i-80 Gold Announces Positive Preliminary Economic Assessment on the Granite Creek Open Pit Project, Nevada; After-Tax NPV(5%) of $421 Million with an After-Tax IRR of 30% at US$2,175/oz Au
i-80 Gold Corp (NYSE:IAUX) has announced positive results from the Preliminary Economic Assessment (PEA) for its Granite Creek Open Pit Project in Nevada. The project demonstrates robust economics with an after-tax NPV(5%) of $421 million and an IRR of 30% at $2,175/oz gold price.
The project features a 10-year mine life with annual gold production of approximately 130,000 ounces following ramp-up. The mine will process 3.5 million tonnes annually through a Carbon-in-Leach (CIL) facility, with an average gold grade of 1.25 g/t and expected recovery of 86.6%.
Key financial metrics include:
- Estimated life-of-mine cash costs of $1,185/oz
- All-in-sustaining costs of $1,225/oz
- Initial construction capital of $200 million
- Pre-production stripping cost of $33.9 million
- Sustaining capital of $30.3 million
i-80 Gold Corp (NYSE:IAUX) ha annunciato risultati positivi dalla Valutazione Economica Preliminare (PEA) per il suo Granite Creek Open Pit Project in Nevada. Il progetto dimostra una solida economia con un NPV(5%) dopo le tasse di 421 milioni di dollari e un IRR del 30% a un prezzo dell'oro di 2.175 dollari/oz.
Il progetto prevede una vita mineraria di 10 anni con una produzione annuale di oro di circa 130.000 once dopo il periodo di ramp-up. La miniera tratterà 3,5 milioni di tonnellate all'anno attraverso un impianto Carbon-in-Leach (CIL), con un grado medio di oro di 1,25 g/t e un recupero previsto dell'86,6%.
I principali indicatori finanziari includono:
- Costi di cassa stimati per la vita della miniera di 1.185 dollari/oz
- Costi totali sostenibili di 1.225 dollari/oz
- Capitale iniziale per la costruzione di 200 milioni di dollari
- Costi di stripping pre-produzione di 33,9 milioni di dollari
- Capitale sostenibile di 30,3 milioni di dollari
i-80 Gold Corp (NYSE:IAUX) ha anunciado resultados positivos de la Evaluación Económica Preliminar (PEA) para su Granite Creek Open Pit Project en Nevada. El proyecto muestra una economía robusta con un NPV(5%) después de impuestos de 421 millones de dólares y un IRR del 30% a un precio del oro de 2,175 dólares/oz.
El proyecto cuenta con una vida útil de la mina de 10 años con una producción anual de oro de aproximadamente 130,000 onzas tras la fase de ramp-up. La mina procesará 3.5 millones de toneladas anualmente a través de una instalación de Carbon-in-Leach (CIL), con una ley promedio de oro de 1.25 g/t y una recuperación esperada del 86.6%.
Los principales indicadores financieros incluyen:
- Costos de efectivo estimados de la vida útil de la mina de 1,185 dólares/oz
- Costos sostenibles totales de 1,225 dólares/oz
- Capital inicial de construcción de 200 millones de dólares
- Costos de stripping pre-producción de 33.9 millones de dólares
- Capital sostenible de 30.3 millones de dólares
i-80 Gold Corp (NYSE:IAUX)는 네바다에 있는 Granite Creek Open Pit Project에 대한 예비 경제 평가(PEA)에서 긍정적인 결과를 발표했습니다. 이 프로젝트는 세후 NPV(5%)가 4억 2,100만 달러와 IRR이 30%로 강력한 경제성을 보여줍니다(금 가격 2,175달러/oz 기준).
이 프로젝트는 10년의 광산 수명을 가지고 있으며, ramp-up 후 연간 약 130,000 온스의 금 생산을 목표로 하고 있습니다. 이 광산은 연간 350만 톤을 처리하며, Carbon-in-Leach (CIL) 시설을 통해 평균 금 함량은 1.25 g/t이고 예상 회수율은 86.6%입니다.
주요 재무 지표는 다음과 같습니다:
- 추정 광산 생애 현금 비용 1,185달러/oz
- 전체 유지 비용 1,225달러/oz
- 초기 건설 자본 2억 달러
- 생산 전 제거 비용 3,390만 달러
- 유지 자본 3,030만 달러
i-80 Gold Corp (NYSE:IAUX) a annoncé des résultats positifs de l'Évaluation Économique Préliminaire (PEA) pour son Granite Creek Open Pit Project dans le Nevada. Le projet démontre une économie solide avec un NPV(5%) après impôts de 421 millions de dollars et un IRR de 30% à un prix de l'or de 2.175 dollars/oz.
Le projet présente une durée de vie de mine de 10 ans avec une production annuelle d'or d'environ 130.000 onces après la phase de montée en puissance. La mine traitera 3,5 millions de tonnes par an via une installation Carbon-in-Leach (CIL), avec une teneur moyenne en or de 1,25 g/t et un taux de récupération attendu de 86,6%.
