Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Nebius Group (NASDAQ: NBIS) announced a significant expansion of its US cloud computing capacity with plans to construct a new data center in New Jersey with up to 300 MW capacity. The build-to-suit facility's first phase is expected to complete by summer 2025, supporting their target of 100 MW installed capacity by end-2025.

The company also revealed capacity additions at other locations:

  • Additional deployment phase in Kansas City, expected online by Q2 2025
  • New colocation deployment in Keflavik, Iceland, powered by geothermal energy, to be operational by Q1 2025
  • Tripled capacity at their Finland data center

These expansions will boost Nebius's total secured expansion capacity to over 400 MW, strengthening their position as a global AI infrastructure provider in both US and European markets.

Nebius Group (NASDAQ: NBIS) ha annunciato una significativa espansione della sua capacità di cloud computing negli Stati Uniti con piani per costruire un nuovo data center nel New Jersey con una capacità fino a 300 MW. La prima fase della struttura su misura dovrebbe essere completata entro l'estate del 2025, supportando l'obiettivo di 100 MW di capacità installata entro la fine del 2025.

L'azienda ha anche rivelato aggiunte di capacità in altre località:

  • Fase di distribuzione aggiuntiva a Kansas City, prevista online entro il secondo trimestre del 2025
  • Nuova distribuzione di colocation a Keflavik, Islanda, alimentata da energia geotermica, che sarà operativa entro il primo trimestre del 2025
  • Capacità triplicata nel loro data center in Finlandia

Queste espansioni aumenteranno la capacità totale di espansione sicura di Nebius a oltre 400 MW, rafforzando la loro posizione come fornitore globale di infrastrutture AI sia nei mercati statunitensi che europei.

Nebius Group (NASDAQ: NBIS) anunció una expansión significativa de su capacidad de computación en la nube en EE. UU. con planes para construir un nuevo centro de datos en New Jersey con una capacidad de hasta 300 MW. Se espera que la primera fase de la instalación a medida se complete para el verano de 2025, apoyando su objetivo de 100 MW de capacidad instalada para finales de 2025.

La empresa también reveló adiciones de capacidad en otras ubicaciones:

  • Fase de despliegue adicional en Kansas City, que se espera esté en línea para el segundo trimestre de 2025
  • Nuevo despliegue de colocation en Keflavik, Islandia, alimentado por energía geotérmica, que estará operativo para el primer trimestre de 2025
  • Capacidad triplicada en su centro de datos en Finlandia

Estas expansiones aumentarán la capacidad total de expansión asegurada de Nebius a más de 400 MW, fortaleciendo su posición como proveedor global de infraestructura de IA en los mercados de EE. UU. y Europa.

네비우스 그룹 (NASDAQ: NBIS)은 뉴저지에 최대 300MW 용량의 새로운 데이터 센터를 건설할 계획을 통해 미국 클라우드 컴퓨팅 용량을 대폭 확장한다고 발표했습니다. 맞춤형 시설의 첫 번째 단계는 2025년 여름까지 완료될 것으로 예상되며, 2025년 말까지 100MW의 설치 용량 목표를 지원합니다.

회사는 또한 다른 위치에서 용량 추가를 공개했습니다:

  • 2025년 2분기 온라인 예정인 캔자스 시티의 추가 배포 단계
  • 지열 에너지로 운영되는 케플라빅, 아이슬란드의 새로운 콜로케이션 배포, 2025년 1분기부터 운영 예정
  • 핀란드 데이터 센터의 용량을 3배로 증가

이러한 확장은 네비우스의 총 확보된 확장 용량을 400MW 이상으로 증가시켜 미국 및 유럽 시장에서 글로벌 AI 인프라 제공자로서의 입지를 강화합니다.

Nebius Group (NASDAQ: NBIS) a annoncé une expansion significative de sa capacité de cloud computing aux États-Unis avec des projets de construction d'un nouveau centre de données dans le New Jersey avec une capacité allant jusqu'à 300 MW. La première phase de cette installation sur mesure devrait être achevée d'ici l'été 2025, soutenant leur objectif de 100 MW de capacité installée d'ici fin 2025.

