STOCK TITAN

Taseko Provides Construction Update on Florence Copper Project

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Taseko Mines (NYSE American: TGB) has provided an update on its Florence Copper project in Arizona. As of December 31, 2024, the project is 56% complete, with first copper production targeted before the end of 2025. Construction activities are on schedule with nearly 450,000 project hours worked without injuries or environmental incidents. The site currently has approximately 290 personnel.

Key activities in Q4 include:

  • Completion of process ponds and surface water runoff pond construction
  • Placement and welding of solvent extraction settler and launder modules
  • Construction of 17 production wells, totaling 51 out of 90 planned wells
  • Advancement in the main pipe corridor development and high-density polyethylene piping installation
  • Commencement of field-erected process and service tank construction
  • Mechanical and piping installations in the SX/EW plant
  • Near completion of structural steel erection for the solvent extraction pipe rack and ongoing piping installation
  • Start of electrical work
  • Erection of the water treatment building and preparation for the electrowinning building

Despite the Department of Energy’s denial of a 48C(e) tax credit application, Taseko maintains a strong financial position with C$330 million in liquidity, including an undrawn US$110 million revolving credit facility.

Taseko Mines (NYSE American: TGB) ha fornito un aggiornamento sul suo progetto di rame Florence in Arizona. Al 31 dicembre 2024, il progetto è completato al 56%, con la produzione di rame prevista prima della fine del 2025. Le attività di costruzione sono in linea con i programmi, avendo accumulato quasi 450.000 ore di lavoro senza incidenti o problemi ambientali. Attualmente, il sito ospita circa 290 persone.

Le attività chiave nel quarto trimestre includono:

  • Completamento della costruzione delle vasche di processo e della vasca di raccolta delle acque meteoriche
  • Installazione e saldatura dei moduli di estrazione del solvente e delle canalizzazioni
  • Costruzione di 17 pozzi di produzione, per un totale di 51 pozzi su 90 previsti
  • Progresso nello sviluppo del corridoio principale delle tubature e installazione di tubi in polietilene ad alta densità
  • Inizio della costruzione di serbatoi di processo e di servizio eretti in campo
  • Installazioni meccaniche e di tubazioni nell'impianto SX/EW
  • Quasi completamento dell'erezione dell'acciaio strutturale per il rack delle tubazioni di estrazione del solvente e installazione in corso delle tubazioni
  • Inizio dei lavori elettrici
  • Erezione del edificio di trattamento delle acque e preparazione per l'edificio di elettrolisi

Nonostante il rifiuto da parte del Dipartimento dell'Energia per una domanda di credito d'imposta 48C(e), Taseko mantiene una solida posizione finanziaria con 330 milioni di dollari canadesi di liquidità, compresi 110 milioni di dollari USA di una linea di credito rotativa non utilizzata.

Taseko Mines (NYSE American: TGB) ha proporcionado una actualización sobre su proyecto de cobre Florence en Arizona. Al 31 de diciembre de 2024, el proyecto está completado en un 56%, con la producción de cobre programada antes del final de 2025. Las actividades de construcción están programadas, habiendo trabajado casi 450,000 horas del proyecto sin incidentes ni problemas ambientales. Actualmente, el sitio cuenta con aproximadamente 290 personas.

Las actividades clave en el cuarto trimestre incluyen:

  • Finalización de la construcción de las balsas de proceso y de la balsa de escorrentía de agua superficial
  • Colocación y soldadura de los módulos de extracción de solventes y las canalizaciones
  • Construcción de 17 pozos de producción, totalizando 51 de los 90 pozos planificados
  • Avance en el desarrollo del corredor principal de tuberías e instalación de tuberías de polietileno de alta densidad
  • Inicio de la construcción de tanques de proceso y de servicio erigidos en el campo
  • Instalaciones mecánicas y de tuberías en la planta SX/EW
  • Casi finalización de la erección del acero estructural para el soporte de tuberías de extracción de solventes y en curso la instalación de tuberías
  • Inicio de trabajos eléctricos
  • Ereción del edificio de tratamiento de agua y preparación para el edificio de electrowinning

A pesar de la denegación por parte del Departamento de Energía de una solicitud de crédito fiscal 48C(e), Taseko mantiene una sólida posición financiera con 330 millones de dólares canadienses en liquidez, incluyendo 110 millones de dólares estadounidenses en una línea de crédito revolvente no utilizada.

타세코 마인즈 (NYSE American: TGB)는 애리조나의 플로렌스 구리 프로젝트에 대한 업데이트를 제공했습니다. 2024년 12월 31일 기준, 프로젝트는 56% 완료되었으며, 2025년 연말 이전에 최초의 구리 생산을 목표로 하고 있습니다. 건설 작업은 예정대로 진행되고 있으며, 450,000시간에 가까운 프로젝트 시간이 중상이나 환경 사고 없이 작업되었습니다. 현재 현장에는 약 290명의 인원이 있습니다.