Les principaux indicateurs financiers comprennent:
- Coûts de trésorerie estimés sur la durée de vie de la mine de 1.185 dollars/oz
- Coûts totaux soutenus de 1.225 dollars/oz
- Capital initial de construction de 200 millions de dollars
- Coûts de décapage pré-production de 33,9 millions de dollars
- Capital de maintien de 30,3 millions de dollars
i-80 Gold Corp (NYSE:IAUX) hat positive Ergebnisse der Vorläufigen Wirtschaftlichkeitsbewertung (PEA) für sein Granite Creek Open Pit Project in Nevada bekannt gegeben. Das Projekt zeigt eine robuste Wirtschaftlichkeit mit einem NPV(5%) nach Steuern von 421 Millionen Dollar und einer IRR von 30% bei einem Goldpreis von 2.175 Dollar/oz.
Das Projekt umfasst eine 10-jährige Lebensdauer der Mine mit einer jährlichen Goldproduktion von etwa 130.000 Unzen nach der Hochlaufphase. Die Mine wird jährlich 3,5 Millionen Tonnen über eine Carbon-in-Leach (CIL) Anlage verarbeiten, mit einem durchschnittlichen Goldgehalt von 1,25 g/t und einer erwarteten Rückgewinnung von 86,6%.
Wichtige Finanzkennzahlen sind:
- Geschätzte Lebensdauer der Mine Bargeldkosten von 1.185 Dollar/oz
- All-in-sustaining Kosten von 1.225 Dollar/oz
- Erstinvestitionen von 200 Millionen Dollar
- Vorproduktionsabraumkosten von 33,9 Millionen Dollar
- Erhaltungsinvestitionen von 30,3 Millionen Dollar
- Strong after-tax NPV of $421M and 30% IRR at $2,175/oz gold
- Significant annual gold production of 130,000 oz
- High gold recovery rate of 86.6%
- Large indicated resource of 1.44M oz at 1.18 g/t
- Existing infrastructure reduces capital requirements
- High initial capital requirement of $200M plus $33.9M pre-stripping
- High strip ratio of 8.2:1
- Additional permits required with 3-year timeline
- High operating costs with AISC of $1,225/oz
Insights
i-80 Gold's Granite Creek Open Pit PEA demonstrates exceptional economic potential with an after-tax NPV(5%) of
The project's fundamentals are robust: 1.44 million ounces of indicated gold resources at 1.18 g/t, with anticipated annual production of 130,000 ounces over a 10-year mine life. Cash costs of
The decision to implement full CIL processing rather than heap leaching represents a critical optimization. While requiring higher upfront capital, the
Located on Nevada's prolific Getchell Trend near Nevada Gold Mines' Turquoise Ridge Complex, the project benefits from established infrastructure, previous mining history, and a potential fast-track permitting pathway as a brownfield development. The expected three-year permitting timeline is reasonable for Nevada.
This PEA demonstrates that Granite Creek Open Pit can serve as a transformational asset for i-80 Gold. The project leverages several strategic advantages that significantly de-risk the development pathway. First, this is a brownfield site with previous production of 987,000 ounces, providing extensive historical data and reduced geological uncertainty. Second, the existing underground infrastructure, particularly dewatering systems, reduces capital requirements.
The shift to full CIL processing addresses the critical challenge of organic carbon in the ore body that would otherwise cause recovery issues in conventional heap leaching. This demonstrates sophisticated technical planning, as preg-robbing characteristics in carbonaceous ores typically present significant metallurgical challenges. The
From a permitting perspective, the project benefits from being a previously disturbed site, though the EIS requirement adds complexity. The three-year permitting timeline appears reasonable but remains the critical path element for development. Water management plans for handling mine-influenced water with elevated arsenic demonstrate environmental diligence.
The
The planned feasibility study completion in Q4 2025 provides a clear development timeline, with additional metallurgical work appropriately focused on optimizing the CIL processing parameters.
This news release constitutes a "designated news release" for the purposes of the Company's prospectus supplement dated August 12, 2024, to its short form base shelf prospectus dated June 21, 2024.
"This Granite Creek Open Pit has all the markings of a top tier project; it is an open pit oxide project in
Granite Creek Open Pit PEA Highlights
Mineral Estimates, Production and Mine Life
- Large open pit carbon-in-leach ("CIL") gold mine with a life of mine ("LOM") of approximately 10 years.
- Annual gold production of approximately 130,000 ounces following ramp up.
- Estimated LOM cash costs(1) of
per ounce and all-in-sustaining costs(1) of$1,185 per ounce.$1,225 - Updated mineral resource estimate resulting in an indicated gold mineral resource of 1.44 million ounces at 1.18 grams per tonne ("g/t").
- Updated mineral resource estimate resulting in an inferred gold mineral resource 0.08 million ounces at 1.09 g/t.
