrido gastos del proyecto de 840 millones de dólares, quedando 110 millones. La empresa mantiene una sólida liquidez de 345 millones de dólares, proporcionando un colchón de financiamiento de 235 millones de dólares.
Torex Gold는 미디어 루나 프로젝트가 87% 완료되었으며 2024년 생산 가이드를 증가시키는 것을 발표했습니다. 회사는 공장 연결을 2024년 11월에서 2025년 2월로 재조정하였고, 2025년 1분기에 첫 구리 농축물이 예상됩니다. 수정된 일정은 2024년 금 생산을 450,000-470,000 온스로 증가시킬 수 있도록 해 주며, 이는 이전 가이드인 400,000-450,000 온스에서 증가한 수치입니다. 프로젝트 비용으로 8억 4천만 달러가 발생하였고, 1억 1천만 달러가 남아 있습니다. 회사는 3억 4천5백만 달러의 강력한 유동성을 유지하고 있으며, 2억 3천5백만 달러의 자금 여유를 제공합니다.
Torex Gold annonce que son projet Media Luna est complet à 87% et informe d'une augmentation des perspectives de production pour 2024. La société a reprogrammé le raccordement de l'usine de novembre 2024 à février 2025, avec le premier concentré de cuivre attendu au premier trimestre 2025. Le calendrier révisé permet d'augmenter la production d'or en 2024 à 450 000-470 000 onces, contre une précédente prévision de 400 000-450 000 onces. Des dépenses de projet de 840 millions de dollars ont été engagées, avec 110 millions de dollars restant. L'entreprise maintient une liquidité solide de 345 millions de dollars, offrant un coussin de financement de 235 millions de dollars.
Torex Gold berichtet, dass sein Projekt Media Luna zu 87% abgeschlossen ist und gibt eine angepasste Produktionsprognose für 2024 bekannt. Das Unternehmen hat den Anlagenanschluss von November 2024 auf Februar 2025 verschoben, wobei der erste Kupferkonzentrat im ersten Quartal 2025 erwartet wird. Der überarbeitete Zeitplan ermöglicht eine Steigerung der Goldproduktion für 2024 auf 450.000-470.000 Unzen, gegenüber der vorherigen Prognose von 400.000-450.000 Unzen. Projektkosten in Höhe von 840 Millionen Dollar sind angefallen, wobei noch 110 Millionen Dollar verbleiben. Das Unternehmen bleibt mit 345 Millionen Dollar stark liquide und bietet einen Finanzierungspuffer von 235 Millionen Dollar.
- Increased 2024 gold production guidance to 450,000-470,000 ounces
- Strong liquidity position with $345 million available at quarter end
- Project 87% complete with engineering concluded and procurement at 97%
- Underground development rates exceeding budget at over 1,300 meters monthly
- Delayed plant tie-in schedule from November 2024 to February 2025 due to equipment delivery delays
- Additional project costs expected due to extended project period
- Total cash costs and all-in sustaining costs trending toward upper end of guidance range
Project
(All amounts expressed in U.S. dollars unless otherwise stated)
Toronto, Ontario--(Newsfile Corp. - October 30, 2024) - Torex Gold Resources Inc. (the "Company" or "Torex") (TSX: TXG) provides a Q3 2024 update on the development of its Media Luna Project ("Media Luna") and increases 2024 production guidance with a decision to undertake the tie-ins and upgrades to the processing plant in February 2025. Unless otherwise stated, progress and milestones referenced in this press release are as of September 30, 2024.
Jody Kuzenko, President & CEO of Torex, stated:
"Development and construction of Media Luna now stands at
"With the overall project construction period nearing completion, our focus has shifted to refining the plan and schedule for the plant tie-in period. As a result of modestly longer delivery windows for critical electrical equipment (primarily switchgear) due in part to recent hurricane activity in the Gulf region, we have rescheduled the start of the plant tie-in period from November 2024 to February 2025, with first copper concentrate production expected in Q1 and commercial production shortly thereafter. With the additional production associated with the pushback in the open pit, a clear contingency plan has long been established for the possibility of a Q1 2025 tie-in period. The overriding business priority has always been centered around readiness to execute the tie-in period and containing this period to no longer than four weeks.
"The refined schedule comes with several benefits - most notably increased gold production in 2024 with another four weeks of production. Importantly, the project team will have the opportunity to conduct advance testing on key processing plant systems, thereby potentially reducing the time required to complete the tie-ins and upgrades to less than four weeks as originally scheduled. Ore production from the ELG Open Pits, ELG Underground, and Media Luna Underground will continue uninterrupted, with ore from Media Luna stockpiled ahead of commissioning the flotation circuits.
"As at quarter end,
INCREASED 2024 PRODUCTION GUIDANCE
With the tie-in period for the processing plant now scheduled to begin in February 2025, gold production in 2024 is forecast to be 450,000 to 470,000 ounces versus original guidance of 400,000 to 450,000 ounces, given the benefit of an additional four weeks of production than was assumed within initial guidance.
