NextDecade Provides Fourth Quarter 2024 Business Update
NextDecade (NASDAQ: NEXT) has provided a Q4 2024 business update highlighting progress on its Rio Grande LNG Facility development. Phase 1 (Trains 1-3) construction is progressing on schedule, with Trains 1-2 and common facilities at 38.1% completion and Train 3 at 15.3% completion as of January 2025.
The company announced plans to develop Trains 6-8, expected to add approximately 18 MTPA of liquefaction capacity. Train 6 (6 MTPA) will be developed inside the existing levee, with FERC pre-filing expected in 2025. Trains 7-8 (12 MTPA combined) will be developed outside the levee.
In December 2024, the company secured a $175 million senior secured loan at 12% interest. The company is actively working to finalize commercial arrangements for Train 4, with existing agreements including a 1.9 MTPA LNG SPA with ADNOC and a non-binding HOA with Aramco for 1.2 MTPA. TotalEnergies holds a 1.5 MTPA purchase option for Train 4.
NextDecade (NASDAQ: NEXT) ha fornito un aggiornamento aziendale per il quarto trimestre del 2024, evidenziando i progressi nello sviluppo della sua struttura LNG di Rio Grande. I lavori di costruzione della Fase 1 (Treni 1-3) stanno procedendo secondo il programma, con i Treni 1-2 e le strutture comuni al 38,1% di completamento e il Treno 3 al 15,3% di completamento a gennaio 2025.
La società ha annunciato piani per sviluppare i Treni 6-8, che si prevede aggiungeranno circa 18 MTPA di capacità di liquefazione. Il Treno 6 (6 MTPA) sarà sviluppato all'interno della diga esistente, con la pre-filing FERC prevista per il 2025. I Treni 7-8 (12 MTPA combinati) saranno sviluppati al di fuori della diga.
Nel dicembre 2024, l'azienda ha ottenuto un prestito senior garantito di 175 milioni di dollari con un tasso d'interesse del 12%. L'azienda sta lavorando attivamente per finalizzare gli accordi commerciali per il Treno 4, con accordi esistenti che includono un LNG SPA di 1,9 MTPA con ADNOC e un HOA non vincolante con Aramco per 1,2 MTPA. TotalEnergies detiene un'opzione di acquisto di 1,5 MTPA per il Treno 4.
NextDecade (NASDAQ: NEXT) ha proporcionado una actualización comercial para el cuarto trimestre de 2024, destacando los avances en el desarrollo de su instalación de LNG en Rio Grande. La construcción de la Fase 1 (Trenes 1-3) está avanzando según lo programado, con los Trenes 1-2 y las instalaciones comunes al 38,1% de finalización y el Tren 3 al 15,3% de finalización a enero de 2025.
La compañía anunció planes para desarrollar los Trenes 6-8, que se espera añadan aproximadamente 18 MTPA de capacidad de licuefacción. El Tren 6 (6 MTPA) se desarrollará dentro de la presa existente, con la pre-filing de la FERC esperada para 2025. Los Trenes 7-8 (12 MTPA en total) se desarrollarán fuera de la presa.
En diciembre de 2024, la empresa aseguró un préstamo senior garantizado de 175 millones de dólares con un interés del 12%. La empresa está trabajando activamente para finalizar los acuerdos comerciales para el Tren 4, con acuerdos existentes que incluyen un LNG SPA de 1,9 MTPA con ADNOC y un HOA no vinculante con Aramco por 1,2 MTPA. TotalEnergies tiene una opción de compra de 1,5 MTPA para el Tren 4.
NextDecade (NASDAQ: NEXT)는 2024년 4분기 사업 업데이트를 제공하여 리오 그란데 LNG 시설 개발의 진행 상황을 강조했습니다. 1단계(기차 1-3) 건설은 일정대로 진행되고 있으며, 기차 1-2와 공용 시설은 38.1% 완공되었고, 기차 3는 2025년 1월 기준으로 15.3% 완공되었습니다.
회사는 약 18 MTPA의 액화 용량을 추가할 것으로 예상되는 기차 6-8 개발 계획을 발표했습니다. 기차 6(6 MTPA)은 기존 제방 내에서 개발될 예정이며, 2025년에는 FERC 사전 제출이 예상됩니다. 기차 7-8(총 12 MTPA)은 제방 밖에서 개발될 것입니다.
