STOCK TITAN

End of FLNG Gimi Force Majeure Events

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary

Golar LNG Limited has announced a revised project schedule for the Greater Tortue Ahmeyim project in collaboration with BP Mauritania Investments Ltd. The target connection date for the Gimi floating liquefaction vessel has been pushed back by 11 months, now expected beyond 2022. Both parties confirmed this change without impacting the terms of the existing Lease and Operate Agreement. This revision is anticipated to aid ongoing discussions with engineering, procurement, and construction contractors, as well as lending banks regarding construction and financing schedules.

Positive
  • Revised project schedule may allow for improved negotiations with contractors and banks.
Negative
  • Connection date for Gimi delayed by 11 months, potentially impacting overall project timelines.

Golar LNG Limited (“Golar”) announces today that Gimi MS Corp., a subsidiary of Golar, has confirmed a revised project schedule with BP Mauritania Investments Ltd. (“BP”) for the Greater Tortue Ahmeyim project. The revised project schedule will result in the target connection date for the converted floating liquefaction natural gas vessel Gimi, previously scheduled for 2022, as set out in the Lease and Operate Agreement dated February 26, 2019 (the “Lease and Operate Agreement”), being extended by 11 months.

Gimi MS Corp. and BP have now received and given notice to each other confirming with each other the revised project schedule and that there is no FM Event ongoing, as defined in the Lease and Operate Agreement. The terms of the Lease and Operate Agreement are unchanged. The confirmation of a revised project schedule with BP and exchange of notices is expected to facilitate the conclusion of ongoing discussions with both engineering, procurement and construction contractors and lending banks regarding the adjustment of construction and financing schedules, respectively.

FORWARD LOOKING STATEMENTS

This press release contains forward-looking statements (as defined in Section 21E of the Securities Exchange Act of 1934, as amended) which reflects management’s current expectations, estimates and projections about its operations. All statements, other than statements of historical facts, that address activities and events that will, should, could or may occur in the future are forward-looking statements. Words such as “may,” “could,” “should,” “would,” “expect,” “plan,” “anticipate,” “intend,” “forecast,” “believe,” “estimate,” “predict,” “propose,” “potential,” “continue,” or the negative of these terms and similar expressions are intended to identify such forward-looking statements.

These statements are not guarantees of future performance and are subject to certain risks, uncertainties and other factors, some of which are beyond our control and are difficult to predict. Therefore, actual outcomes and results may differ materially from what is expressed or forecasted in such forward-looking statements. You should not place undue reliance on these forward-looking statements, which speak only as of the date of this press release. Golar LNG Limited undertakes no obligation to update publicly any forward-looking statements whether as a result of new information, future events or otherwise, unless required by applicable law.

Hamilton, Bermuda

October 1, 2020

Enquiries:

Golar Management Limited: + 44 207 063 7900

Stuart Buchanan

FAQ

What is the new connection date for Golar LNG's Gimi vessel?

The connection date for the Gimi vessel has been postponed by 11 months, beyond 2022.

What company is Golar LNG partnering with for the Greater Tortue Ahmeyim project?

Golar LNG is partnering with BP Mauritania Investments Ltd.

What does the revised project schedule mean for Golar LNG?

The revised schedule may facilitate better discussions regarding construction and financing, although it delays the project's timeline.

Are the terms of the Lease and Operate Agreement changed?

No, the terms of the Lease and Operate Agreement remain unchanged.

When was the original connection date scheduled for the Gimi vessel?

The original connection date was scheduled for 2022.

Golar LNG Ltd

NASDAQ:GLNG

GLNG Rankings

GLNG Latest News

GLNG Stock Data

3.21B
93.07M
10.85%
73.47%
5.08%
Oil & Gas Midstream
Energy
Link
United States of America
Hamilton