FirstEnergy Corp. (NYSE: FE) is engaged in a massive power restoration effort in Northeast Ohio following a historic storm that included two tornados. The company has restored power to over 215,000 customers, with 265,000 still affected. More than 3,050 line workers and 1,000 support personnel are working around the clock in 16-hour shifts to repair damages.

The storm, which hit on Tuesday, was the most impactful to hit The Illuminating Company service territory since July 1993. FirstEnergy is setting up staging sites across the Cleveland area to handle the influx of workers and make the restoration process more efficient. The company expects power to be restored to the majority of customers by 11:30 p.m. on Wednesday, Aug. 14, with some hard-hit areas potentially waiting until Saturday.

FirstEnergy Corp. (NYSE: FE) è impegnata in un ampio sforzo di ripristino dell'energia nel Northeast Ohio a seguito di una tempesta storica che ha incluso due tornado. L'azienda ha ripristinato l'energia a oltre 215.000 clienti, mentre 265.000 sono ancora colpiti. Più di 3.050 operatori di linea e 1.000 personale di supporto stanno lavorando senza sosta in turni di 16 ore per riparare i danni.

La tempesta, che ha colpito martedì, è stata la più impattante nel territorio di servizio della The Illuminating Company dal luglio 1993. FirstEnergy sta allestendo punti di raccolta nell'area di Cleveland per gestire l'afflusso di lavoratori e rendere il processo di ripristino più efficiente. L'azienda prevede di ripristinare l'energia alla maggior parte dei clienti entro le 23:30 di mercoledì 14 agosto, con alcune aree fortemente colpite che potrebbero dover aspettare fino a sabato.

FirstEnergy Corp. (NYSE: FE) está llevando a cabo un gran esfuerzo de restauración de energía en el noreste de Ohio tras una tormenta histórica que incluyó dos tornados. La compañía ha restablecido la energía a más de 215,000 clientes, mientras que 265,000 siguen afectados. Más de 3,050 trabajadores de líneas y 1,000 personal de apoyo están trabajando sin descanso en turnos de 16 horas para reparar los daños.

La tormenta, que ocurrió el martes, fue la más impactante que ha golpeado el territorio de servicio de The Illuminating Company desde julio de 1993. FirstEnergy está estableciendo sitios de preparación en el área de Cleveland para manejar el aflujo de trabajadores y hacer que el proceso de restauración sea más eficiente. La compañía espera restaurar la energía a la mayoría de los clientes para las 11:30 p.m. del miércoles 14 de agosto, aunque algunas áreas muy afectadas podrían esperar hasta el sábado.

FirstEnergy Corp. (NYSE: FE)는 역사적인 폭풍으로 인해 발생한 전원 복구 작업을 위해 오하이오 북동부에서 대규모 작업을 진행하고 있습니다. 이 회사는 215,000명 이상의 고객에게 전력을 복구했습니다, 그러나 265,000명은 여전히 영향을 받고 있습니다. 3,050명의 전선 작업자와 1,000명의 지원 인력이 16시간 교대근무를 하며 피해를 복구하기 위해 밤낮으로 노력하고 있습니다.

화요일에 발생한 이 폭풍은 1993년 7월 이후 The Illuminating Company 서비스 지역에 가장 큰 영향을 미친 폭풍입니다. FirstEnergy는 클리블랜드 지역에 작업자들을 수용할 수 있는 임시 거점을 마련하여 복구 절차를 보다 효율적으로 진행할 계획입니다. 이 회사는 8월 14일 수요일 오후 11시 30분까지 대부분의 고객에게 전력이 복원될 것으로 예상하고 있으며, 일부 강한 피해를 입은 지역은 토요일까지 기다려야 할 수도 있습니다.

FirstEnergy Corp. (NYSE: FE) s'engage dans un immense effort de rétablissement de l'électricité dans le nord-est de l'Ohio à la suite d'une tempête historique qui a inclus deux tornades. L'entreprise a rétabli l'électricité pour plus de 215 000 clients, tandis que 265 000 sont encore affectés. Plus de 3 050 travailleurs de lignes et 1 000 personnes de soutien travaillent jour et nuit en équipes de 16 heures pour réparer les dommages.

La tempête, qui a frappé mardi, a été la plus impactante sur le territoire de service de The Illuminating Company depuis juillet 1993. FirstEnergy met en place des sites de staging dans la région de Cleveland pour gérer l'afflux de travailleurs et rendre le processus de rétablissement plus efficace. L'entreprise s'attend à ce que l'électricité soit rétablie pour la majorité des clients d'ici 23h30 le mercredi 14 août, certaines zones durement touchées pouvant potentiellement attendre jusqu'à samedi.

