NextDecade Provides First Quarter 2024 Business Update
NextDecade provided an update on the first quarter 2024 and early second quarter 2024 activities, focusing on the progress of Phase 1 construction at the Rio Grande LNG Facility. The Company is on track with construction plans, expects to achieve a positive FID on Train 4 in the second half of the year, and is engaging in commercial discussions with potential counterparties. Financially, NextDecade secured a $50 million revolving credit facility and issued $190 million in senior secured notes to support Phase 1 development. The Company aims to become a leading LNG owner and operator while maximizing value for shareholders.
Construction progress of Phase 1 at the Rio Grande LNG Facility is advancing according to plan, with key milestones being achieved in line with the schedule under the EPC contract.
NextDecade expects a positive FID on Train 4 in the second half of 2024, with TotalEnergies likely to purchase 1.5 million tonnes per annum of LNG from Train 4.
Financially, the Company secured a $50 million revolving credit facility and issued $190 million in senior secured notes to support Phase 1 development at the Rio Grande LNG Facility.
While progress on Phase 1 construction is on track, any delays or complications in the construction process could impact the Company's timelines and financial performance.
The Company's reliance on debt and equity funding for Train 4 construction poses potential financial risks, especially if commercial arrangements and financing are not secured as planned.
CEO Commentary
“Construction of Phase 1 at the Rio Grande LNG Facility continues to progress according to plan, as we work alongside Bechtel to construct Trains 1 through 3 and their supporting infrastructure safely, efficiently, on schedule, and within budget,” said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. “The Rio Grande LNG Facility has truly begun to take shape recently, as concrete foundation pours for Train 1 are ongoing, key materials such as piping and structural steel have been delivered to the site, and shoreline work and levee construction are underway. Proactive project and risk management remain key priorities as construction of Phase 1 continues to progress.”
“We are currently at a unique point in the Company’s history as we develop and expect to FID highly attractive expansion capacity this year and next year, while safely constructing Phase 1 capacity, and preparing our organization to achieve our long-term objective of becoming a leading LNG owner and operator. We are confident that delivering on our plans will create long-term value for our stakeholders.”
“We are focused on achieving a positive FID on Train 4 in the second half of this year. We expect TotalEnergies to exercise its option to purchase 1.5 million tonnes per annum of LNG from Train 4, and commercial discussions are progressing well with numerous additional counterparties for the remainder of the LNG necessary to support a positive FID on Train 4 this year. Additionally, we are continuing to work with Bechtel on the EPC contracting process, which we expect will enable us to finalize the EPC contract for Train 4 by the end of the second quarter of 2024. We are determined to capitalize on the robust market opportunity to unlock the value of our fully permitted, brownfield expansion capacity, and we are strongly committed to do so in a way that maximizes value to our shareholders.”
Significant Recent Developments
Construction
Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of March 2024:
-
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was
18.2% , which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was54.9% complete, procurement was34.4% complete, and construction was1.9% complete. -
The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was
6.9% , based on preliminary schedules, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was5.2% complete, procurement was16.7% complete, and construction was0.0% complete.
Financial
-
In January 2024, the Company's wholly-owned subsidiary NextDecade LNG, LLC entered into a credit agreement that provides for a
senior secured revolving credit facility with additional capacity of$50 million to cover interest. Borrowings under the revolving credit facility may be used for general corporate purposes, including development costs related to Train 4 at the Rio Grande LNG Facility. Borrowings bear interest at SOFR or the base rate plus an applicable margin as defined in the credit agreement. The revolving credit facility and interest term loan mature at the earlier of two years from the closing date or 10 business days after a positive FID of Train 4.$12.5 million -
In February 2024, Rio Grande LNG, LLC (Rio Grande) issued and sold
of senior secured notes in a private placement transaction to finance a portion of Phase 1. The senior secured notes were issued on February 9, 2024 and resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured notes will be amortized over a period of approximately 18 years beginning in mid-2029, with a final maturity in June 2047. The senior secured notes bear interest at a fixed rate of$190 million 6.85% and rank pari passu to Rio Grande's existing senior secured financings.
