Hudbay Announces Robust Preliminary Economic Assessment for the Copper World Complex
Hudbay announced the results of a preliminary economic assessment (PEA) for its Copper World Complex in Arizona. The two-phase mine plan has an after-tax net present value (NPV) of $1.296 billion at a copper price of $3.50 per pound, yielding an 18% internal rate of return (IRR). Phase I, with a 16-year mine life, projects annual copper production of 86,000 tonnes at cash costs of $1.15 per pound, while Phase II extends mine life to 44 years with production increasing to 101,000 tonnes annually. The project is designed to reduce emissions and support U.S. copper supply.
- Project NPV of $1.296 billion at $3.50/lb copper.
- Phase I offers standalone operation with an after-tax NPV of $741 million.
- Phase II expected to generate an IRR of 49%.
- Project designed to reduce carbon footprint with onshore copper production.
- Over $3.3 billion in U.S. taxes anticipated over 44 years, creating 500 direct jobs.
- Environmental litigation concerns from project opponents regarding Clean Water Act compliance.
- Dependency on federal permitting for Phase II could delay project progress.
- Two-phase mine plan has an after-tax net present value (
10% ) of$1,296 million and generates an18% internal rate of return at$3.50 per pound copper1 - Phase I reflects a standalone operation on private land and patented mining claims over a 16-year mine life with average annual copper production of approximately 86,000 tonnesi at cash costs and sustaining cash costs of
$1.15 and$1.44 per pound of copperii, respectively, generating an after-tax net present value (10% ) of$741 million and an internal rate of return of17% 1 - Phase I of the Copper World Complex includes a 60,000 ton per day sulfide concentrator, a 20,000 ton per day oxide heap leach, an SX/EW facility and a concentrate leach facility with an initial capital cost estimate of approximately
$1.9 billion . The concentrator is intended to expand to 90,000 tons per day in Phase II - The processing facilities are planned to have annual production capacity of 100,000 tonnes of copper cathode during Phase I and 125,000 tonnes of copper cathode during Phase II, and have been designed to reduce the project's carbon footprint to produce “Made in America” copper
- Supports U.S. copper supply through onshore production of copper cathode expected to be sold entirely to domestic customers and eliminates GHG and sulfur emissions associated with overseas shipping and processing
- Phase II expands mining activities onto federal land and extends the mine life to 44 years with average annual copper production of approximately 101,000 tonnesi at cash costs and sustaining cash costs of
$1.11 and$1.42 per pound of copperii, respectively. Phase II provides additional optionality with an after-tax net present value (10% ) of$555 million and an internal rate of return of49% (and a projected after-tax net present value (10% ) of$2,806 million at the time of Phase II sanctioning)1 - Significant increase in copper contained in all mineral resource categories
- Hudbay is evaluating several opportunities to optimize the project, including the potential to expand Phase I beyond 16 years with additions to the company’s private land package for tailings and waste rock storage and the potential to accelerate Phase II if federal permits are received earlier than as outlined in the PEA
TORONTO, June 08, 2022 (GLOBE NEWSWIRE) -- Hudbay Minerals Inc. (“Hudbay” or the “company”) (TSX, NYSE: HBM) today announced the results of the preliminary economic assessment (“PEA”) of its
1 The valuation metrics presented in this news release are based on a preliminary economic assessment that includes an economic analysis of the potential viability of mineral resources. Mineral resources that are not mineral reserves do not have demonstrated economic viability. This preliminary economic assessment is preliminary in nature, includes inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty the preliminary economic assessment will be realized. See “Qualified Person and NI 43-101” below.
“The Copper World Complex PEA represents the next leg of copper growth at Hudbay, generating significant value for all of our stakeholders with robust project economics and many benefits for the community and local economy in Arizona,” said Peter Kukielski, Hudbay’s President and Chief Executive Officer. “We have been successfully executing an alternative Arizona strategy since 2019 to deliver this attractive project, which is significantly de-risked and has the potential to nearly double our annual copper production while maintaining Hudbay’s first quartile cash cost positioning. Phase I represents an attractive standalone operation on our private land and Phase II provides significant long-term growth potential in this prolific district. Through applying our core competencies of exploration, mine planning and project development, the Copper World Complex is expected to be the next major copper operation in the United States, delivering the copper needed to meet domestic electrification and decarbonization supply chain needs.”
Successfully Executing an Alternative Strategy
Hudbay has been evaluating alternative options to unlock value from its Arizona mineral assets since the July 2019 ruling from the U.S. District Court to vacate the final record of decision (“FROD”) issued by the U.S. Forest Service relating to its Rosemont copper deposit. The FROD was based upon a standalone development plan for the Rosemont deposit utilizing federal land as set forth in Hudbay’s 2017 feasibility study and technical report (the “2017 Feasibility Study”).
Discovering New Mineralization on Patented Mining Claims
In the fall of 2019, the company began pursuing a private land development plan, including exploring nearby patented mining claims in the historic Helvetia mining district. The company initiated a drill program in 2020 to confirm historical drilling in this past-producing region, and the drill program was further expanded throughout 2021 after continuing to receive encouraging results. Four deposits were discovered in early 2021 with oxide and sulfide mineralization occurring at shallow depths on Hudbay’s wholly-owned patented mining claims. By September 2021, the exploration program had identified seven mineral deposits (referred to at the time as the “Copper World deposits”) over a seven-kilometre strike area, as shown in Figure 1. An initial mineral resource estimate was declared at the Copper World deposits in December 2021, which was larger and at a higher level of geological confidence than expected.
Expanding Private Land Package
Hudbay has been acquiring additional private land in the area to support an operation entirely on private land. The company now holds approximately 4,500 acres of private land and patented mining claims, which are enough to support the first 16 years of production at the Copper World Complex. Please refer to Figure 2 for a map of the company’s private land package.
Unlocking District Potential
Following the recent exploration success on patented mining claims and ongoing litigation uncertainty regarding the project design set forth in the 2017 Feasibility Study, Hudbay began to evaluate alternative design options to unlock value within this prospective district. This included remodeling the 2017 mineral resources, incorporating the new mineral resources from successful exploration results and completing new metallurgical testing work, which led to a comprehensive review of the mine plan, process plant design, tailings deposition strategies and permitting requirements for the new project.
Advancing State-Level Permitting
In June 2021, Hudbay initiated the state-level permitting process for the project with an application for its Mined Land Reclamation Plan (“MLRP”), which was subsequently approved by the Arizona State Mine Inspector in October 2021. The MLRP approval included a requirement for reclamation cost bonding prior to initiating work on the company’s private lands and represented the first step in the permitting process for a private land operation.
An aquifer protection permit and air quality permit are the remaining key state-level permits required for a private land operation, which, along with other minor permits, are expected to be advanced in the second half of 2022. Hudbay previously received aquifer protection and air quality permits for the 2017 design of the Rosemont project and these permits have been successfully upheld through litigation.
Hudbay does not believe any federal permits are required for Phase I of the mine plan for the Copper World Complex (see “Simplified Permitting Process” below).
2022 PEA Summary
The Copper World Complex PEA contemplates a two-phased mine plan with the first phase reflecting a standalone operation with processing infrastructure on Hudbay’s private land and mining occurring on patented mining claims. Phase I is expected to require only state and local permits and reflects a 16-year mine life. Phase II extends the mine life to 44 years through an expansion onto federal land to mine the entire deposits. Phase II would be subject to the federal permitting process.
Phase I contemplates average annual copper production of up to 100,000 tonnesi over a 16-year mine life, including approximately 86,000 tonnesi of copper from mined resources at average cash costs and sustaining cash costs of
A summary of key valuation, production and cost details from the PEA can be found below. For further details, including operating and cash flow metrics provided on an annual basis, please refer to Exhibit 1 at the end of this news release. For further details regarding the preliminary nature of the PEA and its limitations, please refer to “Qualified Person and NI 43-101” below.
Summary of Key Metrics (at | Unit | Phase I | Phase II | LOM |
Valuation Metrics (Unlevered)1 | ||||
Net present value @ | $ millions | |||
Net present value @ | $ millions | |||
Internal rate of return (after-tax) | % | |||
Payback period | # years | 5.3 | 1.7 | - |
EBITDA (annual avg.)2 | $ millions | |||
Project Metrics | ||||
Growth capital | $ millions | |||
Construction length | # years | 3.0 | 2.0 | - |
Operating Metrics | ||||
Mine life | # years | 16.0 | 28.0 | 44.0 |
Copper cathode production – mined resources3 | 000 tonnes | 86.4 | 101.3 | 95.9 |
Copper cathode production – total3 | 000 tonnes | 98.7 | 123.3 | 114.3 |
Copper recovery – mill to cathode | % | 77.3 | 80.1 | 79.2 |
Copper recovery – leach to cathode | % | 59.0 | 58.7 | 58.9 |
Sustaining capital (annual avg.) | $ millions | |||
Cash cost4 | $/lb Cu | |||
Sustaining cash cost4 | $/lb Cu |
Note: “LOM” refers to life-of-mine total or average.
1 Calculated assuming the following commodity prices: copper price of
2 EBITDA is a non-IFRS financial performance measure with no standardized definition under IFRS. For further information, please refer to the company's most recent Management's Discussion and Analysis for the three months ended March 31, 2022.
3 The mine plan assumes external concentrate is sourced in years when spare capacity exists at the SX/EW facility in order to maximize the full utilization of the facility. Copper cathode production from mined resources excludes the production from external concentrate. Average annual copper cathode production from external concentrates is approximately 12,000 tonnes in Phase I and 22,000 tonnes in Phase II. There remains the potential to replace external copper concentrate with additional internal feed.