FirstEnergy Corp. (NYSE: FE) ist mit einem umfangreichen Wiederherstellungsprozess der Stromversorgung im Nordosten von Ohio beschäftigt, nachdem ein historischer Sturm mit zwei Tornados die Region getroffen hat. Das Unternehmen hat den Strom für über 215.000 Kunden wiederhergestellt, während 265.000 Kunden weiterhin betroffen sind. Mehr als 3.050 Linienarbeiter und 1.000 Unterstützungsmitarbeiter arbeiten rund um die Uhr in 16-Stunden-Schichten, um die Schäden zu beheben.

Der Sturm, der am Dienstag zuschlug, war der stärkste, der seit Juli 1993 das Dienstgebiet der Illuminating Company betroffen hat. FirstEnergy richtet in der Umgebung von Cleveland vorbereitende Standorte ein, um den Zustrom von Arbeitern zu bewältigen und den Wiederherstellungsprozess effizienter zu gestalten. Das Unternehmen erwartet, dass der Strom für die meisten Kunden bis 23:30 Uhr am Mittwoch, den 14. August, wiederhergestellt wird, während einige stark betroffene Gebiete möglicherweise bis Samstag warten müssen.

Positive
  • Rapid response with over 3,050 line workers and 1,000 support personnel deployed
  • Power already restored to 215,000 customers
  • Setting up efficient staging sites to handle influx of workers
  • Clear restoration timeline provided for majority of customers
Negative
  • 265,000 customers still without power
  • Some areas may be without power until Saturday
  • Extensive damage with hundreds to thousands of damage locations recorded
  • Most impactful storm since 1993, indicating potential for significant repair costs

Insights

This severe weather event and its impact on FirstEnergy's (NYSE: FE) infrastructure is significant. The scale of the outages, affecting over 429,500 customers, is the most substantial since 1993. The company's response, mobilizing 3,050 line workers and 1,000 support personnel, demonstrates the magnitude of the restoration effort.

The extended restoration timeline, with some areas potentially without power until August 14th, could lead to customer dissatisfaction and potential regulatory scrutiny. However, FirstEnergy's transparent communication and detailed restoration process may mitigate some reputational risks. The financial impact on FE will likely be material, considering the extensive damage and resources deployed, potentially affecting short-term earnings.

FirstEnergy's response to this crisis showcases robust emergency preparedness. The rapid mobilization of resources, including setting up staging sites and bringing in mutual assistance, indicates a well-executed disaster response plan. The company's prioritization of critical facilities and transparent communication of Estimated Time of Restoration (ETR) aligns with best practices in emergency management.

However, the extended outage duration for some customers poses significant public safety concerns, particularly regarding vulnerable populations. The emphasis on generator safety is important but may not fully mitigate risks associated with prolonged power loss. Local authorities and FirstEnergy must collaborate closely to address potential secondary emergencies arising from this extended outage situation.

While the full financial impact isn't quantified, this event will likely have a material short-term effect on FirstEnergy's (NYSE: FE) financials. The extensive damage and large-scale restoration effort will incur significant costs, potentially impacting Q3 2024 earnings. However, regulatory mechanisms often allow utilities to recover storm-related costs over time, mitigating long-term financial impacts.

Investors should monitor for any announcements regarding estimated restoration costs and potential regulatory filings for cost recovery. The company's ability to efficiently manage this crisis and minimize outage durations could influence regulatory outcomes and investor sentiment. Despite short-term pressures, FE's fundamental business model as a regulated utility remains stable, with this event unlikely to significantly alter long-term financial projections.

Crews continue working 24/7 to restore service to 265,000 customers following historic storm

AKRON, Ohio, Aug. 8, 2024 /PRNewswire/ -- FirstEnergy Corp. (NYSE: FE) has restored power to more than 215,000 customers of Ohio Edison and The Illuminating Company following a historic weather event Tuesday that included two tornados with winds up to 110 mph in Cuyahoga County, one of which traveled a path 17 miles long and 350 yards wide through the heavily populated area from Brookpark to Bedford.

This was the most impactful storm to hit The Illuminating Company service territory since July 1993, when a powerful line of thunderstorms caused power outages to approximately 300,000 of the company's customers.

Photos and video footage of damage and FirstEnergy crews working across northeast Ohio can be viewed or downloaded here.