L'entreprise a également révélé des ajouts de capacité dans d'autres emplacements :

  • Phase de déploiement supplémentaire à Kansas City, prévue en ligne d'ici le 2ème trimestre 2025
  • Nouvelle déploiement de colocation à Keflavik, Islande, alimentée par l'énergie géothermique, devant être opérationnelle d'ici le 1er trimestre 2025
  • Capacité triplée dans leur centre de données en Finlande

Ces expansions porteront la capacité totale d'expansion sécurisée de Nebius à plus de 400 MW, renforçant leur position en tant que fournisseur d'infrastructure IA à l'échelle mondiale sur les marchés américain et européen.

Nebius Group (NASDAQ: NBIS) hat eine bedeutende Erweiterung seiner Cloud-Computing-Kapazität in den USA angekündigt, mit Plänen zum Bau eines neuen Rechenzentrums in New Jersey mit einer Kapazität von bis zu 300 MW. Die erste Phase der maßgeschneiderten Einrichtung soll bis zum Sommer 2025 abgeschlossen sein und unterstützt das Ziel von 100 MW installierter Kapazität bis Ende 2025.

Das Unternehmen gab auch Kapazitätserweiterungen an anderen Standorten bekannt:

  • Zusätzliche Bereitstellungsphase in Kansas City, die voraussichtlich im 2. Quartal 2025 online geht
  • Neue Colocation-Bereitstellung in Keflavik, Island, betrieben mit geothermischer Energie, die im 1. Quartal 2025 in Betrieb genommen wird
  • Verdreifachte Kapazität in ihrem Rechenzentrum in Finnland

Diese Erweiterungen werden die insgesamt gesicherte Erweiterungskapazität von Nebius auf über 400 MW erhöhen und ihre Position als globaler Anbieter von KI-Infrastruktur sowohl auf dem US-amerikanischen als auch auf dem europäischen Markt stärken.

Positive
  • Major capacity expansion with 300 MW New Jersey facility
  • Total secured expansion capacity exceeds 400 MW
  • Multiple new data centers coming online by 2025
  • Eco-friendly geothermal power source for Iceland facility
Negative
  • Significant capital expenditure required for multiple facility expansions
  • Extended timeline to full capacity deployment (through 2025)

Insights

Nebius Group's expansion announcement represents a significant scaling of its AI infrastructure, with the New Jersey facility adding up to 300 MW of potential capacity. This move substantially accelerates their previously communicated target of 100 MW of installed capacity by end-2025. The phased development approach provides strategic flexibility to match deployment with actual demand growth.

The expansion across multiple geographies (New Jersey, Kansas City, Iceland, and Finland) creates a diversified infrastructure footprint that enhances service reliability and reduces latency for customers across different regions. Particularly notable is the company's emphasis on the US market, signaling a strategic pivot toward capturing market share in the world's largest cloud computing market.

By securing expansion capacity exceeding 400 MW with more in the pipeline, Nebius is positioning itself to capitalize on the surging demand for AI compute resources. The build-to-suit approach in New Jersey gives them control over facility design, likely optimizing power efficiency and cooling systems - critical factors in controlling operational costs and maximizing computational density per square foot.

The Iceland deployment leverages geothermal energy, addressing growing customer preferences for environmentally sustainable compute resources. This multi-region strategy enables Nebius to offer distributed computing options that align with both performance and regulatory requirements.

Nebius's accelerated infrastructure expansion represents a substantial capital commitment that signals confidence in future demand growth. While specific investment figures aren't disclosed, data centers of this scale typically require $5-15 million per MW in development costs, potentially representing a $1.5+ billion long-term investment for the New Jersey facility alone at full capacity.

The phased deployment approach balances growth ambitions with capital efficiency, allowing for calibrated investment timing based on customer acquisition. By securing sites with expansion potential, Nebius gains valuable optionality to scale rapidly if market conditions warrant, while maintaining discipline on utilization rates.

This expansion significantly increases Nebius's total addressable market, particularly in the high-demand US region. The decision to build their own facility rather than solely using colocation services suggests a long-term commitment to the region and expectations of sustained demand that justifies the fixed-cost investment.

The CEO's statement about growing to "multiples of where we are today" indicates a substantial revenue growth trajectory. Given typical data center economics, this expanded capacity could translate to significant recurring revenue growth as utilization increases, though with a lag between capital deployment and revenue realization as capacity is gradually filled.