4 Cash cost and sustaining cash cost, net of by-product credits, per pound of copper produced from internally sourced feed and excludes the cost of purchasing external copper concentrate, which may vary in price or potentially be replaced with additional internal feed. By-product credits calculated using the following commodity prices: molybdenum price of
Cu Price Sensitivity | Unit | |||||
Phase I Valuation Metrics | ||||||
Net present value1 @ | $ millions | $1,097 | ||||
Net present value1 @ | $ millions | $741 | ||||
Internal rate of return1 | % | 17% | ||||
Payback period | # years | 6.0 | 5.3 | 4.7 | 4.3 | 3.9 |
EBITDA (annual avg.)2 | $ millions | $438 | ||||
LOM Valuation Metrics | ||||||
Net present value1 @ | $ millions | $2,044 | ||||
Net present value1 @ | $ millions | $1,296 | ||||
Internal rate of return1 | % | 18% | ||||
EBITDA (annual avg.) 2 | $ millions | $497 |
1 Net present value and internal rate of return are shown on an after-tax basis.
2 EBITDA is a non-IFRS financial performance measure with no standardized definition under IFRS. For further information, please refer to the company's most recent Management's Discussion and Analysis for the three months ended March 31, 2022.
Overview of Proposed Operation
The Copper World Complex is planned to be a traditional open pit shovel and truck operation with a copper sulfide mineral processing plant and an oxide leach processing facility producing copper cathode, molybdenum concentrate and silver doré.
The overall mining operation is expected to consist of four open pits in Phase I with two of the pits expanding onto federal land in Phase II, as shown in Figure 3. Phase I contemplates exploitation of the pits and use of associated infrastructure within a footprint that requires only state and local permits for its 16 years of operation, plus one year of pre-stripping. During this period, all waste and tailings will be disposed on, and leach pads will be located on, Hudbay’s private land. In Phase II, it is assumed that all necessary federal permits will be obtained in order to mine and deposit tailings and waste on unpatented mining claims.
A majority of the newly discovered deposits are intended to be mined in Phase I and these deposits have a lower strip ratio and would contribute approximately
The processing facilities and saleable mineral products are fundamentally different from what was contemplated in the 2017 Feasibility Study. The processing facilities for the Copper World Complex include an oxide leach and solvent extraction and electro-winning (“SX/EW”) facility, a sulfide concentrator, a concentrate leach facility and an acid plant. The capacity of the sulfide concentrator during Phase I is 60,000 tons per day while the tonnage of the run-of-mine leached material is 20,000 tons per day. In year 17, the sulfide throughput will increase to 90,000 tons per day for the duration of Phase II. The pregnant leach solution from the concentrate leach facility will be combined with the solution from the oxide leaching circuit and treated in the SX/EW facility to produce copper cathode. The concentrate leach facility will also produce sulfur which will be processed into sulfuric acid at the acid plant and then used on the oxide leach pads. When the sulfur production from the concentrate leach process is insufficient to support the sulfuric acid requirements of the project, sulfur will be purchased at local market price; conversely, when sulfuric acid production exceeds the operation’s leaching requirements, it will be sold.
The capacity of the contemplated processing facilities allows for the opportunity to process third party feed in certain years when the copper from resources mined may be lower due to grade variability. The PEA assumes third-party concentrate will be sourced in certain years to maximize the utilization of the SX/EW facility, which will have annual production capacity for 100,000 tonnes of copper cathode during Phase I and 125,000 tonnes of copper cathode during Phase II.
The PEA contemplates the construction of three tailings storage facilities for Phase I and an additional larger tailings facility for Phase II. Conventional tailings deposition is planned for Phase I. Dry stack tailings deposition is intended to occur in Phase II, as per the original design set forth in the 2017 Feasibility Study.
Total project capital costs are estimated to be
Reducing GHG Emissions, Supporting Domestic Copper Supply and Generating Significant Local Benefits
Global copper market fundamentals are expected to be strong with a structural deficit emerging in the medium term. Global mine production, and available smelter capacity, are expected to struggle to keep pace with metal demand boosted by the green energy revolution. The U.S. is expected to remain a net copper importer during this period and domestic supply will be required to help secure growing U.S. metal demand related to increased manufacturing capacity, infrastructure development, bolstering the country’s energy independence and domestic EV battery supply chain and production needs.
The “Made in America” copper cathode produced at the Copper World Complex is expected to be sold entirely to domestic U.S. customers, thereby reducing the operation’s total energy requirements, greenhouse gas (“GHG”) and sulfur (SO2) emissions by eliminating overseas shipping, smelting and refining activities relating to copper concentrate (please refer to Figure 5). The company estimates that the project will reduce total energy consumption by more than
The Copper World Complex is expected to generate significant benefits for the community and local economy in Arizona. Over the anticipated 44-year life of the operation, the company expects to contribute more than
Simplified Permitting Process
The permitting process for the Copper World Complex is expected to require state and local permits for Phase I and federal permits for Phase II. On May 23, 2022, the U.S. District Court for the District of Arizona issued a favourable ruling effectively stating that there is no obligation for the Army Corps of Engineers (“ACOE”) to include Phase I of the project as part of the NEPA federal review of the standalone Rosemont project design. Furthermore, on May 12, 2022, a decision from the 9th Circuit Court of Appeals clarified the permitting path for Phase II, and the company expects it will be able to pursue and obtain federal permits within the constraints imposed by the Court’s decision.
In April, two groups of project opponents provided separate notices of their intent to bring citizen suits against Copper World under the Clean Water Act. In each case, project opponents have alleged that the site contains jurisdictional waters of the U.S. and that a Section 404 Clean Water Act permit is needed to advance the project. The ACOE has never determined that there are jurisdictional waters of the U.S. at the Copper World Complex and Hudbay has independently concluded through its own scientific analysis that there are no such waters in the area.
Mineral Resource Estimate
The PEA and mine plan are based on a new resource model for the Copper World Complex, which incorporates a revised resource model for the East deposit (formerly known as Rosemont) with the addition of the Copper World deposits discovered in 2021. The resource model was constructed using the same methods Hudbay applied at Constancia and Mason. Based on this new model, including resource classification criteria calibrated on historical performance at Constancia and the control of grade over-smoothing in the previous 2017 resource model, contained copper in measured and indicated resources increased by
The current mineral resource estimates for the Copper World Complex (effective as of May 1, 2022) are summarized below and replace the prior estimates of mineral reserves and resources at the Rosemont and Copper World deposits set forth in the 2017 Feasibility Study and the December 2021 mineral resource statement, respectively.
Copper World Complex Mineral Resource Estimates1,2,3 | Tonnes (millions) | Cu Grade (%) | Soluble Cu Grade (%) | Mo Grade (g/t) | Ag Grade (g/t) | |
Flotation | Measured | 687 | 0.45 | 0.05 | 138 | 5.1 |
Indicated | 287 | 0.36 | 0.06 | 134 | 3.6 | |
Total Measured and Indicated | 973 | 0.42 | 0.05 | 137 | 4.6 | |
Inferred | 210 | 0.36 | 0.05 | 119 | 3.9 | |
Leach | Measured | 105 | 0.37 | 0.26 | - | - |
Indicated | 94 | 0.35 | 0.26 | - | - | |
Total Measured and Indicated | 200 | 0.36 | 0.26 | - | - | |
Inferred | 52 | 0.40 | 0.29 | - | - |
Note: totals may not add up correctly due to rounding.
1 Mineral resource estimates that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not include factors for mining recovery or dilution.
2 Mineral resource estimates constrained to a Lerch Grossman pit shell with a revenue factor of 1.0 using a copper price of
3 Using a
Copper World Complex Comparison of Mineral Resource Estimates1,2 | |||||||||
2017 | 2022 | % Change | |||||||
Tonnes (millions) | Cu (%) | Cu (000 tonnes) | Tonnes (millions) | Cu (%) | Cu (000 tonnes) | Tonnes (millions) | Cu (%) | Cu (000 tonnes) | |
Measured and Indicated | 1,147 | 0.36 | 4,129 | 1,173 | 0.41 | 4,829 | 2% | 14% | 17% |
Inferred | 75 | 0.30 | 224 | 262 | 0.37 | 957 | 252% | 22% | 328% |
Note: totals may not add up correctly due to rounding.
1 2017 mineral resource estimates are inclusive of mineral reserve estimates.
2 2022 mineral resource estimates include both flotation and leach material.
Project Optimization and Upside Opportunities
Recent technical and exploration work has identified many opportunities that may further enhance project economics, reduce environmental impacts, increase annual production and extend mine life.
- Expanding Private Land Phase I - Hudbay may acquire additional private land to increase the tailings and waste capacity and extend the Phase I mine life beyond 16 years.
- Earlier Receipt of Federal Permits for Phase II - Hudbay is optimistic that the company will be able to secure federal permits sooner than the conservative timelines assumed in the PEA, which will allow the mining of more tonnage at a higher grade earlier in the mine life.
- Green Opportunities – There are several emission reduction opportunities the company will evaluate with future feasibility studies, including the potential to source renewable energy from local providers at a nominal cost, the use of autonomous or electric haul trucks at the operation and various post-reclamation land uses such as domestic renewable energy production. Also, if Hudbay is able to secure additional private land to improve the tailings configuration, there is the potential to accelerate dry stack tailings deposition into Phase I, which would reduce water consumption.