4분기 주요 활동은 다음과 같습니다:

  • 프로세스 연못 및 표면 배수 연못 건설 완료
  • 용매 추출 침전기 및 파이프 모듈의 배치 및 용접
  • 17개의 생산 우물 건설, 총 90개의 계획된 우물 중 51개 완료
  • 주 배관 구역 개발 및 고밀도 폴리에틸렌 파이프 설치 진행
  • 현장에 세워진 공정 및 서비스 탱크 건설 시작
  • SX/EW 플랜트의 기계 및 배관 설치
  • 용매 추출 배관 랙에 대한 구조강철 조립 거의 완료 및 배관 설치 진행 중
  • 전기 작업 시작
  • 수처리 건물 건축 및 전기 침출 건물 준비

에너지부의 48C(e) 세금 공제 신청 거부에도 불구하고, 타세코는 3억 3천만 캐나다 달러의 유동성으로 강한 재무 상태를 유지하고 있으며, 미사용 1억 1천만 미국 달러의 회전 신용 한도가 포함되어 있습니다.

Taseko Mines (NYSE American: TGB) a fourni une mise à jour sur son projet de cuivre Florence en Arizona. Au 31 décembre 2024, le projet est achevé à 56 %, avec une production de cuivre prévue avant la fin de 2025. Les travaux de construction sont à l'heure, avec près de 450 000 heures de projet réalisées sans blessures ni incidents environnementaux. Le site compte actuellement environ 290 personnes.

Les activités clés du 4ème trimestre comprennent :

  • Achèvement de la construction des bassins de traitement et du bassin de ruissellement des eaux de surface
  • Placement et soudage des modules de séparation par solvant et des canalisations
  • Construction de 17 puits de production, totalisant 51 sur 90 prévus
  • Avancement dans le développement du couloir principal de tuyauterie et installation de tuyaux en polyéthylène haute densité
  • Début de la construction des réservoirs de traitement et de service érigés sur le terrain
  • Installations mécaniques et de tuyauteries dans l'usine SX/EW
  • Participation presque terminée de l'édification de l'acier structurel pour le support de tuyauterie de l'extraction de solvant et installation de tuyauteries en cours
  • Démarrage des travaux électriques
  • Érection du bâtiment de traitement des eaux et préparation pour le bâtiment d'électrolyse

Malgré le refus du Département de l'Énergie pour une demande de crédit d'impôt 48C(e), Taseko maintient une position financière solide avec 330 millions de dollars canadiens de liquidités, y compris une ligne de crédit renouvelable non utilisée de 110 millions de dollars américains.

Taseko Mines (NYSE American: TGB) hat ein Update zu seinem Florence Copper-Projekt in Arizona bereitgestellt. Zum 31. Dezember 2024 ist das Projekt zu 56 % abgeschlossen, und die erste Kupferproduktion ist vor Ende 2025 geplant. Die Bauaktivitäten liegen im Zeitplan, mit fast 450.000 geleisteten Projektstunden ohne Verletzungen oder Umweltauswirkungen. Der Standort beschäftigt derzeit etwa 290 Mitarbeiter.

Wesentliche Aktivitäten im 4. Quartal umfassen:

  • Abschluss der Bauarbeiten an den Prozess-Tümpeln und dem Oberflächenabfluss-Tümpel
  • Platzierung und Schweißen der Module für die Lösungsmittel-Extraktion und die Abläufe
  • Errichtung von 17 Produktionsbrunnen, insgesamt 51 von 90 geplanten Brunnen
  • Fortschritte bei der Entwicklung des Hauptleitungs-Korridors und Installation von Rohren aus hochdichtem Polyethylen
  • Beginn des Bauens von vor Ort errichteten Prozess- und Servicetanks
  • Mechanische und Rohrinstallationen in der SX/EW-Anlage
  • Nahezu abgeschlossene Montage des Stahlgerüsts für das Rohrgestell zur Lösungsmittel-Extraktion und laufende Rohrinstallation
  • Beginn der Elektroarbeiten
  • Errichtung des Gebäudes zur Wasseraufbereitung und Vorbereitung für das Gebäude zur Elektrowinning

Trotz der Ablehnung des Antrags auf einen Steuerkredit 48C(e) durch das Energieministerium hält Taseko eine starke Finanzlage mit 330 Millionen CAD an Liquidität, einschließlich einer ungenutzten revolvierenden Kreditlinie von 110 Millionen USD.