2024년 12월, 회사는 12% 이자의 1억 7500만 달러 규모의 고정 담보 대출을 확보했습니다. 회사는 ADNOC와의 1.9 MTPA LNG SPA 및 Aramco와의 1.2 MTPA에 대한 비구속 HOA를 포함한 기존 계약을 통해 기차 4에 대한 상업적 계약을 마무리하기 위해 적극적으로 노력하고 있습니다. TotalEnergies는 기차 4에 대한 1.5 MTPA 구매 옵션을 보유하고 있습니다.
NextDecade (NASDAQ: NEXT) a fourni une mise à jour commerciale pour le quatrième trimestre 2024, mettant en lumière les progrès réalisés dans le développement de son installation LNG de Rio Grande. La construction de la Phase 1 (Trains 1-3) avance selon le calendrier, avec les Trains 1-2 et les installations communes à 38,1 % d'achèvement et le Train 3 à 15,3 % d'achèvement en janvier 2025.
L'entreprise a annoncé des projets pour développer les Trains 6-8, qui devraient ajouter environ 18 MTPA de capacité de liquéfaction. Le Train 6 (6 MTPA) sera développé à l'intérieur de la digue existante, avec un pré-dépôt FERC prévu pour 2025. Les Trains 7-8 (12 MTPA au total) seront développés à l'extérieur de la digue.
En décembre 2024, l'entreprise a sécurisé un prêt senior garanti de 175 millions de dollars avec un intérêt de 12 %. L'entreprise travaille activement à finaliser les accords commerciaux pour le Train 4, avec des accords existants incluant un LNG SPA de 1,9 MTPA avec ADNOC et un HOA non contraignant avec Aramco pour 1,2 MTPA. TotalEnergies détient une option d'achat de 1,5 MTPA pour le Train 4.
NextDecade (NASDAQ: NEXT) hat ein Geschäftsupdate für das vierte Quartal 2024 bereitgestellt, das die Fortschritte beim Bau seiner LNG-Anlage in Rio Grande hervorhebt. Der Bau der Phase 1 (Züge 1-3) verläuft planmäßig, wobei die Züge 1-2 und die gemeinsamen Einrichtungen zu 38,1 % fertiggestellt sind und Zug 3 zu 15,3 % fertiggestellt ist (Stand Januar 2025).
Das Unternehmen kündigte Pläne zur Entwicklung der Züge 6-8 an, die voraussichtlich etwa 18 MTPA an Verflüssigungskapazität hinzufügen werden. Zug 6 (6 MTPA) wird innerhalb des bestehenden Deichs entwickelt, wobei eine FERC-Vorabgenehmigung für 2025 erwartet wird. Die Züge 7-8 (insgesamt 12 MTPA) werden außerhalb des Deichs entwickelt.
Im Dezember 2024 sicherte sich das Unternehmen ein gesichertes Darlehen in Höhe von 175 Millionen US-Dollar mit einem Zinssatz von 12 %. Das Unternehmen arbeitet aktiv daran, die kommerziellen Vereinbarungen für Zug 4 abzuschließen, wobei bestehende Vereinbarungen einen LNG SPA über 1,9 MTPA mit ADNOC und eine nicht verbindliche HOA mit Aramco über 1,2 MTPA umfassen. TotalEnergies hat eine Kaufoption über 1,5 MTPA für Zug 4.
- Phase 1 construction progressing on schedule and budget
- Secured $175M senior secured loan for expansion
- Multiple commercial agreements in place for Train 4
- Plans for 18 MTPA additional capacity with Trains 6-8
- FERC reauthorization vacated by Court of Appeals
- Pending regulatory approval for supplemental EIS
- High interest rate (12%) on new secured loan
- Train 4 EPC contract pricing needs refresh in 2025
Insights
NextDecade's Q4 update reveals significant expansion beyond their initial 5-train Rio Grande LNG facility with development plans for Trains 6-8 that would add approximately 18 MTPA of liquefaction capacity. Construction of Phase 1 (Trains 1-3) remains on schedule and budget, with completion percentages of 38.1% for Trains 1-2 and 15.3% for Train 3.
The company bolstered its financial position through a
A critical regulatory challenge remains unresolved, as the U.S. Court of Appeals vacated FERC's reauthorization of the facility, requiring a supplemental Environmental Impact Statement with a final decision expected by November 2025. While construction continues, this regulatory uncertainty presents a material risk to the expansion timeline.