- Additional Exploration Upside Potential – Continued exploration activities may result in further extension of economic mineralization, including bridging the gap to the north and south of the Bolsa deposit. In addition, 2021 geophysical surveys identified several new targets north and south of the West deposit (formerly known as the Copper World deposit). A large portion of Hudbay’s property in this prolific region has yet to be explored and provides the potential for further discoveries.
Next Steps – Advancing to Pre-feasibility Study
Hudbay continues early site works at the project, which commenced in April 2022 with initial grading and clearing activities. The company also continues to have seven drill rigs turning at site conducting infill drilling in support of additional feasibility studies.
Hudbay expects to advance a pre-feasibility study for Phase I of the Copper World Complex in the second half of 2022, which will focus on converting the remaining inferred mineral resources to measured and indicated and evaluating many of the project optimization and upside opportunities. The company has increased its 2022 spending guidance for Arizona by
During 2023, the company expects to complete a definitive feasibility study on Phase I of the Copper World Complex and receive all required state and local permits for Phase I. Hudbay expects to generate significant free cash flow over the next several years following the recent completion of its brownfield investment projects in Peru and Manitoba. In addition, Hudbay expects to evaluate a variety of financing options, including a potential minority joint venture partner, as part of a prudent financing strategy prior to a project sanction decision, which could be made as early as 2024.
Non-IFRS Financial Performance Measures
Cash cost and sustaining cash cost per pound of copper produced are shown because the company believes they help investors and management assess the performance of its operations, including the margin generated by the operations and the company. Unit operating costs are shown because these measures are used by the company as a key performance indicator to assess the performance of its mining and processing operations. EBITDA is shown to provide additional information about the cash generating potential in order to assess the company’s capacity to service and repay debt, carry out investments and cover working capital needs. These measures do not have a meaning prescribed by IFRS and are therefore unlikely to be comparable to similar measures presented by other issuers. These measures should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS and are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. For further details on these measures, please refer to page 39 of Hudbay’s management’s discussion and analysis for the three months ended March 31, 2022 available on SEDAR at www.sedar.com.
Qualified Person and NI 43-101
The scientific and technical information contained in this news release has been approved by Olivier Tavchandjian, P. Geo, Hudbay’s Vice-President, Exploration and Technical Services. Mr. Tavchandjian is a qualified person pursuant to Canadian Securities Administrators’ National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”).
This PEA is preliminary in nature, includes inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty the preliminary economic assessment will be realized. As a result of this PEA, the 2017 Feasibility Study in respect of the standalone Rosemont project, including the estimates of mineral reserves and mineral resources contained therein, is no longer current and should not be relied upon by investors.
With the completion of the PEA, the company has determined that the Copper World Complex is a material mineral project for purposes of NI 43-101 and expects to file a NI 43-101 technical report to support the disclosure in this news release in the next 45 days. The new technical report will be the current technical report in respect of all the mineral properties that form part of the Copper World Complex and shall supersede and replace the 2017 Feasibility Study.
Cautionary Note to United States Investors
This news release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of United States securities laws. Canadian reporting requirements for disclosure of mineral properties are governed NI 43-101.
For this reason, information contained in this news release in respect of the Copper World Complex may not be comparable to similar information made public by United States companies subject to the reporting and disclosure requirements under the United States federal securities laws and the rules and regulations thereunder. For further information on the differences between the disclosure requirements for mineral properties under the United States federal securities laws and NI 43-101, please refer to the company’s AIF, a copy of which has been filed under Hudbay’s profile on SEDAR at www.sedar.com and the company’s Form 40-F, a copy of which has been filed on EDGAR at www.edgar.com.
Cautionary Note Regarding Forward-Looking Information
This news release contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this news release, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as “plans”, “expects”, “budget”, “guidance”, “scheduled”, “estimates”, “forecasts”, “strategy”, “target”, “intends”, “objective”, “goal”, “understands”, “anticipates” and “believes” (and variations of these or similar words) and statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” “occur” or “be achieved” or “will be taken” (and variations of these or similar expressions). All of the forward-looking information in this news release is qualified by this cautionary note.
Forward-looking information includes, but is not limited to, the results of the PEA, including the production, operating cost, capital cost and cash cost estimates, the projected valuation metrics and rates of return, the cash flow and EBITDA projections, as well as the anticipated permitting requirements and project design, including processing and tailings facilities, metal recoveries, mine life and production rates for the project, the potential to further enhance the economics of the project and optimize the design, the possibility of extending the life of the first production phase, the implications of the recent court decisions in respect of the standalone Rosemont project design, the potential to obtain federal permits for the second phase earlier than planned and the costs and plans for future pre-feasibility and feasibility studies on the Copper World Complex as well as potential timelines for obtaining the required permits and financing and sanctioning the first phase of the project. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by us at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.
The material factors or assumptions that Hudbay identified and were applied by the company in drawing conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to:
- obtaining all required permits to develop the Copper World Complex;
- no delays or disruption due to litigation challenging the permitting requirements for the Copper World Complex and no significant unanticipated litigation;
- the success of exploration and development activities at the Copper World Complex;
- the accuracy of geological, mining and metallurgical estimates;
- anticipated metals prices and the costs of production;
- the supply and demand for metals Hudbay produces;
- the supply and availability of all forms of energy and fuels at reasonable prices;
- no significant unanticipated operational or technical difficulties;
- the availability of additional financing, if needed;
- the availability of personnel for the company’s exploration, development and operational projects and ongoing employee relations;
- maintaining good relations with the communities in which the company operates, including the neighbouring communities and local governments in Arizona;
- no significant unanticipated challenges with stakeholders at the Copper World Complex;
- no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters;
- no contests over title to Hudbay’s properties, including as a result of rights or claimed rights of Indigenous peoples or challenges to the validity of its unpatented mining claims;
- an upfront stream deposit of
$230 million will be paid by Wheaton Precious Metals at the commencement of construction; - no offtake commitments in respect of production from the Copper World Complex;
- certain tax matters, including, but not limited to the mining tax regime in Arizona; and
- no significant and continuing adverse changes in general economic conditions or conditions in the financial markets (including commodity prices and foreign exchange rates).
The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks associated with COVID-19 and its effect on the company’s operations, financial condition, projects and prospects, risks generally associated with the mining industry, such as economic factors (including future commodity prices, currency fluctuations, energy and consumable prices, supply chain constraints and general cost escalation in the current inflationary environment), risks related to ongoing and potential litigation processes and other legal challenges that could affect the permitting timeline for the Copper World Complex, risks related to changes in government and government policy, risks related to changes in law, risks in respect of community relations, risks related to contracts that were entered into in respect of the Rosemont mine project, uncertainties related to the geology, continuity, grade and estimates of mineral reserves and resources, and the potential for variations in grade and recovery rates, as well as the risks discussed under the heading “Risk Factors” in the company’s AIF.
Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. The company does not assume any obligation to update or revise any forward-looking information after the date of this news release or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law.
About Hudbay
Hudbay (TSX, NYSE: HBM) is a diversified mining company primarily producing copper concentrate (containing copper, gold and silver), zinc metal and silver/gold doré. Directly and through its subsidiaries, Hudbay owns three polymetallic mines, four ore concentrators and a zinc production facility in northern Manitoba and Saskatchewan (Canada) and Cusco (Peru), and copper projects in Arizona and Nevada (United States). The company’s growth strategy is focused on the exploration, development, operation and optimization of properties it already controls, as well as other mineral assets it may acquire that fit its strategic criteria. Hudbay’s mission is to create sustainable value through the acquisition, development and operation of high-quality, long-life deposits with exploration potential in jurisdictions that support responsible mining, and to see the regions and communities in which the company operates benefit from its presence. The company is governed by the Canada Business Corporations Act and its shares are listed under the symbol "HBM" on the Toronto Stock Exchange, New York Stock Exchange and Bolsa de Valores de Lima. Further information about Hudbay can be found on www.hudbay.com.
For investor and media inquiries, please contact:
Candace Brûlé
Vice President, Investor Relations
(416) 814-4387
candace.brule@hudbay.com
Exhibit 1: Detailed Cash Flow Model and Key Assumptions
A detailed cash flow model containing annual production and cost information is shown below. Overall assumptions for commodity prices, marketing parameters, operating costs and capital costs are also provided.