Table 1: Updated operational guidance for 2024
Initial 2024 Guidance | Updated 2024 Guidance | ||
Production | |||
Gold | oz | 400,000 to 450,000 | 450,000 to 470,000 |
Gold equivalent | oz AuEq | 410,000 to 460,000 | 460,000 to 480,000 |
Per the contingency plan established, the processing plant will continue to process ore from ELG Open Pit and ELG Underground operations through to the tie-in period for the processing plant in February, while the ramp-up of Media Luna Underground will continue unabated with ore stockpiled ahead of commissioning the new copper ("Cu") and iron sulphide ("FeS") flotation circuits.
Total cash costs (
On a gold equivalent basis, full year production is now estimated at 460,000 to 480,000 ounces from original guidance of 410,000 to 460,000 ounces. Gold equivalent total cash costs and all-in sustaining costs guidance is unchanged.
CAPITAL EXPENDITURES
During Q3 2024,
Table 2: Media Luna Project - Project Expenditures (April 1, 2022 through September 30, 2024)
Millions of U.S. dollars | Project To Date Q3 2024 |
Project expenditures per 2022 Technical Report | |
Adjustment for Q1 2022 underspend | |
Total budgeted spend post March 31, 2022 | |
Final adjustments for stronger Mexican peso / out-of-scope items (June 30, 2024) | |
Revised budgeted spend | |
Expenditures incurred post March 31, 2022 | ( |
Remaining spend | |
Committed expenditures (inclusive of total project expenditures incurred to date) | |
Uncommitted expenditures |
Notes to Table
1) Project period commenced on April 1, 2022; excludes capital expenditures incurred prior to Board approval on March 31, 2022.
2) Project period is defined as April 1, 2022 through declaration of commercial production.
3) Excludes borrowing costs capitalized.
The capital expenditure impact of the schedule adjustment is expected to be modest, with the project team at site now looking at opportunities to offset the costs associated with the extended project period. Of note, given the longer pre-commercial period with the rescheduled tie-ins, capital expenditures related to accelerated underground development will be classified as non-sustaining for that period, versus sustaining had the prior plant tie-in schedule been maintained.
PROJECT COMPLETION
As at quarter end, development of Media Luna was tracking largely to plan with the project
Based on the current schedule related to critical electrical equipment delivery, the tie-in period for the processing plant has been rescheduled to commence in February, with first copper concentrate production in Q1. The updated schedule enables the project team to undertake advance testing on key processing systems outside of the plant tie-in, with a view to potentially reducing the downtime period to less than four weeks.
As previously guided, just in time deliveries of critical electrical equipment was anticipated to be a key risk given little float in the schedule. After reviewing the risks around the tie-in period pushing into the December holiday season, weighed against the existing contingency plan associated with the extension of open pit production into Q2 2025 via the layback in the El Limón pit last year, the greater overall benefit to the business mitigated in favour of rescheduling the processing plant tie-in schedule to February 2025.
Table 3: Media Luna Project - Project Completion (April 1, 2022 through September 30, 2024)
Project To Date Q3 2024 | |
Procurement | |
Engineering | |
Underground development/construction | |
Surface construction | |
Total Project |
Notes to Table
1) Physical progress measured starting as of April 1, 2022; excludes progress made prior to Board approval on March 31, 2022.
2) Project period is defined as April 1, 2022 through declaration of commercial production.
3) Total Project is weighted average based on activity levels.
It should be noted that the ramp-up of the Media Luna underground mine is separate from the completion and commissioning of the processing plant. As such, the revised plant tie-in schedule will have no impact on ore production from Media Luna, which will be stockpiled ahead of wet commissioning of the Cu and FeS flotation circuits.
Engineering
Engineering over the quarter focused primarily on finalization of electrical deliverables and incorporation of vendor information. Engineering work for the project is now complete and will continue to support in the field as necessary to address any installation issues.
Procurement
Procurement for Media Luna is substantially complete, sitting at
Notable orders completed during the quarter included electrical cable, network cabinets and LTE infrastructure for the underground, flotation switchgear, water and slurry pumps, geotextiles for the Guajes pit, fiber optic cable, and carbon steel pipe and fittings. Four battery electric loaders were also delivered to site and have now been commissioned.
Underground Development and Construction
Steady progress was made underground at Media Luna during the quarter. Installation of the Guajes conveyor is nearing completion and commissioning is expected imminently. The breakthrough between Media Luna Upper and Media Luna Lower was achieved at the mine internal ramp, opening up access to three additional mining blocks to support production. The feed chute and chute liner plates were installed at ore pass #8 and tailings feed pipe installation continues to progress in anticipation of the paste plant completion. Vibratory feeders and arch gates below both ore bins 1 and 2 at the 690 level are also substantially complete and commissioning will take place in coordination with the Guajes conveyor (Figure 1).
Following completion of definition drilling for the first seven stopes planned to be taken in the 2024 mine plan, steady progress has been made on definition drilling of stopes in the 2025 mine plan. Drilling to date has yielded positive results with tonnes and grade in line with expectations, aside from some minor spatial variations as is typical with new underground areas. Underground development rates have been strong, with monthly lateral development rates in excess of 1,300 metres over the last few months (including over 1,400 metres in October) relative to the original budget of 1,200 metres per month. As a result, underground development is now slightly ahead of plan.
