Idaho Champion Gold Mobilizes Second Drill Rig to Champagne Project and Provides Update on Drill Programs
Idaho Champion Gold Mines Canada Inc. (OTCQB: GLDRF) updated its exploration program for the Baner and Champagne Gold Projects. Currently, 29% of the 8,000 metres planned for this drilling season have been completed. The company has drilled 1,286 metres at Baner (43% complete) and 1,045 metres at Champagne (21% complete). To enhance efficiency, a second drill rig was mobilized at Champagne. The geological mapping and analysis of historical data are guiding the drilling strategy, targeting potential gold-silver mineralization.
- Mobilization of a second drill rig at Champagne enhances drilling capacity.
- Drilling programs progressing well with Baner completed at 43% and Champagne at 21%.
- Existing historical data used to inform drilling targets suggests potential resource.
- Completion of drilling at Champagne at only 21% indicates slower progress.
- Historical data's reliability in predicting current mineralization remains uncertain.
Drilling to date amounts to approximately
- 6 holes totaling 1,286 metres have been completed at Baner; approximately
43% of the program - 6 holes totaling 1,045 metres have been completed at Champagne; approximately
21% of the program - Second drill rig mobilized for core drilling at Champagne
TORONTO, ON / ACCESSWIRE / September 30, 2020 / Idaho Champion Gold Mines Canada Inc. (CSE:ITKO)(OTCQB:GLDRF)(FSE:1QB1)("Champion" or the "Company"), announces an update regarding its 2020 exploration program on both the Baner Gold and past-producing Champagne Gold Projects in Idaho, USA.
Champagne Gold Project
Champion announces that it has completed six (6) holes totaling 1,045 metres at the past-producing Champagne Gold Project. The completion of hole 6 represents approximately
In order to increase efficiencies and data for the maiden drilling program, the Company also announces that it has mobilized a diamond core rig to site to complete the 5,000 metre program (See press release dated: August 19, 2020).
"Drilling targets at Champagne have been identified using historic and newly acquired data which have been previously released," stated Jonathan Buick, President and CEO. "Ongoing district-wide geologic mapping and review of completed reverse-circulation drill holes have led to recently initiating core drilling to expedite testing and understanding the vuggy silica feeder zones beneath the near-surface cap of gold-silver mineralization mined in the past via several open pits. Precious-metal bearing solutions ascended along steep structural conduits which comprise the principal target objective of the core drilling."
Baner Gold Project
The Company reports that the drilling program is
President and CEO Jonathan Buick stated further, "Drilling at Baner North is progressing well with the commencement of seventh core hole in the Orogrande Shear Zone. Our geologists tell us that shear zone pyritic mineralization has been encountered." The 2020 Baner North drill program is a continuation of the 2018 gold discovery drill program on the Baner Gold zone.
About the Champagne Project
The Champagne Mine* was operated by Bema Gold as a heap leach operation on a high sulfidation gold system that occurs in volcanic rocks. Bema Gold drilled 72 shallow reverse circulation holes on the project, which complement drilling and trenching from other previous operators. The property has had no deep drilling or significant modern exploration since the mine closure in early 1992.
The Champagne Deposit contains epigenetic style gold and silver mineralization that occurs in strongly altered Tertiary volcanic tuffs and flows of acid to intermediate composition.
Champagne has a near surface cap of gold-silver mineralization emplaced by deep-seated structures that acted as conduits for precious metal rich hydrothermal fluids. Higher grade zones in the Champagne Deposit appear to be related to such feeder zones.
* The Company cautions that the information about the past-producing mine may not be indicative of mineralization on Champion's property, and if mineralization does occur, that it will occur in sufficient quantity or grade that would result in an economic extraction scenario. The historic data were simply used to evaluate the prospective nature of the property. The Company has not yet conducted sufficient exploration to ascertain if a mineral resource is present on the property.