More than 3,050 line workers from FirstEnergy, contractor companies and mutual assistance organizations, assisted by more than 1,000 damage assessors, hazard responders, forestry and other support personnel from inside and outside the company, are working around the clock in 16-hour shifts to make repairs as quickly and safely as possible. Hundreds of additional crews are expected to arrive throughout today and begin assisting.

FirstEnergy has begun setting up staging sites across the greater Cleveland area to handle the influx of outside workers and help make the restoration process more efficient. These sites operate like mini-cities in the hardest-hit areas, offering workers a place stock up on materials and supplies as they work to restore power.

There are currently hundreds, even thousands, of damage locations recorded across northeast Ohio, with more broken poles and equipment issues being reported in real-time as field workers continue to assess the outage locations and make repairs.

Current outage updates as of 10 a.m. today include:

  • The Illuminating Company: Approximately 322,600 Illuminating Company customers lost power from the storm, and 248,300 remain without power. Power will be restored to the majority of customers by 11:30 p.m. on Wednesday, Aug. 14.
  • Ohio Edison: Approximately 106,900 Ohio Edison customers lost power from the storm, and 9,100 remain without power. While many remaining customers should be back up and running through the day today and tomorrow, those in the hardest-hit areas of Trumbull County could be without service until Saturday.

Established while crews are restoring power and assessing the full extent of damages, the initial "global estimated time of restoration" (ETR) represents an estimate of when service will be restored to the majority of customers following major outage events. Work to restore power continues around the clock, and many customers will have service restored sooner, based on the level of damage in their area. 

As additional information about necessary repairs is understood, more detailed ETRs are provided. Customers can view their current individual ETR for their particular outage by logging into their account at firstenergycorp.com, texting STAT to 54487, or viewing the outage map at firstenergycorp.com/outages.

FirstEnergy's Restoration Process:

FirstEnergy follows a formal restoration process after severe weather, focusing on repairs that will address the largest number of customers before moving on to more isolated issues. The restoration effort typically begins with transmission and substation facilities and then prioritizes critical facilities like hospitals, communications and emergency response agencies.

Additionally, hundreds of isolated issues affect individual or small numbers of customers. These are the most time-consuming repairs because they require our crews to go to each individual location to make the repairs. Many of the isolated issues include repairs to "service drops," which are wires attached to each home to deliver electricity from the neighborhood power line. These wires are often damaged by fallen trees and large branches.

For updated information on the company's current outages, storm restoration process and tips for staying safe, visit FirstEnergy's 24/7 Power Center at firstenergycorp.com/outages. To learn more about navigating the recently updated map, please visit bit.ly/FEoutagemapupdates.

Generator Safety Reminder:

To ensure the safety of the home's occupants as well as that of electric company employees who may be working on power lines in the area, the proper generator should be selected and installed by a qualified electrician.

When operating a generator, the power coming into the home should always be disconnected. Otherwise, power from the generator could be sent back onto the power lines, creating a hazardous situation for company workers. Locate the generator outside of your home and far away from windows, doors and vents. Never locate a generator inside your home.

View additional generator safety information.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Visit FirstEnergy online at firstenergycorp.com and follow FirstEnergy and its operating companies on X, formerly known as Twitter, @FirstEnergyCorp, @IlluminatingCo, @OhioEdison.

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/thousands-of-personnel-engaged-in-firstenergys-power-restoration-effort-in-northeast-ohio-302218140.html

SOURCE FirstEnergy Corp.

FAQ

How many FirstEnergy (FE) customers are still without power after the August 2024 storm?

As of the press release, approximately 265,000 FirstEnergy (FE) customers were still without power following the historic storm in Northeast Ohio.

When does FirstEnergy (FE) expect to restore power to most customers affected by the August 2024 storm?

FirstEnergy (FE) expects to restore power to the majority of affected customers by 11:30 p.m. on Wednesday, August 14, 2024, with some hard-hit areas potentially waiting until Saturday.

How many workers has FirstEnergy (FE) deployed for the power restoration effort in Northeast Ohio?

FirstEnergy (FE) has deployed over 3,050 line workers and 1,000 support personnel, working in 16-hour shifts to restore power in Northeast Ohio.

What was the extent of the storm damage that affected FirstEnergy's (FE) service area in August 2024?

The storm included two tornados with winds up to 110 mph in Cuyahoga County, one of which traveled a 17-mile path. It was the most impactful storm to hit The Illuminating Company service territory since July 1993.

FirstEnergy Corp.

NYSE:FE

FE Rankings

FE Latest News

FE Stock Data

23.70B
575.92M
0.12%
89.25%
1.9%
Utilities - Regulated Electric
Electric Services
Link
United States of America
AKRON