Phase I: Physicals | Unit | Phase I | Y-03 | Y-02 | Y-01 | Y01 | Y02 | Y03 | Y04 | Y05 | Y06 | Y07 | Y08 | Y09 | Y10 | Y11 | Y12 | Y13 | Y14 | Y15 | Y16 |
Resources Mined | Pre-strip | ||||||||||||||||||||
Copper World deposits | Mt | 216.2 | 21.4 | 24.2 | 26.5 | 25.7 | 20.8 | 17.6 | 3.3 | 9.3 | 11.1 | 7.9 | 9.5 | 6.8 | 8.0 | 4.3 | 8.4 | 11.4 | 0.0 | ||
East deposit | Mt | 224.9 | 1.0 | 10.7 | 7.1 | 21.8 | 17.2 | 12.6 | 18.6 | 21.5 | 19.7 | 18.5 | 22.2 | 17.7 | 13.5 | 22.7 | |||||
Total resources mined | Mt | 441.1 | 21.4 | 24.2 | 26.5 | 26.7 | 31.6 | 24.8 | 25.1 | 26.5 | 23.7 | 26.5 | 31.0 | 26.5 | 26.5 | 26.5 | 26.1 | 24.9 | 22.7 | ||
Waste Mined | Pre-strip | ||||||||||||||||||||
Copper World deposits | Mt | 117.8 | 9.6 | 9.0 | 11.0 | 15.2 | 18.5 | 6.3 | 0.8 | 8.9 | 3.6 | 12.5 | 7.8 | 2.3 | 0.6 | 4.2 | 4.9 | 2.5 | |||
East deposit | Mt | 430.3 | 10.3 | 13.4 | 32.5 | 38.0 | 30.8 | 38.9 | 27.2 | 27.4 | 37.4 | 39.1 | 35.6 | 35.3 | 38.1 | 26.3 | |||||
Total waste mined | Mt | 548.1 | 9.6 | 9.0 | 11.0 | 25.6 | 31.9 | 38.7 | 38.8 | 39.7 | 42.5 | 39.7 | 35.2 | 39.7 | 39.7 | 39.7 | 40.1 | 40.7 | 26.3 | ||
Material Moved | Pre-strip | ||||||||||||||||||||
Rehandle | Mt | 13.8 | 2.2 | 1.7 | 1.4 | 2.8 | 0.4 | 1.5 | 3.8 | ||||||||||||
Total material moved | Mt | 1,003.0 | 31.0 | 33.2 | 37.5 | 52.2 | 65.7 | 65.2 | 65.3 | 66.2 | 69.0 | 66.2 | 66.2 | 66.2 | 66.2 | 66.2 | 66.6 | 67.2 | 52.8 | ||
Strip Ratio | Pre-strip | ||||||||||||||||||||
Copper World deposits | X:X | 0.54 | 0.45 | 0.37 | 0.41 | 0.59 | 0.89 | 0.35 | 0.23 | 0.97 | 0.33 | 1.60 | 0.82 | 0.34 | 0.08 | 0.97 | 0.58 | 0.22 | |||
East deposit | X:X | 1.91 | - | - | 10.77 | 1.25 | 4.55 | 1.75 | 1.79 | 3.09 | 1.46 | 1.27 | 1.90 | 2.11 | 1.60 | 1.99 | 2.82 | 1.16 | |||
Total strip ratio | X:X | 1.24 | 0.45 | 0.37 | 0.41 | 0.96 | 1.01 | 1.56 | 1.54 | 1.50 | 1.80 | 1.50 | 1.13 | 1.50 | 1.50 | 1.50 | 1.54 | 1.63 | 1.16 | ||
Mill | |||||||||||||||||||||
Tonnes milled | Mt | 315.6 | 17.5 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | 19,9 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | 19.9 | |||
Headgrade - Cu | % | 0.47 | 0.47 | 0.45 | 0.45 | 0.45 | 0.45 | 0.45 | 0.56 | 0.48 | 0.45 | 0.45 | 0.45 | 0.49 | 0.45 | 0.45 | 0.45 | 0.51 | |||
Headgrade – Ag | g/tonne | 5.13 | 3.82 | 3.84 | 4.08 | 3.10 | 4.26 | 7.02 | 7.36 | 5.94 | 4.44 | 4.52 | 6.39 | 7.27 | 4.30 | 6.00 | 4.42 | 5.17 | |||
Headgrade – Mo | % | 0.01 | 0.01 | 0.01 | 0.02 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | |||
Leach | |||||||||||||||||||||
Tonnes leached | Mt | 106.0 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | |||
Headgrade – CuSS | % | 0.29 | 0.24 | 0.24 | 0.20 | 0.26 | 0.36 | 0.19 | 0.32 | 0.32 | 0.30 | 0.33 | 0.24 | 0.35 | 0.38 | 0.39 | 0.35 | 0.23 | |||
Headgrade - Cu | % | 0.39 | 0.34 | 0.31 | 0.27 | 0.36 | 0.47 | 0.25 | 0.40 | 0.42 | 0.39 | 0.44 | 0.32 | 0.46 | 0.50 | 0.52 | 0.48 | 0.31 | |||
Purchased Cu Conc | |||||||||||||||||||||
Cu concentrate | Kt | 807.6 | 119.8 | 101.1 | - | 94.2 | 61.9 | 86.6 | - | 21.9 | 47.5 | 49.0 | 67.0 | 16.9 | 39.0 | 32.5 | 55.8 | 14.4 | |||
Grade – Cu | % | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | 25.0 | |||
Grade – Au | g/tonne | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | |||
Grade – Ag | g/tonne | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | |||
Recovery to Cu Cathode | |||||||||||||||||||||
From Mill | % | 77.3 | 71.2 | 70.5 | 72.9 | 70.9 | 74.2 | 77.4 | 80.3 | 79.9 | 80.6 | 79.2 | 79.4 | 79.9 | 79.2 | 80.4 | 76.1 | 82.0 | |||
From Leach | % | 59.0 | 55.9 | 59.9 | 59.5 | 56.8 | 59.7 | 58.5 | 62.2 | 60.6 | 60.2 | 59.0 | 58.8 | 59.8 | 59.0 | 58.3 | 57.6 | 58.5 | |||
From Purchased | % | 97.7 | 96.2 | 97.9 | 97.4 | 97.9 | 98.0 | 98.2 | 98.0 | 98.0 | 98.0 | 98.0 | 98.0 | 98.0 | 98.0 | 98.0 | |||||
Cu Cathode Produced | |||||||||||||||||||||
From Mill | Kt | 1,137.9 | 58.7 | 63.0 | 65.2 | 63.4 | 66.3 | 69.2 | 89.9 | 76.0 | 72.8 | 70.8 | 71.0 | 77.1 | 70.8 | 71.9 | 68.0 | 83.9 | |||
From Leach | Kt | 243.7 | 12.5 | 12.2 | 10.5 | 13.7 | 18.5 | 9.6 | 16.5 | 16.7 | 15.5 | 17.2 | 12.6 | 18.0 | 19.6 | 20.2 | 18.3 | 12.1 | |||
From Purchased | Kt | 197.2 | 28.8 | 24.7 | 22.9 | 15.1 | 21.2 | 5.4 | 11.6 | 12.0 | 16.4 | 4.1 | 9.6 | 8.0 | 13.7 | 3.5 | |||||
Total Cu cathode | Kt | 1,578.8 | 100.0 | 100.0 | 75.8 | 100.0 | 100.0 | 100.0 | 106.4 | 98.0 | 99.9 | 100.0 | 100.0 | 99.3 | 100.0 | 100.0 | 100.0 | 99.5 | |||
Mo Conc Produced | |||||||||||||||||||||
Mo Concentrate | Kt | 34.3 | 2.5 | 1.9 | 2.2 | 1.4 | 1.4 | 1.8 | 3.1 | 2.2 | 2.0 | 2.0 | 2.0 | 2.3 | 2.5 | 2.3 | 2.1 | 2.6 | |||
Grade - Mo | % | 51.13 | 54.33 | 50.39 | 43.17 | 48.04 | 45.92 | 51.67 | 53.88 | 51.87 | 50.71 | 50.47 | 51.24 | 51.98 | 52.39 | 52.34 | 51.61 | 52.96 | |||
Mo in concentrate | Kt | 17.6 | 1.3 | 1.0 | 1.0 | 0.7 | 0.6 | 0.9 | 1.6 | 1.2 | 1.0 | 1.0 | 1.0 | 1.2 | 1.3 | 1.2 | 1.1 | 1.4 | |||
Doré Produced | |||||||||||||||||||||
Ag in Doré - internal feed | 000 oz | 26,808 | 1,102 | 1,155 | 1,214 | 928 | 1,290 | 2,357 | 2,478 | 1,989 | 1,485 | 1,503 | 2,157 | 2,454 | 1,449 | 2,026 | 1,472 | 1,749 | |||
Ag in Doré - purchased conc | 000 oz | 349 | 28.8 | 24.7 | 22.9 | 15.1 | 21.2 | 5.4 | 11.6 | 12.0 | 16.4 | 4.1 | 9.6 | 8.0 | 13.7 | 3.5 | |||||
Au in Doré - purchased conc | 000 oz | 12 | 1.7 | 1.5 | 1.4 | 0.9 | 1.3 | 0.3 | 0.7 | 0.7 | 1.0 | 0.2 | 0.6 | 0.5 | 0.8 | 0.2 | |||||
Acid Plant | |||||||||||||||||||||
Purchased sulfur | Kt | 1,097.1 | 76.4 | 55.7 | 0.0 | 37.2 | 62.4 | 86.7 | 90.7 | 79.9 | 73.0 | 66.0 | 74.0 | 81.2 | 69.6 | 81.1 | 75.1 | 88.0 | |||
Excess acid produced | Kt | 1,570.9 | 118.4 | 59.4 | 77.2 | 115.2 | 60.4 | 152.3 | 25.8 | 52.1 | 118.8 | 97.5 | 161.5 | 111.1 | 85.6 | 83.1 | 111.2 | 141.2 | |||
Total Production | |||||||||||||||||||||
Cu Eq Produced | Kt | 1,739.9 | 109.6 | 107.5 | 83.7 | 107.0 | 106.7 | 112.5 | 119.1 | 108.3 | 109.5 | 109.4 | 112.4 | 112.2 | 109.9 | 111.1 | 109.7 | 111.4 |
Phase I: Unit Costs | Unit | Phase I | Y-03 | Y-02 | Y-01 | Y01 | Y02 | Y03 | Y04 | Y05 | Y06 | Y07 | Y08 | Y09 | Y10 | Y11 | Y12 | Y13 | Y14 | Y15 | Y16 | ||||||||||||||||||
Mining ($/t material moved excl. Pre-strip) | |||||||||||||||||||||||||||||||||||||||
Mining | $/tonne | 1.42 | 1.47 | 1.53 | 1.38 | 1.18 | 1.36 | 1.43 | 1.42 | 1.38 | 1.44 | 1.44 | 1.44 | 1.44 | 1.44 | 1.43 | 1.42 | 1.62 | |||||||||||||||||||||
Deferred stripping | $/tonne | (0.11 | ) | (0.01 | ) | (0.11 | ) | (0.29 | ) | (0.15 | ) | (0.42 | ) | - | (0.07 | ) | (0.26 | ) | (0.08 | ) | (0.09 | ) | (0.01 | ) | (0.02 | ) | (0.05 | ) | (0.01 | ) | (0.22 | ) | |||||||
