Endeavour Silver (NYSE: EXK; TSX: EDR) reported delays at its Terronera project due to critical structural steel delivery issues in December, impacting construction progress and commissioning timelines. As a cost-saving measure, the company reduced its workforce from December 20, 2024, to January 6, 2025.

The wet commissioning is now expected in early Q2 2025. Despite delays, the tailings dam is ready, and dry commissioning of the upper platform continues. The grinding circuit testing has been successful, with SAG and ball mills tested at full operating speed. Above-ground ore stockpiles are approaching capacity, while mine development continues.

Management will provide a detailed Q4 construction update later in January, including a photo gallery and updated site overhead costs for Q1 2025.

Endeavour Silver (NYSE: EXK; TSX: EDR) ha segnalato ritardi nel suo progetto Terronera a causa di problemi critici nella consegna di acciaio strutturale a dicembre, che hanno impattato sul progresso della costruzione e sulle tempistiche di messa in servizio. Come misura di contenimento dei costi, l'azienda ha ridotto il proprio personale dal 20 dicembre 2024 al 6 gennaio 2025.

La messa in servizio umida è ora prevista per inizio Q2 2025. Nonostante i ritardi, la diga di stoccaggio è pronta e continua la messa in servizio secca della piattaforma superiore. I test del circuito di macinazione sono stati soddisfacenti, con mulini SAG e a palle testati a piena velocità operativa. Le scorte di minerale in superficie si avvicinano alla capacità massima, mentre continua lo sviluppo della miniera.

La direzione fornirà un aggiornamento dettagliato sulla costruzione del quarto trimestre più avanti a gennaio, inclusa una galleria fotografica e i costi aggiornati del sito per il primo trimestre 2025.

Endeavour Silver (NYSE: EXK; TSX: EDR) reportó retrasos en su proyecto Terronera debido a problemas críticos en la entrega de acero estructural en diciembre, lo que afectó el progreso de la construcción y los plazos de puesta en marcha. Como medida de ahorro de costos, la empresa redujo su fuerza laboral del 20 de diciembre de 2024 al 6 de enero de 2025.

Ahora se espera que la puesta en marcha húmeda ocurra en principios del Q2 2025. A pesar de los retrasos, la represa de relaves está lista, y continúa la puesta en marcha seca de la plataforma superior. Las pruebas del circuito de molienda han sido exitosas, con los molinos SAG y de bolas probados a plena velocidad operativa. Las pilas de mineral en superficie se están acercando a su capacidad, mientras que el desarrollo de la mina continúa.

La dirección proporcionará una actualización de construcción detallada del cuarto trimestre más adelante en enero, incluida una galería de fotos y costos generales actualizados del sitio para el primer trimestre de 2025.

엔데바 실버 (NYSE: EXK; TSX: EDR)는 12월에 발생한 구조용 강철 배송 문제로 인해 테론에라 프로젝트의 지연을 보고하며, 이는 건설 진행 및 commissioning 일정에 영향을 미쳤습니다. 비용 절감 조치로, 회사는 2024년 12월 20일부터 2025년 1월 6일까지 인력을 줄였습니다.

습식 commissioning은 이제 2025년 2분기 초에 예상됩니다. 지연에도 불구하고 석회석댐은 준비 완료되었으며, 상부 플랫폼의 건조 commissioning이 계속되고 있습니다. 분쇄 회로 테스트는 성공적이었으며 SAG 및 볼 밀은 전면 속도로 시험되었습니다. 지상의 광석 재고는 최대 용량에 근접하고 있으며, 광산 개발은 계속되고 있습니다.

경영진은 1월 말에 4분기 건설 업데이트를 상세히 제공할 예정이며, 사진 갤러리 및 2025년 1분기 현장 간접비 업데이트를 포함할 것입니다.

Endeavour Silver (NYSE: EXK; TSX: EDR) a signalé des retards dans son projet Terronera en raison de problèmes critiques de livraison d'acier structurel en décembre, ce qui a eu un impact sur les progrès de la construction et les délais de mise en service. En tant que mesure d'économie de coûts, l'entreprise a réduit son effectif du 20 décembre 2024 au 6 janvier 2025.

La mise en service humide est maintenant attendue au début du Q2 2025. Malgré les retards, le barrage de résidus est prêt et la mise en service sèche de la plateforme supérieure se poursuit. Les tests du circuit de broyage ont été couronnés de succès, avec des broyeurs SAG et à billes testés à pleine vitesse de fonctionnement. Les stocks de minerai en surface approchent de leur capacité, tandis que le développement de la mine se poursuit.

La direction fournira une mise à jour détaillée de la construction du quatrième trimestre plus tard en janvier, y compris une galerie photo et des coûts généraux mis à jour pour le premier trimestre 2025.