Commercial momentum appears strong for Trains 4-5, with agreements or HOAs with ADNOC (1.9 MTPA), Aramco (1.2 MTPA), and TotalEnergies (potential 1.5 MTPA option) for Train 4. The company's expansion strategy positions it to capitalize on growing global LNG demand, though execution will depend on maintaining regulatory approvals and securing final commercial arrangements to support positive FID decisions.
NextDecade's ambitious expansion plan beyond the initial 5 trains represents a strategic positioning in the tight global LNG market. By developing Trains 6-8 with 18 MTPA additional capacity, the company is exploiting its existing site advantages including Permian Basin proximity, uncongested waterway access, and favorable weather conditions relative to other Gulf Coast locations.
The Train 6 development inside the existing levee creates meaningful economic advantages through reduced site preparation costs. Meanwhile, the regulatory setback requiring a supplemental EIS creates execution risk but appears manageable given FERC's established timeline for completion.
The company's commercialization strategy shows market validation with major global energy players. ADNOC and Aramco's involvement signals Middle Eastern interest in securing U.S. LNG export capacity, while TotalEnergies' options for both Train 4 and 5 demonstrate confidence from a major integrated player.
The financing structure for Train 4 gives existing equity partners options that would fund
Outlines Development Plans for Approximately 18 MTPA of Additional Liquefaction Capacity
CEO Commentary
“As we begin 2025, we are at an exciting time in NextDecade history. Our team is working diligently to capitalize on our outsized growth opportunities while continuing to construct Trains 1 through 3 (Phase 1) at the Rio Grande LNG Facility safely, on schedule, and on budget,” said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. “We are working with multiple potential commercial counterparties to progress Trains 4 and 5 toward positive final investment decisions (FIDs), and we believe we are well positioned to secure commercial support for both trains.”
“Today, we are also pleased to announce development plans for expansion capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. We are currently developing and preparing to start the permitting process for Train 6 and starting the development of Trains 7 and 8. Train 6 is being developed inside the existing levee at the site, which is expected to provide advantages in site preparation and expected economics. We plan to pre-file an application with the Federal Regulatory Energy Commission (FERC) for Train 6 this year. Trains 7 and 8 are being developed on the site outside of the existing levee. Additionally, we expect to explore options for the development of up to two additional trains at our site beyond Train 8.”
Significant Recent Developments
Construction
-
Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of January 2025:
-
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was
38.1% , which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was84.9% complete, procurement was69.2% complete, and construction was10.6% complete. -
The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was
15.3% , which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was33.5% complete, procurement was32.8% complete, and construction was0.4% complete.
-
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was
-
In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
- Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.
- Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA, are being developed on the site outside of the existing levee.
Financial
-
In December 2024, the Company’s wholly-owned subsidiary, Rio Grande LNG Super Holdings, LLC, entered into a credit agreement (the Corporate Credit Agreement) which provided for a
senior secured loan. Proceeds from the senior secured loan were disbursed at closing on December 31, 2024, and net proceeds were used to repay outstanding borrowings under the Company’s existing$175 million revolving credit facility and$50 million interest term loan, and will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility. Borrowings under the senior secured loan bear interest at$12.5 million 12.0% , with interest payable quarterly. Interest may be paid in-kind until March 31, 2027, and up to50% in-kind thereafter. The senior secured loan matures six years from the closing date.
-
In conjunction with the closing of the Corporate Credit Agreement, the Company issued warrants in two equal tranches that are exercisable for an aggregate of approximately 7.2 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the closing date. The first tranche of the warrants are exercisable at
per share, which represents the 30-day volume weighted average trading price for the 30 trading-day period immediately preceding the closing date, and the second tranche of the warrants are exercisable at$7.15 per share.$9.30
Regulatory
-
In August 2024, the
U.S. Court of Appeals for the D.C. Circuit (the Court) issued a decision vacating FERC’s reauthorization of the Rio Grande LNG Facility on the grounds that FERC should have issued a supplemental Environmental Impact Statement (EIS) during its reauthorization process.