Positive
  • Project is 56% complete and on schedule.
  • Nearly 450,000 project hours worked without injuries or environmental incidents.
  • Strong financial position with C$330 million in available liquidity.
Negative
  • Application for the Department of Energy’s 48C(e) tax credit was declined.

Insights

The Florence Copper project's construction update reveals robust operational execution, with 56% completion and maintaining its timeline for first copper production by end-2025. The completion of critical infrastructure components - process ponds, surface water runoff ponds and significant progress in well construction (51 out of 90 planned wells) - demonstrates strong project management. The absence of reportable injuries across 450,000 project hours indicates excellent safety protocols.

The project's strategic significance lies in its positioning as the third-largest copper cathode producer in the USA, addressing critical domestic supply chain needs. However, the denial of the Department of Energy's 48C(e) tax credit represents a missed opportunity for tax benefits, though the company's C$330 million liquidity position, including an undrawn US$110 million credit facility, provides adequate financial buffer for project completion.

From a financial perspective, the maintenance of construction costs within guidance, coupled with substantial liquidity reserves, positions Taseko favorably to complete the Florence project without additional capital requirements. The C$330 million available liquidity provides a robust financial cushion against potential cost overruns or unexpected challenges.

While the rejection of the 48C(e) tax credit is a setback, the project's strategic timing coincides with growing US copper demand and increasing focus on domestic supply chains. This positions Taseko to potentially capture premium pricing in the domestic market, especially given its status as the only greenfield copper mine under construction in the USA. The project's progression towards production phase suggests potential positive impact on Taseko's revenue streams starting late 2025.

VANCOUVER, British Columbia, Jan. 14, 2025 (GLOBE NEWSWIRE) -- Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) ("Taseko" or the "Company") is pleased to update the progress at its 100%-owned Florence Copper project in Florence, Arizona.

As of December 31, 2024, the overall project completion was at 56% and first copper production continues to be targeted before the end of 2025. Construction activities are advancing on schedule and nearly 450,000 project hours have been worked with no reportable injuries or environmental incidents. Currently, there are approximately 290 construction and support personnel on site.

Summary of key activities in the fourth quarter:

  • Process ponds and surface water runoff pond construction completed
  • Solvent extraction settler and launder modules placed and welding of the modules was commenced
  • 17 production wells were fully constructed in the quarter, for a total of 51 wells out of 90 to be drilled during the construction phase
  • Development of the main pipe corridor (from wellfield to process plant) is mostly completed and installation of high density polyethylene piping in the corridor is ongoing
  • Field erected process and service tank construction commenced
  • Mechanical and piping installations are underway throughout the SX/EW plant
  • Erection of structural steel for the solvent extraction pipe rack is nearing completion and piping installation is underway
  • Electrical work commenced
  • Water treatment building was erected, and preparations made to start the electrowinning building erection

Stuart McDonald, President & CEO of Taseko, commented, “We are very pleased with the progress that has been made in the first 12 months of construction. The project remains on schedule, and construction costs remain in line with our previous guidance. We are now less than a year from anticipated first copper production and, in addition to construction activities, our site management team is focussed on operational readiness, key vendor agreements and recruiting.”

“With continued growth in US copper demand and an increasing focus on security of supply chains for critical materials, it is great timing to be bringing on a new source of domestic copper supply. Florence Copper is the only greenfield copper mine currently under construction in the USA and will soon become the third largest copper cathode producer in the country1.”

“We have recently been informed that our application for the Department of Energy’s 48C(e) tax credit has been declined. However, Taseko remains in a strong financial position with C$330 million of available liquidity at year-end, including the undrawn US$110 million revolving credit facility,” concluded Mr. McDonald.

Updated photos can be found on our website at https://tasekomines.com/properties/florence-copper/#construction-updates.

1Based on Wood Mackenzie data

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel; and
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.


FAQ

What is the current completion status of the Florence Copper project?

As of December 31, 2024, the Florence Copper project is 56% complete.

When is the first copper production expected from the Florence Copper project?

First copper production from the Florence Copper project is targeted before the end of 2025.

How many project hours have been worked on the Florence Copper project?

Nearly 450,000 project hours have been worked on the Florence Copper project.

How many production wells have been constructed in the Florence Copper project?

As of the fourth quarter, 51 out of 90 planned production wells have been constructed.

What financial position does Taseko Mines have?

Taseko Mines has C$330 million in available liquidity, including an undrawn US$110 million revolving credit facility.

Was Taseko's application for the Department of Energy’s 48C(e) tax credit approved?

No, Taseko's application for the Department of Energy’s 48C(e) tax credit was declined.

Taseko Mines Limited

NYSE:TGB

TGB Rankings

TGB Latest News

TGB Stock Data

561.72M
296.06M
2.55%
29.72%
0.49%
Copper
Basic Materials
Link
United States of America
Vancouver