Project Economics
- Based on a
/oz gold price, the Project's undiscounted after-tax cash flows(2) total$2,175 with an after-tax net present value(2)("NPV") of$661 million , assuming a$421 million 5% discount rate, generating an30% internal rate of return ("IRR"). - Based on spot gold of
/oz, the Project's undiscounted after-tax cash flows total$2,900 with an after-tax NPV(2) of$1,267 million , assuming a$866 million 5% discount rate, generating an IRR of50% . - Mine construction capital, including all pre-production facilities and infrastructure is estimated at approximately
. No capital is included in mine construction capital for mobile equipment as the plan incorporates contract mining. Unit mining costs have been increased accordingly.$200 million - Additionally, 12.9 million tonnes of stripping is required pre-production and 4.7 million tonnes in the first production year, costing
.$33.9 million - LOM sustaining capital is estimated at
, primarily for tailings dam expansion and general sustaining costs.$30.3 million - Total capital includes a contingency of
25% , or .$49.1 million
Mining and Processing
- The primary mining method will be a conventional open pit truck (10 to 12 trucks) and loader (4 loaders) operation, moving approximately 40 million tonnes per year during a steady state of production.
- The LOM strip ratio is 8.2:1, excluding capitalized pre-stripping.
- Material mined will be treated in a CIL process plant on site at a rate of approximately 3.5 million tonnes per year during steady state.
- Overall average gold grade processed of 1.25 g/t with an expected average gold recovery of
86.6% .
All amounts are in
A summary of key valuation, cost, and operating metrics is presented in Table 1 below. For more detailed metrics presented on an annual basis, see Granite Creek Open Pit Detailed Cash Flow Model in Appendix.
Table 1: Summary of PEA Key Operating and Financial Metrics
Project Economics | Unit | |
Gold Price | $/oz | |
Pre-Tax NPV( | $M | |
After-Tax NPV( | $M | |
After-Tax IRR | % | 30 % |
After-Tax Cash Flow | $M | |
Production Profile | ||
Mine Life | years | ~10 |
Mineralized Material Mined | 000s | 34,854.5 |
Gold Grade of Mineralized Material Mined | g/t Au | 1.25 |
Waste Tonnes Mined (excluding Capitalized Stripping) | 000s | 287,352.9 |
Capitalized Stripping Tonnes Mined | 000s | 21,969.9 |
Total Tonnes Moved (Incl. Capitalized Stripping) | 000s | 339,845.0 |
Total Mineralized Material Processed | 000s | 34,854.5 |
Gold Grade Processed | g/t Au | 1.25 |
Strip Ratio (excluding capitalized stripping) | (waste:mineralized | 8.2:1 |
Average Gold Recovery | % | 86.6 % |
Total Gold Recovered | 000s oz | 1,120 |
Average Annual Gold Equivalent | 000s oz | 110.0 |
Average Annual Gold Production | 000s oz | 128.6 |
Unit Operating Costs | ||
Mineralized Material Mined | $/t mined | |
Processed (CIL) | $/t processed | |
G&A | $/t processed | |
LOM Total Cash Costs(1) (net of by-product credit) | $/oz | |
LOM All-in Sustaining Costs(1) (net of by-product credit) | $/oz | |
Total Capital Costs | ||
Permitting | $M | |
Construction Capital | $M | |
Capitalized Stripping | $M | |
Sustaining Capital | $M | |
Reclamation & Surety | $M | |
Total Capital & Closure Costs | $M |
"The steady increase in the gold price has provided the opportunity to reassess the optimal processing stream for the Granite Creek Open Pit Project. The PEA confirms that anchoring entirely on a CIL processing facility adds significant value, primarily through higher gold recoveries, compared to conventional heap leach processing and reduces recovery risk. Additionally, the Project benefits from existing underground infrastructure, such as the dewatering systems, which improve efficiency and reduce capital requirements. Further, with this being a restart of a previously mined open pit, we anticipate an efficient permitting process," added Matthew Gili, President and Chief Operating Officer.
Mineral Resource Update
The Project's open pit mineral resource was estimated in four main zones from west to east: B, A, CX, and Mag pits. In each zone, the geology was modeled using structural domains and grade indicator shells to define the concentrated high-grade and surrounding low-grade zones. The global estimation was then constrained by an optimized pit shell for resource reporting. Whittle shell optimization model has been utilized to create resource pit shells in Table 2.