- On September 13, 2024, FERC issued notice of its intent to prepare a supplemental EIS in response to the Court’s decision. The notice set forth a schedule providing for the issuance of a draft of the supplemental EIS in March 2025, the final supplemental EIS by the end of July 2025, and issuance of a final order by November 20, 2025.
- On October 21, 2024, the Company filed a petition for rehearing and rehearing en banc with the Court. On December 9, 2024, petitioners in the case and FERC filed responses to the Company’s request for rehearing, and the Court’s decision is pending.
- The Court’s decision will not be effective until the Court has issued its mandate, which is not expected to occur until after the appeals process has been completed. At this time, construction continues on Phase 1 at the Rio Grande LNG Facility.
- The Company expects to take all available legal and regulatory actions, including appellate actions, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals will be maintained to enable a positive FID on Trains 4 and 5 at the Rio Grande LNG Facility.
Rio Grande LNG Facility
NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south
Phase 1 (Trains 1-3)
Phase 1 at the Rio Grande LNG Facility is under construction. Phase 1 includes three liquefaction trains with a total nameplate capacity of approximately 18 MTPA of LNG production, two 180,000 cubic meter full containment LNG storage tanks, and two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity. Phase 1 also includes associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the development area, and warehouses, administrative, operations control room, and maintenance buildings.
As of January 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the fourth quarter and early 2025, the construction team continued steel assembly in the Train 1 area and adjacent pipe racks. Within Train 2, foundations were progressed and steel assembly began. Tank 1 roof panels were set in place, and the first wall concrete pour for Tank 2 was completed. Across the site, Bechtel’s work also continues on installing underground structures, loading berths, piling, concrete foundations, and other siteworks. Bechtel has materially completed purchase orders for critical and high-value items for Phase 1.
NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to
Final Investment Decision on Train 4 and Train 5
We expect to make a positive FID and commence construction on Trains 4 and 5 and related infrastructure at the Rio Grande LNG Facility, subject to, among other things, maintaining requisite governmental approvals, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.
The Company has finalized an EPC contract with Bechtel for Train 4 and related infrastructure. Pricing under the EPC Contract for Train 4 was valid through December 31, 2024, and a pricing refresh is in process and is expected to be completed in 2025.
The Company continues to advance commercial discussions with multiple potential counterparties and expects to finalize commercial arrangements for Train 4 in the coming months to support a positive FID on Train 4. The Company entered into an LNG SPA with ADNOC for the sale of 1.9 MTPA of LNG from Train 4, as well as a non-binding Heads of Agreement (HoA) with Aramco for a 20-year SPA for the sale of 1.2 MTPA of LNG from Train 4. The Company is working with Aramco to finalize a binding SPA. Additionally, an affiliate of TotalEnergies SE (TotalEnergies) has an LNG purchase option of 1.5 MTPA for Train 4, and the Company expects TotalEnergies to exercise the option.
The Company expects to finance construction of Train 4 and associated infrastructure utilizing a combination of debt and equity funding. The Company expects to enter into bank facilities for the debt portion of the funding. In connection with consummating the Rio Grande Phase 1 equity joint venture, the Company's equity partners each have options to invest in Train 4 equity, which, if exercised, would provide approximately
The Company is also progressing the development and commercialization of Train 5. TotalEnergies holds an LNG purchase option for 1.5 MTPA for Train 5, and the Rio Grande Phase 1 equity partners have options to invest in Train 5 equity which are identical to their options to participate in Train 4 equity.
Development of Additional Liquefaction Capacity
The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. Trains 7 and 8 are being developed on the site outside of the existing levee.
Investor Presentation
NextDecade has posted an updated investor presentation to its website concurrently with this release. A copy of this release and the investor presentation can be found on its website at investors.next-decade.com.
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, lower carbon energy. We are focused on delivering secure, low-cost, and sustainable energy solutions through the safe and efficient development and operation of natural gas liquefaction and carbon capture and storage infrastructure. Through our subsidiaries, we are developing and constructing the Rio Grande LNG natural gas liquefaction and export facility near
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
View source version on businesswire.com: https://www.businesswire.com/news/home/20250227832226/en/
NextDecade Contacts
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation
FAQ
What is the current construction progress of NextDecade's Rio Grande LNG Facility Phase 1 as of January 2025?
How much additional LNG capacity will NextDecade's Trains 6-8 development add to the facility?
What major commercial agreements does NextDecade (NEXT) have in place for Train 4?