Mining ex def stripping | $/tonne | 1.30 | 1.46 | 1.42 | 1.09 | 1.03 | 0.93 | 1.43 | 1.35 | 1.12 | 1.36 | 1.35 | 1.43 | 1.41 | 1.38 | 1.42 | 1.20 | 1.62 | |||||||||||||||||||||
Processing ($/t processed (tonnes milled + tonnes leached)) | |||||||||||||||||||||||||||||||||||||||
Sulfide flotation | $/tonne | 3.56 | 3.37 | 3.57 | 3.61 | 3.58 | 3.57 | 3.56 | 3.57 | 3.58 | 3.57 | 3.57 | 3.57 | 3.58 | 3.57 | 3.57 | 3.57 | 3.58 | |||||||||||||||||||||
Molybdenum flotation | $/tonne | 0.09 | 0.08 | 0.09 | 0.18 | 0.08 | 0.09 | 0.07 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | 0.09 | |||||||||||||||||||||
Leach Plant | $/tonne | 0.43 | 0.42 | 0.45 | 0.67 | 0.42 | 0.43 | 0.38 | 0.39 | 0.39 | 0.41 | 0.43 | 0.41 | 0.40 | 0.42 | 0.39 | 0.40 | 0.38 | |||||||||||||||||||||
Acid Plant | $/tonne | 0.70 | 0.83 | 0.59 | 0.14 | 0.44 | 0.65 | 0.84 | 0.88 | 0.79 | 0.73 | 0.68 | 0.74 | 0.80 | 0.71 | 0.80 | 0.75 | 0.85 | |||||||||||||||||||||
Acid Plant (electricity credit) | $/tonne | (0.22 | ) | (0.24 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | (0.22 | ) | ||||
Leach pad | $/tonne | 0.01 | 0.02 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | |||||||||||||||||||||
Doré plant | $/tonne | 0.13 | 0.10 | 0.09 | 0.10 | 0.08 | 0.10 | 0.18 | 0.18 | 0.15 | 0.12 | 0.12 | 0.16 | 0.18 | 0.11 | 0.15 | 0.11 | 0.13 | |||||||||||||||||||||
SX/EW | $/tonne | 0.86 | 0.94 | 0.87 | 0.70 | 0.86 | 0.86 | 0.86 | 0.91 | 0.85 | 0.86 | 0.86 | 0.86 | 0.86 | 0.86 | 0.86 | 0.86 | 0.86 | |||||||||||||||||||||
Total | $/tonne | 5.57 | 5.52 | 5.46 | 5.20 | 5.27 | 5.50 | 5.70 | 5.81 | 5.64 | 5.58 | 5.55 | 5.63 | 5.70 | 5.56 | 5.65 | 5.58 | 5.69 | |||||||||||||||||||||
Other Unit Costs ($/t processed (tonnes milled + tonnes leached)) | |||||||||||||||||||||||||||||||||||||||
Onsite G&A | $/tonne | 0.89 | 0.97 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 | |||||||||||||||||||||
Sustaining cash cost ($/lb Cu) | |||||||||||||||||||||||||||||||||||||||
Cash cost1 | $/lb | 1.15 | 1.14 | 1.27 | 1.30 | 1.30 | 1.21 | 1.34 | 1.03 | 1.11 | 1.18 | 1.18 | 1.19 | 1.06 | 1.09 | 1.09 | 1.07 | 0.97 | |||||||||||||||||||||
Sustaining cash cost1 | $/lb | 1.44 | 1.38 | 1.63 | 1.72 | 1.63 | 1.88 | 1.70 | 1.30 | 1.41 | 1.40 | 1.40 | 1.37 | 1.24 | 1.28 | 1.26 | 1.37 | 1.25 | |||||||||||||||||||||
Total cash cost2 | $/lb | 1.41 | 1.75 | 1.75 | 1.30 | 1.73 | 1.52 | 1.72 | 1.03 | 1.23 | 1.41 | 1.42 | 1.51 | 1.15 | 1.29 | 1.26 | 1.36 | 1.05 | |||||||||||||||||||||
Total sustaining cash cost2 | $/lb | 1.66 | 1.92 | 2.03 | 1.72 | 1.99 | 2.09 | 2.01 | 1.30 | 1.51 | 1.61 | 1.61 | 1.66 | 1.32 | 1.47 | 1.42 | 1.62 | 1.32 | |||||||||||||||||||||
1 Internal feed only; 2 Includes purchased concentrate |
Phase I: Cash Flows | Unit | Phase I | Y-03 | Y-02 | Y-01 | Y01 | Y02 | Y03 | Y04 | Y05 | Y06 | Y07 | Y08 | Y09 | Y10 | Y11 | Y12 | Y13 | Y14 | Y15 | Y16 |
Cash Flows | |||||||||||||||||||||
Gross rev – internal | $M | 11,475 | 606 | 620 | 626 | 635 | 686 | 666 | 877 | 761 | 732 | 728 | 706 | 794 | 751 | 763 | 718 | 806 | |||
Gross rev – purchased | $M | 1,552 | 227 | 195 | - | 180 | 119 | 167 | - | 42 | 92 | 94 | 129 | 33 | 75 | 63 | 108 | 28 | |||
TC/RC | $M | (75) | (6) | (5) | (5) | (3) | (3) | (3) | (7) | (5) | (4) | (5) | (4) | (5) | (6) | (5) | (5) | (6) | |||
Freight | $M | (43) | (2) | (2) | (2) | (2) | (2) | (4) | (4) | (3) | (2) | (2) | (3) | (4) | (2) | (3) | (2) | (3) | |||
Royalty | $M | (253) | (14) | (14) | (12) | (14) | (14) | (16) | (21) | (17) | (16) | (16) | (16) | (18) | (16) | (16) | (15) | (19) | |||
Opex - Mining | $M | (1,266) | (48) | (53) | (57) | (68) | (61) | (93) | (90) | (77) | (90) | (89) | (95) | (94) | (92) | (95) | (81) | (86) | |||
Opex - Processing | $M | (2,346) | (133) | (145) | (138) | (140) | (146) | (151) | (154) | (150) | (148) | (147) | (149) | (151) | (147) | (150) | (148) | (151) | |||
Opex - Purch Cu Conc | $M | (1,332) | (198) | (167) | - | (155) | (102) | (143) | - | (36) | (78) | (81) | (111) | (28) | (64) | (54) | (92) | (24) | |||
Opex - Onsite G&A | $M | (376) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | (24) | |||
Opex - Property tax | $M | (296) | (35) | (33) | (33) | (32) | (30) | (24) | (22) | (20) | (18) | (16) | (13) | (9) | (5) | (3) | (3) | (3) | |||
Opex - Surety bond fees | $M | (34) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) |
Closure Costs | $M | ||||||||||||||||||||
Tax - Federal income | $M | (494) | (3) | (2) | (26) | (34) | (51) | (51) | (48) | (64) | (60) | (63) | (48) | (46) | |||||||
Tax - State income | $M | (98) | - | (1) | (6) | (7) | (10) | (10) | (9) | (13) | (12) | (12) | (9) | (9) | |||||||
Tax - State severance | $M | (62) | (1) | (2) | (2) | (2) | (4) | (4) | (6) | (6) | (6) | (7) | (6) | (7) | (6) | (5) | |||||
Cash From Ops before WC | $M | 6,351 | (2) | (2) | (2) | 372 | 372 | 354 | 375 | 418 | 368 | 519 | 426 | 376 | 374 | 357 | 411 | 391 | 394 | 393 | 458 |
WC Changes – AR | $M | (91) | (91) | 2 | 21 | (21) | 1 | (3) | (4) | 8 | (2) | 0 | (2) | 1 | 0 | (0) | (0) | (1) | |||
WC Changes – AP | $M | 76 | 62 | 123 | (80) | (17) | 1 | (30) | 28 | 3 | 2 | (21) | 4 | 10 | (0) | 4 | (11) | 4 | (1) | 5 | (11) |
WC Changes - Stream | $M | 230 | 230 | ||||||||||||||||||
Cash from Operations | $M | 6,565 | 291 | 121 | (82) | 264 | 375 | 345 | 383 | 422 | 368 | 493 | 438 | 383 | 375 | 359 | 401 | 395 | 393 | 397 | 446 |
Growth – EPCM | $M | (1,177) | (239) | (635) | (303) | - | |||||||||||||||
Growth - Owners Costs | $M | (475) | (48) | (223) | (205) | - | |||||||||||||||
Growth - Contingency | $M | (265) | (51) | (149) | (64) | - | |||||||||||||||
Sustaining capital | $M | (531) | (24) | (45) | (44) | (35) | (85) | (48) | (39) | (26) | (21) | (21) | (17) | (19) | (19) | (19) | (28) | (42) | |||
Deferred stripping | $M | (111) | (0) | (4) | (15) | (10) | (28) | - | (5) | (18) | (5) | (6) | (1) | (2) | (4) | (1) | (15) | - | |||
Cash From Investing | $M | (2,559) | (338) | (1,007) | (572) | (24) | (49) | (59) | (45) | (112) | (48) | (43) | (44) | (26) | (27) | (18) | (21) | (23) | (20) | (43) | (42) |
Net Cash Flow | $M | 4,007 | (47) | (886) | (654) | 240 | 326 | 286 | 338 | 309 | 320 | 450 | 393 | 357 | 348 | 342 | 380 | 372 | 373 | 354 | 404 |
NPV @ | $M | 1,097 | |||||||||||||||||||
NPV @ | $M | 741 | |||||||||||||||||||
IRR | % | 17 | |||||||||||||||||||
PAYBACK | # years | 5.3 |
Phase II: Physicals | Unit | Phase II | LOM | Y15 | Y16 | Y17 | Y18 | Y19 | Y20 | Y21 | Y22 | Y23 | Y24 | Y25-29 | Y30-34 | Y35-39 | Y40-44 | Y45-49 |