About the Baner Project
The Baner Project is located within the Orogrande Shear Zone (OSZ), a 20-kilometre long and up to 1-kilometre wide regional shear zone located in Central Idaho. The OSZ is comprised of a series of grabens composed of metamorphosed Proterozoic sedimentary rocks of the Belt Supergroup and granitic rocks of the Cretaceous Idaho Batholith, which
is intruded by Tertiary rhyolites and dacitic dikes. Hydrothermal alteration is spatially associated with the OSZ consisting of: silicification, sericitization, and chloritization. Different types of mineral systems occur in the OSZ and along sympathetic structures in the area, most likely of Cretaceous or Tertiary ages. Mineralization may include disseminated bulk-mineable precious metal mineralization associated with sheeted or stockwork veins, hydraulic breccias and with extensive widespread alteration; but high-grade gold also occurs within discreet structurally controlled quartz veins and silicified zones.
The Baner Project is in the central Idaho Gold Belt, 8 km south of Elk City, Idaho. Elk City is an historic gold mining region dating back to the 1860's and once supported more than 20 underground mines and extensive placer operations. During the 1930's there were three cyanide gold mills along Crooked River, which processed open pit and underground sulfide ore. Exploration in the district during the 1980's and 1990's was primarily focused on near-surface bulk-tonnage gold potential and included companies such as Cypress-Amax, Kinross Gold, and Bema Gold. Premium Exploration conducted extensive airborne and surface geophysics, soil geochemistry, and drilling around 2010. Currently, in April 2020, Endomines AB, a Nordic gold producer, began mining operations at the Friday Project at Orogrande, which is Idaho's newest producing gold asset.
Qualified Person
The technical information in this press release has been reviewed and approved by Peter Karelse P.Geo., a consultant to the Company, who is a Qualified Person as defined by NI 43-101. Mr. Karelse has more than 30 years of experience in exploration and development.
About Idaho Champion Gold Mines Inc.
Idaho Champion is a discovery-focused gold exploration company that is committed to advancing its
ON BEHALF OF THE BOARD
"Jonathan Buick"
Jonathan Buick, President and CEO
For further information, please visit the Company's SEDAR profile at www.sedar.com or the Company's corporate website at www.idahochamp.com.
For further information please contact:
Nicholas Konkin, Marketing and Communications
Phone: (416) 477 7771 ext. 205
Email: nkonkin@idahochamp.com
THIS PRESS RELEASE DOES NOT CONSTITUTE AN OFFER TO SELL OR THE SOLICITATION OF AN OFFER TO BUY ANY SECURITIES IN ANY JURISDICTION, NOR SHALL THERE BE ANY OFFER, SALE, OR SOLICITATION OF SECURITIES IN ANY STATE IN THE UNITED STATES IN WHICH SUCH OFFER, SALE, OR SOLICITATION WOULD BE UNLAWFUL.
Cautionary Statements
Neither the Canadian Securities Exchange nor its regulation services provider has reviewed or accepted responsibility for the adequacy or accuracy of this press release This press release may include forward-looking information within the meaning of Canadian securities legislation, concerning the business of the Company. Forward-looking information is based on certain key expectations and assumptions made by the management of the Company. Although the Company believes that the expectations and assumptions on which such forward-looking information is based on are reasonable, undue reliance should not be placed on the forward-looking information because the Company can give no assurance that they will prove to be correct. Forward-looking statements contained in this press release are made as of the date of this press release. The Company disclaims any intent or obligation to update publicly any forward looking information, whether as a result of new information, future events or results or otherwise, other than as required by applicable securities laws.
SOURCE: Idaho Champion Gold Mines Canada Inc.
View source version on accesswire.com:
https://www.accesswire.com/608455/Idaho-Champion-Gold-Mobilizes-Second-Drill-Rig-to-Champagne-Project-and-Provides-Update-on-Drill-Programs
FAQ
What is the current progress of the drilling programs for GLDRF?
What are the drilling targets for the Champagne Gold Project?
How many total meters of drilling are planned for the 2020 season by Idaho Champion?