Table 2: Granite Creek Open Pit Mineral Resource Estimate Statement as of May 4, 2021
Measured and Indicated Mineral Resources | |||||
Class | Deposit | Tonnes | Au | Au | |
(Mt) | (g/t) | (Moz ) | |||
Measured | Pit B | 2.91 | 1.32 | 0.123 | |
Pit A | 0.56 | 1.07 | 0.019 | ||
CX | 10.89 | 1.30 | 0.455 | ||
Mag | 12.00 | 1.21 | 0.468 | ||
Total Measured | 26.36 | 1.26 | 1.066 | ||
Indicated | Pit B | 0.36 | 1.10 | 0.013 | |
Pit A | 0.69 | 0.80 | 0.018 | ||
CX | 2.97 | 1.25 | 0.120 | ||
Mag | 7.32 | 0.93 | 0.219 | ||
Total Indicated | 11.34 | 1.01 | 0.369 | ||
Measured | Pit B | 3.27 | 1.29 | 0.136 | |
Pit A | 1.25 | 0.92 | 0.037 | ||
CX | 13.86 | 1.29 | 0.575 | ||
Mag | 19.32 | 1.11 | 0.687 | ||
Total Measured & Indicated | 37.70 | 1.18 | 1.435 |
Inferred Mineral Resources | |||||
Class | Deposit | Tonnes | Au | Au | |
(000s) | (g/t) | (000s oz) | |||
Inferred | Pit B | 0.03 | 0.64 | 0.001 | |
Pit A | 0.21 | 0.59 | 0.004 | ||
CX | 1.35 | 1.16 | 0.050 | ||
Mag | 0.56 | 1.11 | 0.020 | ||
Total Inferred | 2.15 | 1.09 | 0.075 |
Notes to table above: I. The effective date of the mineral resources estimate is May 4, 2021. II. The qualified persons for the estimate are Terre Lane QP-MMSA and Hamid Samari QP-MMSA of GRE, Inc. III. Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant factors. Mineral resources are not ore reserves and are not demonstrably economically recoverable. IV. Mineral resources are reported at a 0.30 g/t cutoff, an assumed gold price of 2,040 $/tr. oz, using variable recovery, a slope angle of 41 degrees, V. An inferred mineral resource is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred mineral resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. It is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued exploration. VI. The reference point for mineral resources is in situ. |
Economic Analysis
The project economics shown in the PEA are favorable, providing positive NPV values at varying gold prices, capital costs, and operating costs. The Project's NPV and IRR in relation to fluctuations in the gold price are outlined in Table 3.
Table 3: Granite Creek Open Pit Gold Price Sensitivity After-tax Analysis
Gold Price ($/oz) | |||||||
NPV | |||||||
IRR (%) | 21 % | 26 % | 30 % | 39 % | 46 % | 50 % | 52 % |
Project Overview
Granite Creek Open Pit is a large open pit CIL gold development project. The Granite Creek property (the "Property") also includes the Granite Creek Underground Project, a fully permitted, constructed and operating mine currently in the production ramp up phase. The Property is located at the intersection of the highly prolific
Access to the Property is provided by a combination of paved interstate and state highways and well-maintained, unpaved private roads. The towns of
Between 1980 and 1999, approximately 987,000 ounces of gold was produced from various open pit mining operations on the site. The Granite Creek Open Pit is an expansion of the previously mined areas.
Geology and Mineralization
Mineralization at Granite Creek is
Conversely, mineralization is hosted in the Lower Comus marble, limestone, and siltstone in the CX and B pits. In the CX and B pits, mineralization is strongly structurally controlled, typically by inverted thrust faults and normal faults trending north to northeast. In the Mag pit, mineralization has a stronger stratigraphic control with mineralization along bedding in the footwall of the northwest trending Mag fault.
Mining and Processing
The PEA demonstrates an initial mine life of approximately 10 years with an annual gold production of approximately 130,000 ounces following production ramp up. The PEA represents a preliminary point-in-time estimate of the mine plan. The previous preliminary economic assessment released on Granite Creek in 2021, envisioned a predominately heap leach operation with a small-scale CIL plant for Granite Creek open pit. Further work and higher gold prices have demonstrated better economics by migrating to a full CIL scenario.
The Project's above ground mine plan will be accomplished using conventional open pit mining techniques with 10 to 12 haul trucks (133 tonne) and four loaders (nine cubic yard bucket). Mineralized material will be mined at a rate of 10,000 tonnes per day, assuming 350 days of mining a year, for a total of 3.5 million tonnes annually.
Waste rock would be placed in waste rock storage facilities and as pit backfill as the mining sequence allows. Pits were designed with overall 41-degree side wall slopes and 90-foot haul roads with a maximum of
The study envisions the construction of 10,000 tonne per day CIL plant on-site. The process plant for Granite Creek was selected based on the material characteristics, in particular the presence of organic carbon ("TOC") and the associated cyanide leach performance. The variable organic carbon concentrations in the material make the use of conventional cyanide heap leaching less robust and require more strict ore control measures to divert high TOC materials to an alternative leach process. Given this, a CIL process was selected, CIL also showed a significant gold recovery advantage over heap leaching.
The Project's process design includes primary crushing via a large jaw crusher with an intermediate stockpile. The crushed material is fed to a sag and ball mill circuit consisting of a semi-autogenous ("SAG") mill in closed circuit with a ball mill. Pebble crushing has not been included at this stage. The target throughput is 10,000 tonnes per day at a
The CIL circuit employs simultaneous cyanide gold leaching and activated carbon gold adsorption with the carbon advancing countercurrent to the leach slurry. The presence of active carbon during the leaching mitigates the impact of gold adsorption by the organic carbon present in the material.