Resources Mined | ||||||||||||||||||
Copper World deposits | Mt | 124.2 | 340.4 | 0.7 | 3.0 | 2.0 | 1.5 | 3.3 | 13.8 | 14.1 | 11.6 | 74.2 | 0.0 | |||||
East deposit | Mt | 783.2 | 1,008.1 | 29.1 | 33.4 | 28.6 | 37.6 | 35.6 | 23.6 | 22.3 | 24.8 | 109.2 | 158.4 | 151.3 | 129.4 | |||
Total resources mined | Mt | 907.4 | 1,348.5 | 29.8 | 36.4 | 30.5 | 39.1 | 38.8 | 37.3 | 36.4 | 36.4 | 183.4 | 158.4 | 151.3 | 129.4 | |||
Waste Mined | ||||||||||||||||||
Copper World deposits | Mt | 19.3 | 137.1 | 0.8 | 0.2 | 0.1 | 0.3 | 2.2 | 3.9 | 4.3 | 2.5 | 5.0 | ||||||
East deposit | Mt | 1,643.2 | 2,073.5 | 15.7 | 74.6 | 74.6 | 71.9 | 70.2 | 70.0 | 70.5 | 72.2 | 363.7 | 376.7 | 329.7 | 53.4 | |||
Total waste mined | Mt | 1,662.5 | 2,210.6 | 16.5 | 74.8 | 74.7 | 72.1 | 72.4 | 73.9 | 74.8 | 74.8 | 368.7 | 376.7 | 329.7 | 53.4 | |||
Material Moved | ||||||||||||||||||
Rehandle | Mt | 30.9 | 44.7 | 6.0 | 4.0 | 21.0 | ||||||||||||
Total material moved | Mt | 2,600.8 | 3,603.8 | 46.3 | 111.2 | 111.2 | 111.2 | 111.2 | 111.2 | 111.2 | 111.2 | 556.1 | 556.1 | 481.0 | 182.8 | |||
Strip Ratio | ||||||||||||||||||
Copper World deposits | X:X | 0.16 | 0.40 | 1.15 | 0.08 | 0.04 | 0.18 | 0.67 | 0.28 | 0.30 | 0.22 | 0.07 | ||||||
East deposit | X:X | 2.10 | 2.06 | 0.54 | 2.23 | 2.61 | 1.91 | 1.98 | 2.97 | 3.16 | 2.91 | 3.33 | 2.38 | 2.18 | 0.41 | |||
Total strip ratio | X:X | 1.83 | 1.64 | 0.55 | 2.05 | 2.45 | 1.84 | 1.87 | 1.98 | 2.05 | 2.05 | 2.01 | 2.38 | 2.18 | 0.41 | |||
Mill | ||||||||||||||||||
Tonnes milled | Mt | 805.4 | 1,120.9 | 23.2 | 29.8 | 29.8 | 29.8 | 29.8 | 29.8 | 29.8 | 29.8 | 149.0 | 149.0 | 149.0 | 126.6 | |||
Headgrade - Cu | % | 0.41 | 0.42 | 0.56 | 0.56 | 0.43 | 0.48 | 0.56 | 0.55 | 0.46 | 0.37 | 0.41 | 0.38 | 0.37 | 0.31 | |||
Headgrade – Ag | g/tonne | 5.06 | 5.08 | 6.75 | 8.21 | 5.66 | 4.56 | 4.85 | 5.41 | 5.30 | 4.22 | 3.60 | 5.33 | 5.26 | 5.27 | |||
Headgrade – Mo | % | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.02 | 0.01 | 0.01 | 0.01 | 0.01 | 0.02 | |||
Leach | ||||||||||||||||||
Tonnes leached | Mt | 121.6 | 227.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 6.6 | 33.1 | 30.4 | 2.3 | 2.8 | |||
Headgrade – CuSS | % | 0.23 | 0.26 | 0.18 | 0.22 | 0.35 | 0.32 | 0.26 | 0.23 | 0.21 | 0.19 | 0.27 | 0.17 | 0.15 | 0.25 | |||
Headgrade - Cu | % | 0.31 | 0.35 | 0.24 | 0.28 | 0.47 | 0.42 | 0.35 | 0.30 | 0.29 | 0.27 | 0.36 | 0.22 | 0.22 | 0.30 | |||
Purchased Cu Conc | ||||||||||||||||||
Cu concentrate | Kt | 2,534.0 | 3,341.6 | 101.0 | 64.5 | 101.7 | 189.1 | 525.9 | 293.6 | 499.7 | 758.5 | |||||||
Grade – Cu | % | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | 25.00 | |||
Grade – Au | g/tonne | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | 0.50 | |||
Grade – Ag | g/tonne | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | |||
Recovery to Cu Cathode | ||||||||||||||||||
From Mill | % | 80.1 | 79.2 | 81.5 | 81.3 | 79.8 | 80.0 | 80.3 | 76.6 | 76.6 | 75.1 | 76.9 | 83.0 | 82.1 | 81.4 | |||
From Leach | % | 58.7 | 58.9 | 58.9 | 61.5 | 59.2 | 58.6 | 58.7 | 58.6 | 56.3 | 56.1 | 58.6 | 59.1 | 54.7 | 61.8 | |||
From Purchased | % | 97.1 | 97.3 | 97.5 | 98.1 | 97.8 | 97.8 | 97.8 | 97.4 | 96.7 | 96.5 | |||||||
Cu Cathode Produced | ||||||||||||||||||
From Mill | Kt | 2,617.5 | 3,755.4 | 106.1 | 136.1 | 102.5 | 115.2 | 134.7 | 125.2 | 104.1 | 83.9 | 471.8 | 466.6 | 447.1 | 324.2 | |||
From Leach | Kt | 219.4 | 463.1 | 9.3 | 11.4 | 18.3 | 16.4 | 13.6 | 11.7 | 10.8 | 9.9 | 69.8 | 40.1 | 2.8 | 5.3 | |||
From Purchased | Kt | 615.4 | 812.6 | 24.6 | 15.8 | 24.9 | 46.3 | 128.6 | 71.5 | 120.8 | 182.9 | |||||||
Total Cu cathode | Kt | 3,452.3 | 5,031.1 | 140.0 | 147.5 | 136.7 | 131.6 | 148.3 | 136.9 | 139.8 | 140.0 | 670.2 | 578.2 | 570.7 | 512.5 | |||
Mo Conc Produced | ||||||||||||||||||
Mo Concentrate | Kt | 116.6 | 150.9 | 2.8 | 3.2 | 3.1 | 4.0 | 4.5 | 3.4 | 4.5 | 4.0 | 16.6 | 24.1 | 24.4 | 21.9 | |||
Grade - Mo | % | 52.96 | 52.54 | 51.07 | 51.14 | 52.89 | 51.34 | 51.68 | 50.85 | 54.45 | 54.43 | 51.54 | 53.31 | 53.48 | 53.88 | |||
Mo in concentrate | Kt | 61.7 | 79.3 | 1.4 | 1.6 | 1.7 | 2.1 | 2.3 | 1.7 | 2.5 | 2.2 | 8.6 | 12.8 | 13.0 | 11.8 | |||
Doré Produced | ||||||||||||||||||
Ag in Doré - internal feed | 000 oz | 68,539 | 95,347 | 2,657 | 4,165 | 2,853 | 2,295 | 2,443 | 2,659 | 2,591 | 2,032 | 8,624 | 13,528 | 13,333 | 11,359 | |||
Ag in Doré - purchased conc | 000 oz | 1,094 | 1,443 | 44 | 28 | 44 | 82 | 227 | 127 | 216 | 328 | |||||||
Au in Doré - purchased conc | 000 oz | 37 | 48 | 1 | 1 | 1 | 3 | 8 | 4 | 7 | 11 | |||||||
Acid Plant | ||||||||||||||||||
Purchased sulfur | Kt | 655.2 | 1,752.3 | 45.9 | 71.5 | 76.2 | 22.4 | 18.3 | 48.5 | 51.6 | 42.0 | 140.5 | 59.8 | 78.6 | ||||
Excess acid produced | Kt | 5,733.3 | 7,304.3 | 187.7 | 78.3 | 44.8 | 106.7 | 96.9 | 71.7 | 99.5 | 103.9 | 725.8 | 711.5 | 1,827.6 | 1,678.9 | |||
Total Production | ||||||||||||||||||
Cu Eq Produced | Kt | 3,949.5 | 5,689.4 | 155.6 | 166.0 | 150.8 | 146.7 | 164.4 | 151.2 | 156.8 | 154.5 | 735.4 | 670.4 | 684.0 | 613.5 |
Phase II: Unit Costs | Unit | Phase II | LOM | Y15 | Y16 | Y17 | Y18 | Y19 | Y20 | Y21 | Y22 | Y23 | Y24 | Y25-29 | Y30-34 | Y35-39 | Y40-44 | Y45-49 | |||||||||||||||
Mining ($/t material moved excl. Pre-strip) | |||||||||||||||||||||||||||||||||
Mining | $/tonne | 1.35 | 1.37 | 1.85 | 1.27 | 1.27 | 1.31 | 1.32 | 1.32 | 1.32 | 1.32 | 1.32 | 1.32 | 1.35 | 1.56 | ||||||||||||||||||
Deferred stripping | $/tonne | (0.18 | ) | (0.16 | ) | (0.03 | ) | (0.07 | ) | (0.18 | ) | (0.00 | ) | (0.02 | ) | (0.27 | ) | (0.32 | ) | (0.26 | ) | (0.33 | ) | (0.12 | ) | (0.17 | ) | - | |||||
Mining ex def stripping | $/tonne | 1.17 | 1.21 | 1.83 | 1.21 | 1.09 | 1.31 | 1.30 | 1.05 | 1.01 | 1.06 | 0.99 | 1.20 | 1.18 | 1.56 | ||||||||||||||||||
Processing ($/t processed (tonnes milled + tonnes leached)) | |||||||||||||||||||||||||||||||||
Sulfide flotation | $/tonne | 4.04 | 3.89 | 4.43 | 3.78 | 3.77 | 3.80 | 3.79 | 3.78 | 3.77 | 3.78 | 3.78 | 3.84 | 4.56 | 4.53 | ||||||||||||||||||
Molybdenum flotation | $/tonne | 0.11 | 0.11 | 0.11 | 0.10 | 0.08 | 0.12 | 0.13 | 0.11 | 0.09 | 0.08 | 0.10 | 0.12 | 0.13 | 0.13 | ||||||||||||||||||
Leach Plant | $/tonne | 0.49 | 0.47 | 0.49 | 0.39 | 0.35 | 0.46 | 0.49 | 0.42 | 0.40 | 0.41 | 0.44 | 0.47 | 0.57 | 0.62 | ||||||||||||||||||
Acid Plant | $/tonne | 0.26 | 0.40 | 0.46 | 0.52 | 0.55 | 0.23 | 0.21 | 0.39 | 0.41 | 0.35 | 0.27 | 0.18 | 0.23 | 0.14 | ||||||||||||||||||
