Georgia Power files plan preparing for future energy landscape, building upon solid foundation to meet needs of customers and state

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Positive)
Tags
Rhea-AI Summary

Georgia Power has filed its 2022 Integrated Resource Plan (IRP) with the Georgia Public Service Commission, outlining a strategic roadmap for meeting future energy needs. The plan includes transitioning to cleaner resources, retiring outdated coal units, and doubling renewable capacity to 11,500 MW by 2035. Proposed investments focus on enhancing grid reliability, energy storage, and customer efficiency programs. The IRP aims to ensure affordable and reliable energy for its 2.7 million customers while embracing new technologies for a sustainable energy landscape.

Positive
  • Proposed retirement of 12 coal units, totaling over 3,500 MW, by 2028, enhancing economic viability.
  • Doubling renewable capacity to 11,500 MW by 2035, promoting cleaner energy.
  • Investment in 1,000 MW energy storage by 2030, improving grid resilience.
  • Expanded customer programs to boost energy efficiency and reliability.
Negative
  • Retirement of coal units may face regulatory and operational challenges.
  • Transitioning to new energy sources could incur high upfront costs.

ATLANTA, Jan. 31, 2022 /PRNewswire/ -- Today, Georgia Power filed its 2022 Integrated Resource Plan (IRP) which sets forth a proactive, innovative and transformational roadmap for how the company will continue to meet the energy needs of customers, local communities and the State of Georgia for future generations.

Filed with the Georgia Public Service Commission (PSC), the 2022 IRP outlines Georgia Power's plan to thoughtfully transition its fleet to more economical, cleaner resources; invest in its transmission system to make it smarter and even more reliable and resilient; double its renewable and solar capacity; focus on energy storage solutions; and offer innovative energy efficiency programs for customers.

"At Georgia Power, we know that to continue to meet the changing needs of our customers we must prepare now to build the electric system and energy infrastructure of the future," said Chris Womack, chairman, president and CEO of Georgia Power. "We believe this IRP outlines how we will do that and how, working with the Georgia Public Service Commission, we will build upon the solid foundation we already have as the energy landscape continues to evolve. It demonstrates our commitment to making smart investments today, so that our customers can continue to have clean, safe, reliable and affordable energy for decades to come." 

The company files an IRP with the Georgia PSC every three years to outline how it will continue delivering clean, safe, reliable and affordable energy to its 2.7 million customers over the next 20 years. As part of today's filing, Georgia Power is proposing a comprehensive strategy to both transform Georgia's energy sources and help to ensure that the state's network of transmission lines and grid infrastructure continues to deliver reliable energy to Georgians – both today and in the future.

Transforming Georgia's Energy Sources, Growing Renewable Energy 
As coal-fired generation continues to be less economically viable, the company is proposing to retire and decertify all Georgia Power-controlled coal units, with the exception of Plant Bowen Units 3 & 4, which will continue to operate no later than 2035. The company's plan includes retirement of a total of 12 generating units, or more than 3,500 megawatts (MW), by 2028 and, if approved, would begin later this year and continue through 2028. To facilitate this fleet transformation, Georgia Power is proposing to certify an additional 2,356 megawatts (MW) of capacity from natural gas power purchase agreements (PPAs), procured through the company's 2022-2028 Capacity Request for Proposals (RFP) as well as significantly increase its renewable capacity.

The company is also planning to double its renewable generation by adding 6,000 MW by 2035, which includes a request for approval of 2,300 MW* in this IRP. The new capacity would expand the company's renewable resource portfolio to approximately 11,500 MW by 2035 as well as support the transition to cleaner, more cost-effective energy resources for customers. 

Additionally, as the energy resource mix continues to evolve and the presence of intermittent renewable resources grows, the company is:

  • Requesting approval to own and operate 1,000 MW of energy storage by 2030, which includes a specific request for approval to own and operate the 265-MW McGrau Ford Battery Facility.
  • Proposing to continue to invest in its hydro plants, including Plants Burton, North Highlands and Sinclair, to improve efficiencies in hydro system operations and help to ensure these units continue to provide clean and dispatchable carbon-free energy for another 40 years.

Investments in Reliability, Resilience
Georgia Power is continuously investing in the power grid to make it smarter and more reliable. The 2022 IRP outlines additional investments and plans to continue to enhance the reliability and resilience of the state's electrical grid system, including a multi-faceted approach developed to address future reliability needs associated with the retirement of coal units. The company is calling for an integrated solution comprised of new generation and transmission assets aimed at meeting the long-term needs of the state.

"Providing customers with reliable service is at the center of our business and as we continue to transition our fleet and grow renewable energy that focus remains true. Looking to Georgia's future growth and energy needs, we know that new and emerging technologies have the potential to fundamentally alter the way energy is created, transported and ultimately consumed. That's why a critical component of our fleet and grid transformation plan involves leveraging new technologies," added Womack.

