Atlas Salt Submits Early Works Development Plan for Great Atlantic Salt Project
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF) has submitted its Early Works Development Plan for the Great Atlantic Salt Project in Newfoundland and Labrador to the Department of Industry, Energy and Technology. The plan outlines site preparation and early-stage infrastructure development ahead of full-scale mine construction.
The key components include:
- Construction of a 1.3 km primary access road and 300m secondary access route
- Site preparation activities including clearing, grubbing, and stockpile pad grading
- Development of laydown areas and temporary construction facilities
- Implementation of environmental controls including stormwater management systems
Pending governmental approval, Early Works construction is scheduled to begin in 2025. The company aims to position itself as a leading low-cost producer in the North American salt market through this development.
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF) ha presentato il suo Piano di Sviluppo per i Lavori Preliminari del Progetto Great Atlantic Salt nel Newfoundland e Labrador al Dipartimento dell'Industria, dell'Energia e della Tecnologia. Il piano delinea la preparazione del sito e lo sviluppo delle infrastrutture nelle fasi iniziali prima della costruzione della miniera su larga scala.
I componenti chiave includono:
- Costruzione di una strada di accesso primaria di 1,3 km e di un percorso secondario di 300 m
- Attività di preparazione del sito, tra cui disboscamento, rimozione della vegetazione e livellamento delle aree di stoccaggio
- Sviluppo di aree di deposito e strutture temporanee per la costruzione
- Implementazione di controlli ambientali, inclusi sistemi di gestione delle acque piovane
In attesa dell'approvazione governativa, la costruzione dei Lavori Preliminari è programmata per iniziare nel 2025. L'azienda mira a posizionarsi come un produttore leader a basso costo nel mercato del sale nordamericano attraverso questo sviluppo.
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF) ha presentado su Plan de Desarrollo de Obras Iniciales para el Proyecto Great Atlantic Salt en Newfoundland y Labrador al Departamento de Industria, Energía y Tecnología. El plan describe la preparación del sitio y el desarrollo de infraestructura en las primeras etapas antes de la construcción a gran escala de la mina.
Los componentes clave incluyen:
- Construcción de un camino de acceso primario de 1,3 km y una ruta de acceso secundaria de 300 m
- Actividades de preparación del sitio que incluyen desmonte, limpieza y nivelación de áreas de acopio
- Desarrollo de áreas de almacenamiento y instalaciones temporales de construcción
- Implementación de controles ambientales, incluidos sistemas de gestión de aguas pluviales
Con la aprobación gubernamental pendiente, se prevé que la construcción de las Obras Iniciales comience en 2025. La empresa tiene como objetivo posicionarse como un productor líder de bajo costo en el mercado de sal de América del Norte a través de este desarrollo.
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF)는 뉴펀들랜드와 래브라도에 위치한 그레이트 아틀란틱 솔트 프로젝트를 위한 초기 작업 개발 계획을 산업, 에너지 및 기술부에 제출했습니다. 이 계획은 대규모 광산 건설 이전의 부지 준비 및 초기 단계 인프라 개발을 설명합니다.
주요 구성 요소는 다음과 같습니다:
- 1.3km의 주요 접근 도로 및 300m의 보조 접근 경로 건설
- 정리, 풀베기 및 재고 패드 평탄화와 같은 부지 준비 활동
- 임시 건설 시설 및 적치장 개발
- 우수 관리 시스템을 포함한 환경 관리의 구현
정부의 승인이 대기 중이며, 초기 작업 건설은 2025년에 시작될 예정입니다. 이 회사는 이 개발을 통해 북미 소금 시장에서 저비용 생산자로 자리매김하는 것을 목표로 하고 있습니다.
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF) a soumis son Plan de Développement des Travaux Préliminaires pour le Projet Great Atlantic Salt à Terre-Neuve et Labrador au Ministère de l'Industrie, de l'Énergie et de la Technologie. Le plan décrit la préparation du site et le développement d'infrastructures à un stade précoce avant la construction de la mine à grande échelle.
Les principaux éléments comprennent:
- Construction d'une route d'accès principale de 1,3 km et d'un chemin d'accès secondaire de 300 m
- Activités de préparation du site, y compris le défrichement, le déblayage et le nivellement des zones de stockage
- Développement de zones de stockage et d'installations temporaires de construction
- Mise en œuvre de contrôles environnementaux, y compris des systèmes de gestion des eaux pluviales
En attente de l'approbation gouvernementale, la construction des Travaux Préliminaires est prévue pour commencer en 2025. L'entreprise vise à se positionner comme un producteur leader à faible coût sur le marché du sel nord-américain grâce à ce développement.