The Company will continue with aggressive definition drilling and underground development programs in 2025 with the target of having all stopes to be mined in 2026 drilled off by the end of the year and the aim of accelerating underground development. Both programs are expected to de-risk the ramp-up of underground operations to the design rate of 7,500 tonnes per day.
Figure 1: Ore bins feed chutes have been assembled at the 690 level
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_ore%20bin.jpg
Surface Construction
Significant progress was made on surface construction, now at
Progress was also made on the installation of power infrastructure. At the 230 kV switchyard, transmission towers have been erected and the grounding grid has been installed (Figure 4). Block work was also completed on the electrical building while electrical trenches and duct banks were put in place. At the 230 kV substation, the two primary transformers have been installed (Figure 5). The transmission line between the switchyard and substation was hung during the quarter with connection to the substation now complete and switchyard expected to be completed in Q4 2024.
On the south side of the Balsas River, construction of the paste plant is also progressing well with installation of the thickener, binder silo, and building steel all having noticeably advanced (Figure 6). The paste plant remains on track to be completed in Q1 2025, with commissioning sequenced to occur after the processing plant infrastructure is commissioned.
Figure 2: Construction of the flotation area is advancing, with both e-houses and associated cables now installed. Progress was also made on the installation of the regrind mill and cleaner cells.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_002full.jpg
Figure 3: Construction of the water treatment plant is ongoing, with detox tanks for the first phase of water testing installed during the quarter
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_003full.jpg
Figure 4: Galvanized towers have been installed at the 230 kV switchyard to support the transmission line between the yard and the substation
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_004full.jpg
Figure 5: The 230 kV substation is substantially complete with main transformers in place
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_005full.jpg
Figure 6: Construction of the binder silo, thickener, and building steel at the paste plant
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_006full.jpg
Operational Readiness
In parallel with development and construction activities, the surface and underground operational readiness strategy continues to advance as planned. Operational readiness teams are accountable for ensuring that processes and systems for all new work areas are established and ready in advance of the handover from the project team to operations. This includes workforce transition planning and training, developing the operating strategy (including all standard operating procedures) and maintenance plans for all fixed and mobile equipment, blend and feed strategies, commissioning plans, first fills, concentrate shipment logistics, and all other requirements for a smooth ramp up.
Recruitment of personnel for both the underground and new process areas is well advanced. Of the new Media Luna recruits,
Negotiations with the various haulage companies for Cu concentrate transport to port distribution facilities are complete and contracts are being finalized. The Company is also in the final stages of settling contracts for the sale of Cu concentrate to a mix of traders and smelters. Metal payables are in line with that which was incorporated into the most recent Technical Report dated effective March 16, 2022, and filed on March 31, 2022 ("Technical Report").
PROJECT EXECUTION PLAN
Based on the updated schedule for the tie-in and upgrades of the processing plant as well as other deliverables, the project execution plan for Media Luna has been updated accordingly (Figure 7).
Figure 7: Project execution plan for the Media Luna Project
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/228339_2b08b6a9f436099f_007full.jpg
More detail on the Media Luna Project, including the Feasibility Study results, can be found in the Technical Report.
ABOUT TOREX GOLD RESOURCES INC.
Torex is an intermediate gold producer based in Canada, engaged in the exploration, development, and operation of its
FOR FURTHER INFORMATION, PLEASE CONTACT:
TOREX GOLD RESOURCES INC.
Jody Kuzenko
President and CEO
Direct: (647) 725-9982
jody.kuzenko@torexgold.com
Dan Rollins
Senior Vice President, Corporate Development & Investor Relations
Direct: (647) 260-1503
dan.rollins@torexgold.com
QUALIFIED PERSON
The technical and scientific information in this press release has been reviewed and approved by Dave Stefanuto, P. Eng, Executive Vice President, Technical Services and Capital Projects of the Company, and a qualified person under National Instrument 43-101.
CAUTIONARY NOTES ON FORWARD-LOOKING STATEMENTS
This press release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements that: tie-ins and upgrades to processing plant schedule moves to February 2025; first copper concentrate expected in Q1 2025 and commercial production shortly thereafter; installation of the Guajes conveyor is almost complete, with commissioning expected imminently; the project team will have the opportunity to conduct advanced testing on key processing plant systems, thereby potentially reducing the time required to complete the tie-ins and upgrades to less than four weeks as originally scheduled; with the tie-in period for the processing plant now scheduled to begin in February 2025, gold production in 2024 is forecast to be 450,000 to 470,000 ounces versus original guidance of 400,000 to 450,000 ounces; total cash costs (
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/228339
FAQ
What is Torex Gold's (TORXF) updated 2024 gold production guidance?
When will Torex Gold's (TORXF) Media Luna plant tie-in begin?
What is the current completion percentage of Torex Gold's (TORXF) Media Luna Project?