The loaded carbon is stripped of the gold in a modified Zadra elution circuit. Hot cyanide and sodium hydroxide solutions remove the gold from the carbon into a concentrated stream that reports to an electrowinning circuit. The electrowon gold is further thermally refined into doré bars prior to shipment.
A conventional tailings storage facility would be constructed near the CIL plant.
Capital Cost Summary
Mine construction capital and sustaining capital over LOM is estimated to total approximately
Granite Creek Open Pit is expected to generate an estimated
Table 4: Granite Creek Open Pit Capital Cost Estimates (excludes permitting and reclamation costs)
Mine Construction | Sustaining | |
($M) | ($M) | |
Capitalized Waste | ||
Construction Capital | ||
Sustaining Capital | ||
Contingency | ||
Total Capital Cost |
Operating Cost Summary
The PEA estimates cash costs(1) of
Table 5: Granite Creek Open Pit Total and Unit Operating Costs
Total Costs | Unit Cost | Cost per Ounce | |
($M) | ($/t ) | ($/oz Au) | |
Mining | |||
Processing | |||
G&A | |||
Refining, Royalties & Net Proceeds Tax | |||
Total Operating Cost/Cash Costs(1) | |||
Closure & Reclamation | |||
Sustaining Capital | |||
All-in Sustaining Costs(1) |
Permitting
The Project has the necessary permits for the ongoing small-scale underground mining operation.
In order to execute the project plan, additional state and federal permits are required. The Project will extend to non-patented mining claims and will require a permit under the National Environmental Policy Act ("NEPA") which is the regulation that requires an Environmental Impact Statement ("EIS"). The EIS requires significant effort to acquire; however, i-80 Gold currently expects to successfully permit the Project in a reasonable time frame of three years.
State permits are required for air quality protection, groundwater protection, surface water protection, and water rights. The current PEA includes a timeline for acquiring these permits, and the costs associated with the permitting effort.
Water Management
The underground mine will abstract up to 3,000 gpm of dewatering water coming from the underground mine sumps and the dewatering wells required to dewater the mine. The MAG pit is currently flooded and must be dewatered. Many of the types of dewatering water contain elevated arsenic concentrations above Nevada Reference Values, as does much of
Closure
The site closure costs are estimated at
Next Steps to Feasibility Study
A feasibility study in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and Subpart 1300 of Regulation S-K ("S-K 1300") with an updated mineral resource estimate is expected to be completed in Q4 2025. Below is a summary of additional work to be conducted.
Metallurgical
- Improved geo-metallurgical analysis by increasing the range of materials tested to include grade (gold, silver, carbon and sulfur), spatial (elevation and strike), and geologic domains.
- Additional CIL testing to improve the gold extraction relationships.
- Comminution testing examining the SAG and ball mill work index.
- Infill the drill hole database with TOC and sulfur assays.
- Conduct arsenic and mercury assays on all samples employed for metallurgical testing.
Technical Disclosure and Qualified Persons
The PEA was prepared in accordance with NI 43-101. The PEA will be filed within 45 days of the date of this press release under the Company's issuer profile on SEDAR+ at www.sedarplus.ca. An Initial Assessment for the Granite Creek Open Pit Project ("S-K 1300 Report") was also prepared in accordance with S-K 1300 and Item 601 of the Regulation S-K and the S-K 1300 Report will be filed on EDGAR at www.sec.gov. Both reports will be available on the Company's website at www.i80gold.com. The mineral estimates and project economics are the same under the PEA and the S-K 1300 Report.
The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Terre Lane (SME No. 4053005 / MMSA No. 01407QP) of Global Resource Engineering ("GRE"), and Tyler Hill CPG., Vice President Geology for the Company, who are all qualified persons within the meaning of NI 43-101 and S-K 1300.
For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see the Company's Annual Information Form dated March 12, 2024 filed under the Company's profile on SEDAR+ at www.sedarplus.ca and filed with the Company's Form 40-F under the Company's profile on EDGAR at www.sec.gov. Further information about the PEA referenced in this news release, including information in respect of data verification, key assumptions, parameters, risks and other factors, will be contained in the PEA.
The PEA is preliminary in nature and includes an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources that are considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the results of the PEA will be realized. Mineral resources do not have demonstrated economic viability and are not mineral reserves.
Endnotes
- This is a non-IFRS/non-GAAP measure. Please see the section titled "Non-IFRS Performance Measures/Non-GAAP Financial Performance Measures" below.
- Cash flow and NPV are calculated as of the start of construction, which is anticipated to commence in early 2028, subject to obtaining the necessary permits by December 31, 2027, as anticipated.
- Turquoise Ridge Complex gold mineral resource estimate of approximately 20 million ounces (110 Mt at 5.42 g/t Au) as at December 31, 2023 based on publicly filed technical reports of Barrick Gold Corporation available on SEDAR+ at www.sedarplus.ca and www.barrick.com. No qualified person of the Company has independently verified any mineral resource information in respect of the Turquoise Ridge Complex contained in this news release and such information is not necessarily indicative of the mineralization on the property subject to such technical reports.