Atlas Salt Inc. (TSXV:SALT)(OTCQB:REMRF) hat seinen frühen Entwicklungsplan für das Great Atlantic Salt Projekt in Neufundland und Labrador beim Ministerium für Industrie, Energie und Technologie eingereicht. Der Plan beschreibt die Standortvorbereitung und die Entwicklung der Infrastruktur in der frühen Phase vor dem Bau der Großmine.
Die wichtigsten Komponenten umfassen:
- Bau einer 1,3 km langen Hauptzugangsstraße und einer 300 m langen Nebenstraße
- Standortvorbereitungsaktivitäten, einschließlich Rodung, Abholzung und Nivellierung von Lagerflächen
- Entwicklung von Ablageflächen und temporären Bauanlagen
- Implementierung von Umweltkontrollen, einschließlich Regenwassermanagementsystemen
Nach Genehmigung durch die Regierung ist der Baubeginn der frühen Arbeiten für 2025 geplant. Das Unternehmen strebt an, sich durch diese Entwicklung als führender Anbieter mit niedrigen Kosten auf dem nordamerikanischen Salzmarkt zu positionieren.
- Project development milestone achieved with Early Works Plan submission
- Strategic positioning as potential low-cost salt producer in North America
- Phased approach helps de-risk project development
- Construction start still pending governmental approval
- Additional capital expenditure required for infrastructure development
ST. JOHN'S, NEWFOUNDLAND AND LABRADOR / ACCESS Newswire / March 3, 2025 / Atlas Salt Inc. ("Atlas Salt" or the "Company") (TSXV:SALT)(OTCQB:REMRF) is pleased to announce the formal submission of the Early Works Mine Development and Rehabilitation and Closure Plan (the "Early Works Development Plan") to the Department of Industry, Energy and Technology for the Government of Newfoundland and Labrador, for the Great Atlantic Salt Project (the "Project") in Newfoundland and Labrador, Canada.
The submission of the Early Works Development Plan marks a critical milestone in advancing the Project toward construction. This plan outlines the phased approach for site preparation and early-stage infrastructure development, ensuring regulatory compliance while de-risking key project components ahead of full-scale mine construction.
Key Components of the Early Works Development Plan
Site Preparation: Clearing and grubbing activities, stockpile pad grading, and initial earthworks to establish the mine site footprint.
Primary and Secondary Access Roads: Construction of a 1.3 km primary access road from Steel Mountain Road and a 300 m secondary access route along the planned conveyor corridor.
Surface Infrastructure: Development of laydown areas, temporary construction facilities, and essential utilities to support subsequent project phases.
Sediment and Erosion Control Measures: Implementation of stormwater management systems, catchment ditches, and a temporary settling basin to mitigate environmental impacts.
Regulatory Compliance and Permitting: Submission of required approvals for road access, site disturbance, and water management infrastructure, ensuring alignment with provincial environmental guidelines.
The Early Works Development Plan enables Atlas Salt to initiate critical site activities ahead of full project execution, accelerating timelines for major construction phases. By proactively addressing key infrastructure and environmental management requirements, the Company aims to optimize the transition into mine development while maintaining a rigorous approach to regulatory compliance.
Richard LaBelle, CEO of Atlas Salt, commented: "The submission of the Early Works Development Plan represents another significant step in de-risking the Great Atlantic Salt Project and positioning Atlas Salt as a leading low-cost producer in the North American salt market. This milestone ensures we remain on track for the timely development of critical project infrastructure, paving the way for commercial production."
Pending governmental review and approval, Early Works construction is expected to commence in 2025, with subsequent phases progressing in alignment with the overall project schedule.
For further information and ongoing updates, please visit https://atlassalt.com.
About Atlas Salt Inc.
Atlas Salt Inc. is developing Canada's next salt mine and is committed to responsible and sustainable mining practices. With a focus on innovation and efficiency, the company is poised to make significant contributions to the North American salt market while upholding its values of environmental stewardship and community engagement.
For information, please contact:
Richard LaBelle, CEO
investors@atlassalt.com
(709) 739-9545
We seek safe harbor.
Cautionary Statement
Neither the TSX Venture Exchange nor its Regulation Services Provider, (as the term is defined in the Policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This press release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation, statements relating to the future operating or financial performance of the Company, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible", and similar expressions, or statements that events, conditions, or results "will", "may", "could", or "should" occur or be achieved. Forward-looking statements in this press release relate to, among other things: obtaining financing, completion, delivery and timing of project components and requirements, and analysis and assumptions related thereto. Actual future results may differ materially. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by the respective parties, are inherently subject to significant business, technical, economic, and competitive uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements and the parties have made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: the timing, completion and delivery of required permits, supply arrangements and financing. Readers should not place undue reliance on the forward-looking statements and information contained in this news release concerning these times. Except as required by law, the Company does not assume any obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change, except as required by law.
SOURCE: Atlas Salt Inc.
View the original press release on ACCESS Newswire