STOCK TITAN

California Governor Signs Legislation Seeking to Extend Diablo Canyon Power Plant Operations to Support Statewide Grid Reliability

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Very Positive)
Tags
Rhea-AI Summary

California Governor Gavin Newsom signed Senate Bill 846, allowing Diablo Canyon Power Plant (DCPP) to extend operations five years beyond its 2025 license expiration. This extension aims to enhance energy reliability and decrease greenhouse gas emissions as new renewable resources come online. PG&E will seek necessary NRC approvals and a state-authorized loan of up to $1.4 billion to support the operation. Currently, DCPP generates 2,200 megawatts, providing about 17% of California's zero-carbon electricity supply.

Positive
  • Extension of DCPP operations could improve energy reliability and support California's clean energy goals.
  • Loan up to $1.4 billion authorized to help extend DCPP operations and lower customer costs.
Negative
  • None.

Plant Would Serve as a Reliable, Low-Cost, Carbon-Free Bridge While State Brings New Renewable Resources Online

PG&E is Committed to the Highest Levels of Safety, Performance and Security at DCPP

OAKLAND, Calif.--(BUSINESS WIRE)-- Following approval by the California State Legislature, Governor Gavin Newsom today signed Senate Bill 846 into law, seeking to extend operations at Diablo Canyon Power Plant (DCPP) in San Luis Obispo County for five years beyond its current license expiration in 2025. The plant, owned and operated by Pacific Gas and Electric Company (PG&E), would be used to improve statewide energy system reliability and reduce greenhouse gas emissions while additional renewable energy and carbon-free resources come online.

PG&E must now obtain the necessary U.S. Nuclear Regulatory Commission (NRC) licenses, as well as other required state regulatory approvals. The law directs all relevant state agencies and PG&E as the plant operator to act quickly and coordinate on the necessary and prudent actions to extend plant operations.

The state will authorize a loan of up to $1.4 billion to PG&E to support extending operations at the plant. The bill directs PG&E to take steps to secure funds from the U.S Department of Energy (DOE), and any other potentially available federal funding, which would be used to pay back the loan and lower costs for customers. PG&E has filed an application for federal funding through the DOE’s Civil Nuclear Credit program.

“PG&E is committed to California’s clean energy future. As a regulated utility, we follow the energy policies of the state. We are proud of the role Diablo Canyon plays in providing safe, reliable, low-cost and carbon-free energy to our customers and Californians. We will do our part to help the state achieve its energy reliability and decarbonization goals, while continuing to run one of the top performing plants in the country. The team of people at Diablo Canyon delivers for our hometowns every day through their industry-leading commitment to safe operations,” said PG&E Corporation CEO Patti Poppe.

DCPP can generate 2,200 megawatts of baseline electricity, and currently provides approximately 17% of California’s zero-carbon electricity supply and 8.6% of the state’s total electricity supply.

PG&E is committed to the highest levels of safety, performance and security at DCPP. The plant has an excellent safe operating record and is subject to rigorous regulatory oversight, including with respect to seismic safety. To learn more, click here. The NRC’s current assessment places DCPP among the highest performing plants in the nation. All plant operations will continue to be overseen and monitored by the NRC, as well as several other independent industry and external oversight entities.

About PG&E

Pacific Gas and Electric Company, a subsidiary of PG&E Corporation (NYSE:PCG), is a combined natural gas and electric utility serving more than 16 million people across 70,000 square miles in Northern and Central California. For more information, visit www.pge.com/ and http://www.pge.com/about/newsroom/.

MEDIA RELATIONS:

415-973-5930

Source: Pacific Gas and Electric Company

FAQ

What is Senate Bill 846 regarding PG&E and Diablo Canyon?

Senate Bill 846 allows Diablo Canyon Power Plant to operate for five additional years beyond its 2025 license expiration.

How much electricity does Diablo Canyon generate for California?

Diablo Canyon generates 2,200 megawatts, supplying about 17% of California's zero-carbon electricity.

What financial support is PG&E receiving for Diablo Canyon operations?

PG&E is authorized to secure up to $1.4 billion from the state to support extended operations at Diablo Canyon.

What steps must PG&E take following the signing of Senate Bill 846?

PG&E must obtain licenses from the U.S. Nuclear Regulatory Commission and other state regulatory approvals.

What is the significance of Diablo Canyon Power Plant for California's energy supply?

DCPP plays a critical role in providing safe, reliable, low-cost, and carbon-free energy to California.

PG&E Corporation

NYSE:PCG

PCG Rankings

PCG Latest News

PCG Stock Data

55.17B
2.54B
2.73%
78.2%
1.3%
Utilities - Regulated Electric
Electric & Other Services Combined
Link
United States of America
OAKLAND