  • New build-to-suit facility in New Jersey will have design capacity of up to 300 MW;
  • Incremental capacity also being added at existing facility in Kansas City and new site in Iceland.

AMSTERDAM--(BUSINESS WIRE)-- Nebius Group N.V. (“Nebius Group” or the “Company”; NASDAQ: NBIS), a leading AI infrastructure company, today announced a major upgrade to its US-based cloud computing capacity with the planned construction of a new data center in New Jersey with capacity of up to 300 MW.

The data center that Nebius has commissioned in New Jersey will be built to Nebius’s own design, enabling the company to achieve maximum efficiency and offer superlative performance to customers. The facility is a phased development expandable up to a total capacity of 300 MW, with the first capacity expected to be completed as early as summer 2025. This delivers on the company’s previous guidance for 100 MW of installed capacity by the end of 2025, with potential to accelerate beyond that if required to meet demand.

Arkady Volozh, founder and CEO of Nebius, said:

“Our first major data center in the US clearly advances our strategic goal of expanding our footprint in the American market as we continue building Nebius into a leading global AI infrastructure provider. This site has the potential to host dedicated large-scale instances, and we have considerable flexibility to accelerate our deployment plans as and when we need to.

“With New Jersey, we now have secured expansion capacity to over 400 MW. And we are actively reviewing options to extend this pipeline further as we seek to grow aggressively to multiples of where we are today.”

In addition to the new data center in New Jersey, Nebius today announced incremental capacity additions at its existing colocation deployment in Kansas City and a new location in Iceland.

In Kansas City, Nebius has agreed a second deployment phase, with the additional capacity expected to be online by the end of Q2 2025. Delivery of the first phase at Kansas City remains on track for Q1 2025. In Iceland, Nebius confirmed a new colocation deployment in Keflavik, Iceland, as it builds out more AI infrastructure in Europe. Physical deployment and software installation are underway, and the new capacity is expected to be fully operational and available to clients by the end of Q1 2025. This deployment is powered by Iceland's abundant geothermal energy to reduce environmental impact.

Combined with the tripling of capacity at Nebius’s first data center in Finland, as well as potential deployments at new sites currently in the pipeline, these additions will make a significant contribution to the company’s planned ramp-up of installed capacity in the US and Europe during 2025.

About Nebius

Nebius (NASDAQ:NBIS) is a technology company building full-stack infrastructure to service the explosive growth of the global AI industry, including large-scale GPU clusters, cloud platforms, and tools and services for developers. Headquartered in Amsterdam and listed on Nasdaq, the company has a global footprint with R&D hubs across Europe, North America and Israel.

Nebius’ core business is an AI-centric cloud platform built for intensive AI workloads. With proprietary cloud software architecture and hardware designed in-house (including servers, racks and data center design), Nebius gives AI builders the compute, storage, managed services and tools they need to build, tune and run their models.

A Preferred cloud service provider in the NVIDIA Partner Network, Nebius offers high-end infrastructure optimized for AI training and inference. The company boasts a team of around 400 skilled engineers, delivering a true hyperscale cloud experience tailored for AI builders. To learn more please visit www.nebius.com.

Media Relations: media@nebius.com

Source: Nebius Group

FAQ

What is the capacity of Nebius's new New Jersey data center and when will it be operational?

The New Jersey data center will have a total capacity of up to 300 MW, with the first phase expected to be operational by summer 2025.

How much total expansion capacity has NBIS secured with these new developments?

Nebius has secured expansion capacity of over 400 MW across their various locations.

When will Nebius's Kansas City facility's second phase be completed?

The additional capacity at Kansas City is expected to be online by the end of Q2 2025.

What are the environmental features of NBIS's new Iceland data center?

The Iceland facility in Keflavik will be powered by geothermal energy to reduce environmental impact and will be operational by Q1 2025.

What is Nebius's (NBIS) installed capacity target for the end of 2025?

Nebius aims to achieve 100 MW of installed capacity by the end of 2025.

Nebius Group

NASDAQ:NBIS

NBIS Rankings

NBIS Latest News

NBIS Stock Data

6.98B
192.58M
3.64%
27.07%
2.82%
Internet Content & Information
Communication Services
Link
Netherlands
Amsterdam