About i-80 Gold Corp.
i-80 Gold Corp. is a
Forward-Looking Information
Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws, including but not limited to, statements regarding the updated results of the PEA on the Project, such as future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs, timing for permitting and environmental assessments, timing, completion and results of feasibility studies, and the size and timing of phased development of the Project. Furthermore, forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by the Company as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. With respect to this specific forward-looking information concerning the development of the Project, the Company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of gold, silver and other commodities; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) natural disasters and/or accidents; * currency fluctuations; (xi) changes in regulations; (xii) the compliance by and/or key suppliers with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies, including permitting and environmental assessments; (xv) the ability to raise sufficient capital to develop such projects; (xiv) changes in project scope or design; and (xv) political factors.
Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the Company's current expectations regarding future events, performance and results and speak only as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.
This release also contains references to estimates of mineral resources. The estimation of mineral resources is inherently uncertain and involves subjective judgments about many relevant factors. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the Project, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that may ultimately prove to be inaccurate. Mineral resource estimates may have to be re-estimated based on: (i) fluctuations in commodities prices; (ii) results of drilling, (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the date of any estimates; and (vi) the possible failure to receive required permits, approvals and licenses or changes to existing mining licenses.
Forward-looking statements and information involve significant known and unknown risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results expressed or implied by such forward-looking statements or information, including, but not limited to: the Company's ability to finance the development of its mineral properties; assumptions and discount rates being appropriately applied to the PEA and S-K 1300 Report, uncertainty as to whether there will ever be production at the Company's mineral exploration and development properties; risks related to the Company's ability to commence production at the Project and generate material revenues or obtain adequate financing for its planned exploration and development activities; uncertainties relating to the assumptions underlying resource and reserve estimates; mining and development risks, including risks related to infrastructure, accidents, equipment breakdowns, labour disputes, bad weather, non-compliance with environmental and permit requirements or other unanticipated difficulties with or interruptions in development, construction or production; the geology, grade and continuity of the Company's mineral deposits; the uncertainties involving success of exploration, development and mining activities; permitting timelines; government regulation of mining operations; environmental risks; unanticipated reclamation expenses; prices for energy inputs, labour, materials, supplies and services; uncertainties involved in the interpretation of drilling results and geological tests and the estimation of reserves and resources; unexpected cost increases in estimated capital and operating costs; the need to obtain permits and government approvals; material adverse changes, unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations. For a more detailed discussion of such risks and other factors that could cause actual results to differ materially from those expressed or implied by such forward-looking statements, refer to i-80 Gold's filings with Canadian securities regulators, including the most recent Annual Information Form, available on SEDAR+ at www.sedarplus.ca.
Non-IFRS/Non-GAAP Financial Performance Measures
The Company has included certain terms or performance measures in this news release that commonly used in the gold mining industry that are not defined under International Financial Reporting Standards ("IFRS") or United States Generally Accepted Accounting Principles ("US GAAP"). This includes: all-in sustaining costs per ounce and cash cost per ounce. Non-IFRS/Non-GAAP financial performance measures do not have any standardized meaning prescribed under IFRS or US GAAP, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS US GAAP and should be read in conjunction with the Company's financial statements. Because the Company has provided these measures on a forward-looking basis, it is unable to present a quantitative reconciliation to the most directly comparable financial measure calculated and presented in accordance with IFRS or US GAAP without unreasonable efforts. This is due to the inherent difficulty of forecasting the timing or amount of various reconciling items that would impact the most directly comparable forward-looking IFRS or US GAAP measure that have not yet occurred, are outside of the Company's control and/or cannot be reasonably predicted.
Definitions
"All-in sustaining costs" is a non-IFRS or US GAAP financial measure calculated based on guidance published by the World Gold Council ("WGC"). The WGC is a market development organization for the gold industry and is an association whose membership comprises leading gold mining companies. Although the WGC is not a mining industry regulatory organization, it worked closely with its member companies to develop these metrics. Adoption of the all-in sustaining cost metric is voluntary and not necessarily standard, and therefore, this measure presented by the Company may not be comparable to similar measures presented by other issuers. The Company believes that the all-in sustaining cost measure complements existing measures and ratios reported by the Company. All-in sustaining cost includes both operating and capital costs required to sustain gold production on an ongoing basis. Sustaining operating costs represent expenditures expected to be incurred at the Project that are considered necessary to maintain production. Sustaining capital represents expected capital expenditures comprising mine development costs, including capitalized waste, and ongoing replacement of mine equipment and other capital facilities, and does not include expected capital expenditures for major growth projects or enhancement capital for significant infrastructure improvements.
