STOCK TITAN

TASEKO MINES PROVIDES FINANCING UPDATE FOR FLORENCE COPPER

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Negative)
Tags

VANCOUVER, BC, July 13, 2023 /PRNewswire/ - Taseko Mines Limited (TSX: TKO) (NYSE American: TGB) (LSE: TKO) ("Taseko" or the "Company") is pleased to provide an update on a number of recent financing initiatives.

On June 30, Taseko's corporate revolving credit facility was increased from US$50 million to US$80 million.  The accordion feature, which was added and announced in January, was fully underwritten and credit approved by ING Capital LLC who joins alongside the existing lender, National Bank.  The corporate facility is available for general corporate purposes, including to support the capital needs of the Florence Copper project.  The credit facility matures in July 2026 and is secured by first liens against Taseko's rights under the Gibraltar joint venture as well as the shares of Gibraltar Mines Ltd., Curis Holdings (Canada) Ltd., and Florence Holdings Inc. and contains customary covenants for a facility of this nature.

Also in late June, the Company closed an additional silver stream sale to Osisko Gold Royalties ("Osisko") for US$10.25 million for its incremental 12.5% share of Gibraltar Mine that Taseko purchased in March of this year from Sojitz Corporation. Taseko also extended the silver delivery threshold to coincide with the Company's recently updated mineral reserve estimate. 

Stuart McDonald, President & CEO of Taseko, stated, "The permitting process at Florence Copper is nearing an end and as we prepare for construction our focus is to ensure we have a strong balance sheet and a solid financing plan in place. We continue to evaluate construction financing proposals which will complement our current liquidity and the two transactions previously announced with Mitsui (US$50 million) and Bank of America (US$25 million). We have recently engaged Endeavour Financial to assist in executing on these financing initiatives and are confident that we can close the transactions needed to provide the capital for construction of the Florence Copper commercial production facility.

We have not issued any shares to-date under the US$50 million At-The-Market equity facility announced in May. This facility is an alternative financing option for Taseko but with no obligation for us to use."

For further information on Taseko, see the Company's website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations - 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

CAUTION REGARDING FORWARD-LOOKING INFORMATION 

This document contains "forward-looking statements" that were based on Taseko's expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus ("COVID-19") and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the "Florence Copper Project" or "Florence Copper") that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility ("PTF") and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency ("EPA") in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis ("MD&A"), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading "Risk Factors".

Cision View original content:https://www.prnewswire.com/news-releases/taseko-mines-provides-financing-update-for-florence-copper-301876951.html

SOURCE Taseko Mines Limited

Taseko Mines Limited

NYSE:TGB

TGB Rankings

TGB Latest News

TGB Stock Data

602.82M
293.35M
2.48%
30.6%
0.57%
Copper
Basic Materials
Link
United States of America
Vancouver