For the 2022 IRP, the company has identified long-duration storage, hydrogen, tall wind technologies and distributed energy resources as areas of potential investment.

Diverse, Flexible Customer Programs 
In addition to investments in its transmission and generation systems and assets, the company also recognizes how important demand-side resources, such as energy efficiency programs and demand response programs, are to Georgia Power's resource mix. They benefit customers and support system reliability by reducing energy use and managing demand during severe weather events. Consistent with prior IRPs, the 2022 IRP offers a robust portfolio of these programs designed to provide significant value for all customers, including those facing income challenges. New programs proposed in this IRP include:

  • Distributed Energy Resource (DER) Customer Program – This program enables participating customers to receive a resiliency service via a company-owned, operated and maintained DER. Participating customers could elect to receive a credit in exchange for the company's ability to access the DER for the benefit of all customers during a system reliability event. If approved, it would provide system reliability benefits for all customers while supporting commercial and industrial customers with enhanced resiliency needs.
  • Income-Qualified Community Solar Pilot – If approved, this program will provide income-qualified customers access to Community Solar generated energy at discounted prices.  The discount will be made available by participating corporate sponsors who will receive corresponding Renewable Energy Certificates (RECs). 

Additionally, the company is requesting to continue the Home Energy Efficiency Assistance Program (HEEAP) and its current program in connection with HopeWorks as well as extend the Residential Investment for Saving Energy (RISE) Pilot, which promotes energy efficiency improvements in qualifying existing, income-qualified single-family homes and a limited number of multifamily properties

Integrated Resource Plan Process
Today's filing initiates a series of additional filings and public hearings with the Georgia PSC. At the conclusion of this open and transparent process, the Georgia PSC is expected to vote on the company's IRP request this summer. The 2022 IRP is a result of detailed analysis, which includes projections of future fuel costs, peak load and energy forecasts, an analysis of available generation technologies, a 10-year transmission plan, a comprehensive environmental strategy, and an economic assessment of potential and proposed energy efficiency and demand response programs. The company also evaluates the cost-effectiveness of its generating resources given changing environmental regulations and emerging technologies and how to best add resilience to the electric system.

To learn more about how Georgia Power is meeting the needs of customers through a diverse, balanced energy portfolio, visit www.GeorgiaPower.com.

* REC Disclaimer: Georgia Power purchases only the null energy output from some renewable generating facilities that have contracted to sell that energy to Georgia Power. Ownership of the associated renewable energy credits (RECs) is specified in each respective power purchase agreement. The party that owns the RECs retains the right to use them.

About Georgia Power
Georgia Power is the largest electric subsidiary of Southern Company (NYSE: SO), America's premier energy company. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company's promise to 2.7 million customers in all but four of Georgia's 159 counties. Committed to delivering clean, safe, reliable and affordable energy at rates below the national average, Georgia Power maintains a diverse, innovative generation mix that includes nuclear, coal and natural gas, as well as renewables such as solar, hydroelectric and wind. Georgia Power focuses on delivering world-class service to its customers every day and the company is recognized by J.D. Power as an industry leader in customer satisfaction. For more information, visit www.GeorgiaPower.com and connect with the company on Facebook (Facebook.com/Georgia Power), Twitter (Twitter.com/GeorgiaPower) and Instagram (Instagram.com/ga_power).

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/georgia-power-files-plan-preparing-for-future-energy-landscape-building-upon-solid-foundation-to-meet-needs-of-customers-and-state-301471866.html

SOURCE Georgia Power

FAQ

What is Georgia Power's 2022 Integrated Resource Plan (IRP)?

Georgia Power's 2022 IRP is a strategic roadmap filed with the Georgia Public Service Commission, detailing plans to transition to cleaner energy, enhance grid reliability, and double renewable capacity by 2035.

How much renewable energy will Georgia Power add by 2035?

Georgia Power plans to double its renewable generation capacity to approximately 11,500 MW by 2035.

What is Georgia Power's plan for coal unit retirements?

The plan includes retiring 12 coal units, exceeding 3,500 MW of capacity, by 2028, with the goal of transitioning to more economical and cleaner energy sources.

What investments are planned for improving energy storage?

Georgia Power is requesting approval to own and operate 1,000 MW of energy storage by 2030, including the 265-MW McGrau Ford Battery Facility.

When will the Georgia Public Service Commission vote on the IRP?

The Georgia Public Service Commission is expected to vote on Georgia Power's IRP request in the summer following the public hearings.

The Southern Company

NYSE:SO

SO Rankings

SO Latest News

SO Stock Data

96.76B
1.09B
0.16%
70.71%
1.68%
Utilities - Regulated Electric
Electric Services
Link
United States of America
ATLANTA