"Cash cost per gold ounce" is a common financial performance measure in the gold mining industry but has no standard meaning under IFRS or US GAAP. The Company believes that, in addition to conventional measures prepared in accordance with IFRS or US GAAP, certain investors use this information to evaluate the Company's performance and ability to generate cash flow. Cash cost figures are calculated in accordance with a standard developed by The Gold Institute. The Gold Institute ceased operations in 2002, but the standard is considered the accepted standard of reporting cash cost of production in North America. Adoption of the standard is voluntary, and the cost measures presented may not be comparable to other similarly titled measures of other companies.
For a more detailed breakdown on how these measures were calculated, please see the table below:
Total Costs | Unit Cost | Cost per Ounce | |
($M) | ($/t ) | ($/oz Au) | |
Mining | |||
Processing | |||
G&A | |||
Refining, Royalties & Net Proceeds Tax | |||
Total Operating Cost/Cash Costs(1) | |||
Closure & Reclamation | |||
Sustaining Capital | |||
All-in Sustaining Costs(1) |
APPENDIX
Granite Creek Open Pit Project Detailed Cash Flow Model
Granite Creek Open Pit | UNITS | TOTAL / LOM | 2028E | 2029E | 2030E | 2031E | 2032E | 2033E | 2034E | 2035E | 2036E | 2037E | 2038E | 2039E | 2040E | 2041E | ||||||||||||||||
MINING | ||||||||||||||||||||||||||||||||
Mine Life | Years | ~10 | ||||||||||||||||||||||||||||||
Mineralized Material Mined | k tonnes | 34,854.5 | 291 | 4,511 | 4,110 | 4,091 | 3,739 | 1,531 | 4,954 | 4,333 | 5,483 | 1,812 | - | - | ||||||||||||||||||
Expensed Waste Moved | k tonnes | 287,352.9 | - | 25,936 | 47,957 | 36,314 | 35,287 | 31,497 | 50,415 | 33,147 | 24,739 | 2,061 | - | - | ||||||||||||||||||
k tonnes | ||||||||||||||||||||||||||||||||
Total Moved | k tonnes | 322,207 | - | 291 | 30,447 | 52,066 | 40,405 | 39,026 | 33,028 | 55,369 | 37,480 | 30,222 | 3,873 | - | - | |||||||||||||||||
Strip Ratio | (waste:mineralized material) | 8.2:1 | 0 | 5.7:1 | 11.7:1 | 8.9:1 | 9.4:1 | 20.6:1 | 10.2:1 | 7.6:1 | 4.5:1 | 1.1:1 | ||||||||||||||||||||
Strip Ratio (Including Capitalized Strip.) | (waste:mineralized material) | 8.9:1 | 44.4:1 | 7.8:1 | 11.7:1 | 8.9:1 | 9.4:1 | 20.6:1 | 10.2:1 | 7.6:1 | 4.5:1 | 1.1:1 | ||||||||||||||||||||
Daily Mining Rate | tpd | 10,291.7 | - | 798 | 12,360 | 11,259 | 11,207 | 10,244 | 4,195 | 13,572 | 11,871 | 15,022 | 4,963 | - | - | |||||||||||||||||
Capitalized Mining | k tonnes | 17,637.7 | 12,937 | 4,701 | - | - | - | - | - | - | - | - | - | - | ||||||||||||||||||
PROCESSING | ||||||||||||||||||||||||||||||||
Total Material for Processing | k tonnes | 34,854 | - | - | 2,188 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 1,167 | |||||||||||||||||
Au Average Grade | g/t Au | 1.25 | - | - | 1.87 | 1.28 | 1.27 | 1.03 | 0.88 | 1.48 | 1.75 | 1.64 | 1.21 | 0.53 | 0.53 | |||||||||||||||||
Contained Gold | '000 oz Au | 1,397 | - | - | 131.7 | 144.5 | 142.8 | 115.6 | 99.0 | 166.6 | 196.9 | 184.3 | 136.2 | 59.8 | 19.9 | |||||||||||||||||
CIL Processing | ||||||||||||||||||||||||||||||||
Total Tonnes Processed | k tonnes | 34,854 | 2,188 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 3,500 | 1,167 | |||||||||||||||||||
Gold Grade | g/t Au | 1.25 | - | - | 1.87 | 1.28 | 1.27 | 1.03 | 0.88 | 1.48 | 1.75 | 1.64 | 1.21 | 0.53 | 0.53 | |||||||||||||||||
Silver Grade | g/t Au | 0.00 | - | - | - | - | - | - | - | - | - | - | - | - | - | |||||||||||||||||
Contained Gold | '000 oz Au | 1,397 | 131.7 | 144.5 | 142.8 | 115.6 | 99.0 | 166.6 | 196.9 | 184.3 | 136.2 | 59.8 | 19.9 | |||||||||||||||||||
Recovered Gold | '000 oz Au | 1,210 | 113.8 | 125.8 | 123.8 | 100.2 | 85.6 | 145.4 | 170.7 | 159.5 | 117.6 | 51.0 | 17.0 | |||||||||||||||||||
Recovered Silver | '000 oz Ag | - | ||||||||||||||||||||||||||||||
Total Tonnes Processed | k tonnes | 34,854 | - | - | 2,187.5 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 3,500.0 | 1,167.0 | |||||||||||||||||