Rio Grande LNG Facility
NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south
Phase 1 (Trains 1-3)
Phase 1 at the Rio Grande LNG Facility is under construction. Phase 1 includes three liquefaction trains with a total nameplate capacity of 17.61 MTPA of LNG production, two 180,000 cubic meter full containment LNG storage tanks, and two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity. Phase 1 also includes associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the entire site, and warehouses, administrative, operations control room, and maintenance buildings.
As of March 2024, progress on Trains 1 through 3 is in line with the schedule under the EPC Contracts. The civil works program has continued to progress via the deep soil mixing program, as Train 1 deep soil mixing is approaching completion and rigs are preparing to move to Train 2 for production and Train 3 for testing. Concrete foundation pours for Train 1 are underway. Delivery of key materials to site has begun, including large bore above-ground pipe and structural steel. Additionally, LNG tank piling has progressed significantly, berth 1 piling work commenced, and levee construction continues.
Bechtel has made meaningful progress on procurement for Phase 1, with a focus on completing purchase orders for critical and high-value items early in the construction process. As of March 2024, Bechtel has issued approximately
NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to
Final Investment Decision on Train 4 and Train 5
NextDecade is targeting a positive FID and the issuance of a full notice to proceed (NTP) to Bechtel for Train 4 and its related infrastructure at the Rio Grande LNG Facility in the second half of 2024. Achieving a positive FID on Trains 4 and 5, the fully permitted expansion capacity at the Rio Grande LNG Facility will be subject to, among other things, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.
The Company has undertaken certain pre-FID activities for Train 4, including the FEED and EPC contract processes with Bechtel, which the Company expects will enable the finalization of the EPC contract for Train 4 by the end of the second quarter of 2024.
The Company continues to advance commercial discussions with multiple potential counterparties and expects to finalize commercial arrangements for Train 4 in the coming months to support an FID on Train 4 in the second half of 2024.
The Company expects to finance construction of Train 4 utilizing a combination of debt and equity funding. The Company expects to enter into bank facilities for the debt portion of the funding. In connection with consummating the Rio Grande Phase 1 equity joint venture, the Company's equity partners each have options to invest in Train 4 equity, which, if exercised, would provide approximately
The Company expects to begin the EPC contracting process for Train 5 after a positive FID on Train 4. TotalEnergies also holds an LNG purchase option for 1.5 MTPA for Train 5, and the Rio Grande Phase 1 equity partners have options to invest in Train 5 equity which are materially equivalent to their options to participate in Train 4 equity.
Investor Presentation
NextDecade has posted an updated investor presentation to its website concurrently with this release. A copy of this release and the investor presentation can be found on its website at www.next-decade.com.
About NextDecade Corporation
NextDecade Corporation is an energy company accelerating the path to a net-zero future. Leading innovation in more sustainable LNG and carbon capture solutions, NextDecade is committed to providing the world access to cleaner energy. Through our subsidiaries Rio Grande LNG and NEXT Carbon Solutions, we are developing a 27 MTPA LNG export facility in
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
View source version on businesswire.com: https://www.businesswire.com/news/home/20240509995231/en/
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation
FAQ
<p>What is the progress of Phase 1 construction at the Rio Grande LNG Facility?</p>
The overall project completion percentage for Trains 1 and 2 and the common facilities was 18.2% in March 2024, with Train 3 progress at 6.9%, all in line with the EPC contract schedule.
<p>When does NextDecade expect a positive FID on Train 4?</p>
NextDecade targets a positive FID on Train 4 in the second half of 2024, with ongoing commercial discussions and expectation of TotalEnergies to purchase 1.5 million tonnes per annum of LNG from Train 4.
<p>What financial steps has NextDecade taken to support Phase 1 development?</p>
The Company secured a $50 million revolving credit facility in January 2024 and issued $190 million in senior secured notes in February 2024 to finance Phase 1 at the Rio Grande LNG Facility.