Advancing the Great Atlantic Salt Project: Atlas Salt's Approach to EA Conditions and Permitting
Atlas Salt (TSXV:SALT)(OTCQB:REMRF) has outlined its strategy for meeting Environmental Assessment (EA) conditions and phased permitting for the Great Atlantic Salt Project. The project was released from environmental assessment in 52 days, with 70-80% of conditions proactively addressed in the initial registration. The company's phased approach includes: Early Works for site preparation, Capital Development for surface and underground infrastructure, and Commercial Operations Development. Key environmental focuses include real-time water monitoring, seasonal wildlife benchmarking, community engagement, climate adaptation, and progressive rehabilitation.
Atlas Salt (TSXV:SALT)(OTCQB:REMRF) ha delineato la sua strategia per soddisfare le condizioni di Valutazione Ambientale (VA) e il rilascio dei permessi per fasi per il Grande Progetto di Sale Atlantico. Il progetto è stato rilasciato dalla valutazione ambientale in 52 giorni, con il 70-80% delle condizioni affrontate proattivamente nella registrazione iniziale. L'approccio per fasi dell'azienda include: Lavori Preliminari per la preparazione del sito, Sviluppo del Capitale per infrastrutture di superficie e sotterranee, e Sviluppo delle Operazioni Commerciali. Focus ambientali chiave includono monitoraggio dell'acqua in tempo reale, benchmarking della fauna selvatica stagionale, coinvolgimento della comunità, adattamento ai cambiamenti climatici e riabilitazione progressiva.
Atlas Salt (TSXV:SALT)(OTCQB:REMRF) ha delineado su estrategia para cumplir con las condiciones de Evaluación Ambiental (EA) y la obtención de permisos por fases para el Gran Proyecto de Sal Atlántico. El proyecto fue liberado de la evaluación ambiental en 52 días, con el 70-80% de las condiciones abordadas proactivamente en el registro inicial. El enfoque por fases de la empresa incluye: Obras Preliminares para la preparación del sitio, Desarrollo de Capital para infraestructura superficial y subterránea, y Desarrollo de Operaciones Comerciales. Enfoques ambientales clave incluyen monitoreo del agua en tiempo real, evaluación estacional de la fauna, participación comunitaria, adaptación climática y rehabilitación progresiva.
아틀라스 솔트 (TSXV:SALT)(OTCQB:REMRF)는 대서양 소금 프로젝트에 대한 환경 평가(EA) 조건 충족과 단계별 허가 방안을 세웠습니다. 이 프로젝트는 52일 만에 환경 평가에서 해제되었으며, 초기 등록에서 70-80%의 조건이 적극적으로 해결되었습니다. 회사의 단계적 접근은: 부지 준비를 위한 초기 작업, 표면 및 지하 인프라를 위한 자본 개발, 상업 운영 개발을 포함합니다. 주요 환경 중점 사항에는 실시간 수질 모니터링, 계절별 야생동물 기준 설정, 지역 사회 참여, 기후 적응 및 점진적 재활 등이 포함됩니다.
Atlas Salt (TSXV:SALT)(OTCQB:REMRF) a défini sa stratégie pour répondre aux conditions d'Évaluation Environnementale (EE) et aux permis phasés pour le Grand Projet de Sel Atlantique. Le projet a été libéré de l'évaluation environnementale en 52 jours, avec 70-80 % des conditions traitées proactivement dans l'enregistrement initial. L'approche par phases de l'entreprise comprend : travaux préliminaires pour la préparation du site, développement des infrastructures de surface et souterraines, et développement des opérations commerciales. Les principaux objectifs environnementaux incluent la surveillance de l'eau en temps réel, l'évaluation saisonnière de la faune, l'engagement communautaire, l'adaptation au changement climatique et la réhabilitation progressive.
Atlas Salt (TSXV:SALT)(OTCQB:REMRF) hat seine Strategie zur Erfüllung der Bedingungen der Umweltbewertung (EA) und zur phasenweisen Genehmigung des Großen Atlantischen Salzugprojekts skizziert. Das Projekt wurde nach 52 Tagen von der Umweltbewertung befreit, wobei 70-80% der Bedingungen proaktiv in der ursprünglichen Anmeldung angesprochen wurden. Der phasenweise Ansatz des Unternehmens umfasst: Vorarbeiten zur Standortvorbereitung, Kapitalentwicklung für Oberflächen- und Untergrundinfrastruktur sowie Entwicklung kommerzieller Operationen. Wichtige Umweltfoki sind Echtzeit-Wasserüberwachung, saisonale Wildtierbenchmarking, Gemeindebeteiligung, Klimaanpassung und progressive Rekultivierung.