Acid Plant (electricity credit) | $/tonne | (0.17 | ) | (0.19 | ) | (0.19 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.16 | ) | (0.19 | ) | (0.22 | ) | ||||
Leach pad | $/tonne | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.00 | 0.00 | ||||||||||||||||||
Doré plant | $/tonne | 0.15 | 0.14 | 0.17 | 0.22 | 0.15 | 0.12 | 0.13 | 0.14 | 0.14 | 0.11 | 0.10 | 0.15 | 0.17 | 0.18 | ||||||||||||||||||
SX/EW | $/tonne | 0.84 | 0.84 | 1.05 | 0.90 | 0.84 | 0.82 | 0.90 | 0.84 | 0.86 | 0.86 | 0.83 | 0.74 | 0.83 | 0.88 | ||||||||||||||||||
Total | $/tonne | 5.72 | 5.68 | 6.53 | 5.75 | 5.60 | 5.41 | 5.51 | 5.53 | 5.52 | 5.44 | 5.36 | 5.34 | 6.31 | 6.27 | ||||||||||||||||||
Other Unit Costs ($/t processed (tonnes milled + tonnes leached)) | |||||||||||||||||||||||||||||||||
Onsite G&A | $/tonne | 0.95 | 0.93 | 1.01 | 1.02 | 1.02 | 1.02 | 1.02 | 1.02 | 1.02 | 1.02 | 1.02 | 1.02 | 0.78 | 0.79 | ||||||||||||||||||
Sustaining cash cost ($/lb Cu) | |||||||||||||||||||||||||||||||||
Cash cost1 | $/lb | 1.11 | 1.12 | 0.97 | 1.01 | 1.18 | 1.13 | 0.99 | 1.04 | 1.10 | 1.37 | 1.19 | 1.26 | 1.07 | 0.90 | ||||||||||||||||||
Sustaining cash cost1 | $/lb | 1.42 | 1.43 | 1.19 | 1.68 | 1.49 | 1.47 | 1.25 | 1.33 | 1.48 | 1.73 | 1.57 | 1.55 | 1.36 | 1.08 | ||||||||||||||||||
Total cash cost2 | $/lb | 1.46 | 1.44 | 1.35 | 1.01 | 1.42 | 1.13 | 0.99 | 1.04 | 1.47 | 1.97 | 1.56 | 1.49 | 1.49 | 1.64 | ||||||||||||||||||
Total sustaining cash cost2 | $/lb | 1.73 | 1.71 | 1.53 | 1.68 | 1.69 | 1.47 | 1.25 | 1.33 | 1.79 | 2.22 | 1.87 | 1.75 | 1.72 | 1.75 | ||||||||||||||||||
1 Internal feed only; 2 Includes purchased concentrate |
Phase II: Cash Flows | Unit | Phase II | LOM | Y15 | Y16 | Y17 | Y18 | Y19 | Y20 | Y21 | Y22 | Y23 | Y24 | Y25-29 | Y30-34 | Y35-39 | Y40-44 | Y45-49 | ||||||||||||||||||||||||||
Cash Flows | ||||||||||||||||||||||||||||||||||||||||||||
Gross rev – internal | $M | 24,722 | 36,197 | 969 | 1,212 | 995 | 1,096 | 1,230 | 1,125 | 977 | 804 | 4,556 | 4,413 | 4,159 | 3,186 | |||||||||||||||||||||||||||||
Gross rev – purchased | $M | 4,845 | 6,397 | 194 | 124 | 196 | 364 | 1,012 | 563 | 951 | 1,440 | |||||||||||||||||||||||||||||||||
TC/RC | $M | (280) | (355) | (6) | (6) | (7) | (10) | (11) | (8) | (11) | (10) | (41) | (58) | (60) | (54) | |||||||||||||||||||||||||||||
Freight | $M | (111) | (154) | (4) | (7) | (5) | (4) | (4) | (4) | (4) | (3) | (14) | (22) | (22) | (19) | |||||||||||||||||||||||||||||
Royalty | $M | (587) | (841) | (24) | (32) | (24) | (25) | (30) | (28) | (24) | (19) | (103) | (104) | (101) | (74) | |||||||||||||||||||||||||||||
Opex - Mining | $M | (3,048) | (4,314) | (84) | (134) | (121) | (146) | (145) | (116) | (112) | (118) | (551) | (668) | (568) | (285) | |||||||||||||||||||||||||||||
Opex - Processing | $M | (5,307) | (7,653) | (195) | (209) | (204) | (197) | (201) | (201) | (201) | (198) | (977) | (958) | (955) | (811) | |||||||||||||||||||||||||||||
Opex - Purch Cu Conc | $M | (4,180) | (5,512) | (167) | (106) | (168) | (312) | (867) | (484) | (824) | (1,251) | |||||||||||||||||||||||||||||||||
Opex - Onsite G&A | $M | (877) | (1,253) | (30) | (37) | (37) | (37) | (37) | (37) | (37) | (37) | (185) | (183) | (118) | (102) | |||||||||||||||||||||||||||||
Opex - Property tax | $M | (292) | (588) | (16) | (15) | (15) | (15) | (14) | (17) | (16) | (16) | (68) | (53) | (40) | (6) | |||||||||||||||||||||||||||||
Opex - Surety bond fees | $M | (55) | (89) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (2) | (9) | (9) | (9) | (9) | (5) | ||||||||||||||||||||||||||||
Closure Costs | $M | (200) | (200) | (200) | ||||||||||||||||||||||||||||||||||||||||
Tax - Federal income | $M | (1,616) | (2,110) | (55) | (83) | (50) | (65) | (84) | (73) | (59) | (36) | (304) | (281) | (276) | (249) | |||||||||||||||||||||||||||||
Tax - State income | $M | (317) | (415) | (11) | (16) | (10) | (13) | (16) | (14) | (12) | (7) | (60) | (55) | (54) | (49) | |||||||||||||||||||||||||||||
Tax - State severance | $M | (190) | (252) | (7) | (9) | (6) | (7) | (9) | (8) | (7) | (5) | (36) | (33) | (33) | (29) | |||||||||||||||||||||||||||||
Cash From Ops before WC | $M | 12,509 | 18,859 | 562 | 662 | 533 | 577 | 678 | 616 | 520 | 404 | 2,353 | 2,068 | 2,051 | 1,690 | (205) | ||||||||||||||||||||||||||||
WC Changes – AR | $M | 91 | (36) | (5) | 10 | 3 | (15) | 11 | (5) | 0 | (16) | 42 | 15 | (44) | 130 | |||||||||||||||||||||||||||||
WC Changes – AP | $M | (76) | 81 | (42) | 19 | (17) | (10) | 2 | (6) | 28 | 18 | (31) | (9) | (35) | 105 | (179) | ||||||||||||||||||||||||||||
WC Changes - Stream | $M | 230 | ||||||||||||||||||||||||||||||||||||||||||
Cash from Operations | $M | 12,524 | 19,089 | 81 | 484 | 676 | 526 | 570 | 665 | 621 | 544 | 422 | 2,306 | 2,102 | 2,031 | 1,751 | (254) | |||||||||||||||||||||||||||
Growth – EPCM | $M | (444) | (1,621) | (222) | (222) | |||||||||||||||||||||||||||||||||||||||
Growth - Owners Costs | $M | (264) | (739) | (132) | (132) | |||||||||||||||||||||||||||||||||||||||
Growth - Contingency | $M | (177) | (442) | (89) | (89) | |||||||||||||||||||||||||||||||||||||||
Sustaining capital | $M | (967) | (1,498) | (31) | (179) | (38) | (75) | (52) | (29) | (38) | (29) | (169) | (162) | (109) | (56) | |||||||||||||||||||||||||||||
Deferred stripping | $M | (456) | (567) | (1) | (7) | (20) | (0) | (2) | (31) | (35) | (29) | (184) | (67) | (79) | - | |||||||||||||||||||||||||||||
Cash From Investing | $M | (2,308) | (4,867) | (443) | (443) | (32) | (187) | (58) | (75) | (55) | (60) | (73) | (58) | (353) | (229) | (188) | (56) | |||||||||||||||||||||||||||
Net Cash Flow | $M | 10,216 | 14,222 | (361) | (443) | 452 | 489 | 468 | 495 | 611 | 561 | 470 | 364 | 1,953 | 1,873 | 1,842 | 1,695 | (254) | ||||||||||||||||||||||||||
NPV @ | $M | 947 | 2,044 | |||||||||||||||||||||||||||||||||||||||||
NPV @ | $M | 555 | 1,296 | |||||||||||||||||||||||||||||||||||||||||
IRR | % | 49% | 18% | |||||||||||||||||||||||||||||||||||||||||
PAYBACK | # years | 1.7 | - |
PRICE DECK | ||
PRICE / RATE | UNIT | LONG TERM |
Metals | ||
Copper | $/lb | 3.50 |
Copper net premium1 | $/lb | 0.01 |
Molybdenum | $/lb | 11.00 |
Gold - offtaker | $/oz | 1,600.00 |
Silver - offtaker | $/oz | 22.00 |
Silver - stream | $/oz | 3.90 |
Stream contracted escalator2 | % per year | 1.00 |
Other | ||
Molten sulfur - purchases | $/tonne | 215.00 |
Molten sulfur - sales | $/tonne | 195.00 |
Acid - sales | $/tonne | 145.00 |
Electricity | $/kWh | 0.075 |
NSR royalty | % | 3.00 |
1 Copper cathode premium net of cathode transport charge
2 Annual escalator begins in Year 4