Total Gold Production | '000 oz Au | 1,210 | - | - | 113.8 | 125.8 | 123.8 | 100.2 | 85.6 | 145.4 | 170.7 | 159.5 | 117.6 | 51.0 | 17.0 | |||||||||||||||||
REVENUE | ||||||||||||||||||||||||||||||||
Gold Price | US$/oz Au | |||||||||||||||||||||||||||||||
Silver Price | US$/oz Ag | |||||||||||||||||||||||||||||||
Gold Revenues | US$M | - | - | |||||||||||||||||||||||||||||
Silver Revenue | - | - | - | - | - | - | - | - | - | - | - | - | - | |||||||||||||||||||
Total Revenue | - | - | ||||||||||||||||||||||||||||||
OPERATING COSTS | ||||||||||||||||||||||||||||||||
Mining Costs (all) | US$M | - | - | |||||||||||||||||||||||||||||
CIL Processing | US$M | - | ||||||||||||||||||||||||||||||
G&A | US$M | |||||||||||||||||||||||||||||||
Total Operating Cost | US$M | - | - | |||||||||||||||||||||||||||||
Refining & Sales | US$M | - | ||||||||||||||||||||||||||||||
Royalties & State Taxes | US$M | |||||||||||||||||||||||||||||||
Mining costs | US$/t mined | - | - | - | - | |||||||||||||||||||||||||||
Mining Costs | US$/t mined | - | - | - | - | |||||||||||||||||||||||||||
Mining costs | US$/t mined | - | - | - | - | |||||||||||||||||||||||||||
Processing | US$/t process. | - | - | |||||||||||||||||||||||||||||
G&A | US$/t process. | - | - | |||||||||||||||||||||||||||||
Total | US$/t process. | - | - | |||||||||||||||||||||||||||||
CAPITAL EXPENDITURES | ||||||||||||||||||||||||||||||||
Contingent. Payments | US$M | |||||||||||||||||||||||||||||||
Permitting | US$M | |||||||||||||||||||||||||||||||
Capitalized Stripping | US$M | - | - | - | - | - | - | - | - | - | - | - | ||||||||||||||||||||
Initial & Construction Capital | US$M | - | - | - | - | - | - | - | - | - | - | - | - | |||||||||||||||||||
Sustaining Capital | US$M | - | - | |||||||||||||||||||||||||||||
Total Capital | US$M | - | ||||||||||||||||||||||||||||||
Reclamation & Surety | US$M | - | - | - | - | - | - | - | - | - | - | - | - | |||||||||||||||||||
CASH COSTS & AISC | ||||||||||||||||||||||||||||||||
Total Cash Costs (Inc. Royalty) | US$/oz | - | - | - | ||||||||||||||||||||||||||||
All-in Sustaining Costs(1) | US$/oz | - | - | - | ||||||||||||||||||||||||||||
CASH FLOW ANALYSIS | ||||||||||||||||||||||||||||||||
Revenue | US$M | - | - | - | ||||||||||||||||||||||||||||
Operating Costs Gold & Royalties | US$M | ( | - | - | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | - | ||||||||||||||||
Depreciation | US$M | ( | - | - | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | - | ||||||||||||||||
Net Operating Income (Pre-Tax) | US$M | - | - | - | ||||||||||||||||||||||||||||
Income Taxes & | US$M | ( | - | - | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | - | ||||||||||||||||
Net Income | US$M | - | - | - | ||||||||||||||||||||||||||||
Depreciation & Depletion | US$M | - | ||||||||||||||||||||||||||||||
Reclamation | US$M | ( | - | - | - | - | - | - | - | - | - | - | - | ( | ( | |||||||||||||||||
Operating Cash Flow | US$M | - | - | ( | ||||||||||||||||||||||||||||
Capital Expenditures | US$M | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | ( | - | ||||||||||||||||
NET CASH FLOW | US$M | ( | ( | ( | ||||||||||||||||||||||||||||
PROJECT ECONOMICS (as of Jan. 1 2028) | ||||||||||||||||||||||||||||||||
After-tax NPV | US$M | |||||||||||||||||||||||||||||||
30 % | ||||||||||||||||||||||||||||||||
Notes to table above: | ||||||||||||||||||||||||||||||||
(1) AISC annual calculations are on a cash basis rather than on an accrual basis. As such, the weighted average of the annual AISC amounts will not agree to the life of mine AISC. | ||||||||||||||||||||||||||||||||
(2) Includes a |
View original content to download multimedia:https://www.prnewswire.com/news-releases/i-80-gold-announces-positive-preliminary-economic-assessment-on-the-granite-creek-open-pit-project-nevada-after-tax-npv5-of-421-million-with-an-after-tax-irr-of-30-at-us2-175oz-au-302394446.html
SOURCE i-80 Gold Corp