- Project received quick environmental assessment approval in 52 days
- 70-80% of environmental conditions were proactively addressed in initial registration
- Structured phased development approach demonstrates clear path to commercialization
- None.
Advancing the Great Atlantic Salt Project: Atlas Salt's Approach to EA Conditions and Permitting
ST. JOHN'S, NL / ACCESSWIRE / November 4, 2024 / Atlas Salt Inc. ("Atlas Salt" or the "Company") (TSXV:SALT)(OTCQB:REMRF) is pleased to share its approach to meeting Environmental Assessment (EA) conditions and to outline its phased permitting strategy for the Great Atlantic Salt Project. This strategy reflects Atlas Salt's commitment to advancing the project responsibly, laying the groundwork for Canada's next major salt mine through strong environmental stewardship and regulatory alignment at each development stage.
Understanding EA Conditions and Atlas Salt's Proactive Approach
EA conditions are a standard requirement for large-scale mining projects, designed to balance development with environmental protections. Atlas Salt's Great Atlantic Salt Project was released from the environmental assessment process with a moderate level of conditions, approximately 70
EA Conditions Fully Integrated into Project Development Plans
Atlas Salt has incorporated all EA conditions stipulated by the Department of Environment and Climate Change into the Company's project plans. Activities and tasks required to meet these conditions were closely developed and refined in consultation with regulatory bodies to align with government expectations and standards.
Phased Permitting Strategy to Support Development Progression
Atlas Salt is implementing a phased approach to permitting, with each phase designed to advance the Project while meeting specific regulatory requirements and environmental standards:
Early Works - This phase encompasses surface-level site preparations and infrastructure setup, including land clearing, access road construction, and installation of environmental controls. The Early Works Mine Development Plan, currently under development, will ensure that Atlas Salt adheres to stringent environmental standards as foundational construction activities commence.
Capital Development Following the Early Works, the Capital Development phase focuses on both surface and underground development necessary for operational readiness. Key activities include constructing the box cut, main decline, and underground infrastructure. This phase will incorporate detailed environmental management practices, including specific measures related to sub-surface construction and continuous monitoring to ensure compliance with environmental requirements.
Commercial Operations Development - The final phase, will be scaling the mine to commercial production, including full operational readiness and ongoing environmental monitoring.
Commitment to Responsible Development and Transparent Engagement
Atlas Salt is dedicated to best practices in responsible mining. The EA conditions not only meet regulatory expectations but also support Atlas Salt's values in environmental and social responsibility. By embedding EA requirements into the project from its inception, Atlas Salt emphasizes its commitment to advancing the Great Atlantic Salt Project responsibly, underscoring the Company's goal to balance environmental sustainability with market growth.
The Company maintains regular communication with the Department of Environment and Climate Change and other regulatory bodies, providing updates on compliance and project status. Atlas Salt also continues active engagement with Indigenous groups, community stakeholders, and local governments, ensuring consistent updates and addressing inquiries throughout each development phase.
CEO Richard LaBelle stated, "The Great Atlantic Salt Project's phased permitting approach, coupled with proactive integration of EA conditions, demonstrates our commitment to responsible development. We are advancing this project with a focus on environmental integrity and community partnership, positioning ourselves to become a leading long-life, low-Greenhouse Gas (GHG) salt producer in the North American market."
For further information and ongoing updates, please visit https://atlassalt.com.
About Atlas Salt Inc.
Atlas Salt Inc. is developing Canada's next salt mine and is committed to responsible and sustainable mining practices. With a focus on innovation and efficiency, the company is poised to make significant contributions to the North American salt market while upholding its values of environmental stewardship and community engagement.
For information, please contact:
Richard LaBelle, CEO
investors@atlassalt.com
(709) 739-9545
We seek safe harbor.
Cautionary Statement
Neither the TSX Venture Exchange nor its Regulation Services Provider, (as the term is defined in the Policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This press release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation, statements relating to the future operating or financial performance of the Company, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible", and similar expressions, or statements that events, conditions, or results "will", "may", "could", or "should" occur or be achieved. Forward-looking statements in this press release relate to, among other things: obtaining financing, completion, delivery and timing of project components and requirements, and analysis and assumptions related thereto. Actual future results may differ materially. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by the respective parties, are inherently subject to significant business, technical, economic, and competitive uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements and the parties have made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: the timing, completion and delivery of required permits, supply arrangements and financing. Readers should not place undue reliance on the forward-looking statements and information contained in this news release concerning these times. Except as required by law, the Company does not assume any obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change.
SOURCE: Atlas Salt
View the original press release on accesswire.com