MARKETING ASSUMPTIONS | ||
PRICE / RATE | UNIT | LONG TERM |
Molybdenum Concentrate | ||
Treatment charge | $/lb | 1.30 |
Payable % - Mo | % | 99.00 |
Freight | $/wmt | 20.00 |
Moisture | % | 6.00 |
Doré | ||
Refining charge - doré bar | $/oz | 0.40 |
Refining charge - Au | $/oz | 0.55 |
Payable % - Au | % | 99.90 |
Payable % - Ag | % | 99.90 |
Freight | $/oz | 1.40 |
Purchased Copper Concentrate | ||
Purchase price | $/dmt | 1,649.55 |
Cu grade | % | 25.00 |
Mo grade | % | 0.01 |
Au grade | g/dmt | 0.50 |
Ag grade | g/dmt | 15.00 |
Zn grade | % | 0.20 |
S grade | % | 35.00 |
Treatment charge | $/dmt | 80.00 |
Refining charge - Cu | $/lb | 0.08 |
Payable % - Cu | % | 96.50 |
Payable % - Au | % | 90.00 |
Payable % - Ag | % | 90.00 |
Min deduction - Cu | % | 1.00 |
Min grade - Au | g/dmt | 1.00 |
Min grade - Ag | g/dmt | 30.00 |
Freight capture | $/dmt | 80.00 |
OPERATING COST DETAILS – MINING | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Labor | $M | ||||||
Maintenance | $M | ||||||
Fuel | $M | ||||||
Blasting | $M | ||||||
Indirect | $M | ||||||
Other | $M | ||||||
Subtotal* | $M | ||||||
Deferred stripping | $M | ( | ( | ( | |||
Total* | $M | $1,266 | $3,048 | $4,314 |
*Excludes pre-stripping costs
OPERATING COST DETAILS – PROCESSING | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Sulfide flotation | $M | ||||||
Molybdenum flotation | $M | ||||||
Leach plant | $M | ||||||
Acid plant | $M | ||||||
Acid plant (electricity credit) | $M | ( | ( | ( | |||
Leach pad | $M | ||||||
Doré plant | $M | ||||||
SX/EW | $M | ||||||
Total | $M | $2,346 | $5,307 | $7,653 |
UNIT OPERATING COST SUMMARY | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Mining excl. def stripping | $/t material moved | ||||||
Concentrator | $/t processed | ||||||
Sulfide leach | $/lb Cu prod | ||||||
Oxide heap leach | $/lb Cu prod | ||||||
SX/EW | $/lb Cu prod | ||||||
Onsite G&A | $/t processed |
CAPITAL COST SUMMARY | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Growth - EPCM | $M | ||||||
Growth - owner's costs | $M | ||||||
Growth - subtotal | $M | ||||||
Sustaining | $M | ||||||
Deferred stripping | $M | ||||||
Total | $M | $2,559 | $2,308 | $4,867 |
GROWTH CAPITAL DETAILS – EPCM | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Sitewide | $M | ||||||
Mining | $M | ||||||
Primary crushing | $M | ||||||
Sulfide plant | $M | ||||||
Molybdenum plant | $M | ||||||
Reagents | $M | ||||||
Plant services | $M | ||||||
SX/EW plant | $M | ||||||
Concentrate leach plant | $M | ||||||
Acid plant | $M | ||||||
Doré plant | $M | ||||||
Site services and utilities | $M | ||||||
Internal infrastructure | $M | ||||||
External infrastructure | $M | ||||||
Common construction | $M | ||||||
Other | $M | ||||||
Contingency | $M | ||||||
Total | $M | $1,345 | $621 | $1,966 |
GROWTH CAPITAL DETAILS – OWNER’S COSTS | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Pre-stripping | $M | ||||||
Mining fleet and equipment | $M | ||||||
Tailings storage | $M | ||||||
Heap leach pad | $M | ||||||
Earthworks and roads | $M | ||||||
G&A and other | $M | ||||||
Indirects and contingency | $M | ||||||
Total | $M | $572 | $264 | $836 |
SUSTAINING CAPITAL DETAILS | |||||||
METRIC | UNIT | Phase I | Phase II | LOM | |||
Mining | $M | ||||||
Processing | $M | ||||||
Admin | $M | ||||||
Deferred stripping | $M | ||||||
Total | $M | $642 | $1,423 | $2,065 |
Figure 1: Copper World Complex Mineralization
The Copper World Complex consists of several mineral deposits hosting both oxides and sulfide copper mineralization, with a majority of the deposits located on patented mining claims.
https://www.globenewswire.com/NewsRoom/AttachmentNg/e3612e49-e5b6-4348-9d82-1b64f0359c5f
Figure 2: Private Land Package to Support Phase I
Hudbay’s total private land package has increased since 2019 to approximately 4,500 acres with the inclusion of private land claims (fee land) and patented mining claims. This private land package is estimated to support the first phase of approximately 16 years of operations at the Copper World Complex.
https://www.globenewswire.com/NewsRoom/AttachmentNg/57c71963-0cd8-4e53-b92c-7bad068b424b
Figure 3: Phase I and Phase II Open Pit Footprint
The overall mine footprint is expected to consist of four open pits in Phase I with two of the pits expanding onto federal land in Phase II. Phase I considers exploitation of the pits and their associated infrastructure within a footprint that requires only state and local permits for 16 years of operation.
https://www.globenewswire.com/NewsRoom/AttachmentNg/0e7311c1-a337-4bf8-a396-aa0dbebd03b7
Figure 4: Contribution of Resources Mined over the Mine Life
The Peach, Elgin, West, Broadtop and Bolsa deposits contribute approximately
https://www.globenewswire.com/NewsRoom/AttachmentNg/0ec42721-0055-4bea-8a1b-82986101b2f9
Figure 5: Reduction in Energy Consumption and GHG Emissions from Sulfide and Oxide Leaching
One of the many benefits of producing copper cathode on site is that the cathode is likely to be sold entirely to the domestic U.S. market, thereby reducing energy consumption, greenhouse gas and sulfur emissions by eliminating overseas shipping, smelting and refining.
https://www.globenewswire.com/NewsRoom/AttachmentNg/3f1d3a07-4fed-4e6f-b7ad-918a4a01eb8f
i "Tonnes” refers to metric tonnes and “tons” refers to imperial or U.S. short tons. The mine plan assumes external concentrate is sourced in years when spare capacity exists at the SX/EW facility in order to maximize the full utilization of the facility. Copper cathode production from mined resources excludes the production from external concentrate. Average annual copper cathode production from external concentrates is approximately 12,000 tonnes in Phase I and 22,000 tonnes in Phase II. There remains the potential to replace external copper concentrate with additional internal feed.
ii Cash cost and sustaining cash cost, net of by-product credits, per pound of copper produced from internally sourced feed and excludes the cost of purchasing external copper concentrate, which may vary in price or potentially be replaced by additional internal feed. By-product credits calculated using the following commodity prices: molybdenum price of
FAQ
What is the after-tax NPV of Hudbay's Copper World Complex?
When is the expected mine life for Phase I of the Copper World project?
What average annual copper production is projected for Phase II?
What is the internal rate of return for Phase II of the Copper World Complex?