Endeavour Silver (NYSE: EXK; TSX: EDR) berichtete von Verzögerungen bei seinem Terronera-Projekt aufgrund kritischer Probleme mit der Lieferung von Stahlstrukturen im Dezember, was den Baufortschritt und die zeitlichen Abläufe der Inbetriebnahme beeinträchtigt hat. Als Kostenersparnis reduzierte das Unternehmen seine Belegschaft vom 20. Dezember 2024 bis zum 6. Januar 2025.

Die nasse Inbetriebnahme wird jetzt für Anfang Q2 2025 erwartet. Trotz der Verzögerungen ist der Absetzstausee bereit, und die trockene Inbetriebnahme der oberen Plattform wird fortgesetzt. Die Tests des Mahlanlage waren erfolgreich, wobei SAG- und Kugelmühlen mit voller Betriebsgeschwindigkeit getestet wurden. Die Oberflächenlagerstätten nähern sich ihrer Kapazität, während die Minenentwicklung fortgesetzt wird.

Das Management wird später im Januar ein detailliertes Update zur Konstruktion des vierten Quartals bereitstellen, einschließlich einer Fotogalerie und aktualisierten Standortnebenkosten für das erste Quartal 2025.

Positive
  • Successful testing of grinding circuit with SAG and ball mills at full operating speed
  • Tailings dam ready for use
  • Ore stockpiles nearing capacity
  • Mine development and stope preparation continuing on multiple levels
Negative
  • Project delays due to critical structural steel delivery issues
  • Wet commissioning pushed back to early Q2 2025
  • Temporary workforce reduction implemented as cost-saving measure
  • Supply chain interruptions affecting construction progress

Insights

The delay in Terronera's critical structural steel components and subsequent workforce reduction represents a notable setback in Endeavour Silver's project timeline. The shift of wet commissioning to early Q2 2025 impacts the company's near-term production outlook.

Despite these challenges, several positive operational milestones have been achieved:

  • The tailings dam is ready for operation
  • Successful dry commissioning of the upper platform continues
  • Ore stockpiles are approaching capacity
  • SAG and ball mills have passed initial testing

The strategic decision to reduce workforce during the holiday season, while causing a short-term delay, demonstrates prudent cost management. The project's fundamentals remain solid, with key infrastructure components already in place. The temporary setback should be viewed in the context of the broader project timeline, with minimal long-term impact on the mine's overall value proposition.

The construction delays at Terronera exhibit classic critical path disruption symptoms in large-scale mining projects. The convergence of supply chain issues with seasonal transport restrictions created a cascade effect on project timelines.

Key project management insights:

  • The decision to reduce workforce during delays shows adaptive management practices
  • Parallel progress in non-critical path activities (ore stockpiling, mine development) maintains project momentum
  • The successful equipment testing indicates risk mitigation in mechanical systems

In simpler terms: Think of this like building a house - you can't install the roof before the walls are up (critical path), but you can still work on the garden (parallel activities) while waiting for wall materials. The delay is more a timing issue than a fundamental project problem.

VANCOUVER, British Columbia, Jan. 08, 2025 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) provides an update on the progress at its Terronera project.

The Terronera project experienced delivery delays during December of critical path structural steel components required for the lower platform construction and tailing filter area installations. This has adversely impacted overall project productivity and expected commissioning timelines. In light of these delays, management reduced the site workforce over the holiday season from December 20, 2024 to January 6, 2025 as a cost saving measure. The lower platform construction and filter area installation is the critical path to wet commissioning, which is now expected in early Q2 2025.

Following Mexico’s lifting of the transport restrictions, critical steel deliveries and installation resumed this week. The earthworks team has the tailings dam ready for use, and the operational readiness team continues the dry commissioning of the upper platform. Above ground ore stockpiles, including crushed ore are nearing capacity, while the mine personnel will continue stope preparation on multiple levels and advancing mine development. Commissioning of the grinding circuit commenced with SAG and ball mills being successfully tested for multiple hours at full operating speed to check bearing temperatures, vibrations and lubrication systems under no-load conditions.

Management will provide a Q4 construction update similar to previous quarterly updates later this month, including a photo gallery and updated site overhead costs to be incurred over Q1 2025.

Don Gray, Chief Operating Officer commented, “Unfortunately, the revised timing of structural steel deliveries coincided with the holiday season transport restrictions, resulting in supply-chain delivery interruptions and limited availability of key support technicians. Once it was clear that site productivity would be impacted, we felt it prudent to maintain a smaller workforce and temporarily reduce manpower costs. This gave our construction team an opportunity to re-charge for the final effort in bringing Terronera to a successful completion.”

About Endeavour Silver: Endeavour is a mid-tier precious metals company committed to sustainable and responsible mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco State, the Company aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a portfolio of exploration projects in Mexico, Chile, and the United States, which has helped it achieve its goal of becoming a premier senior silver producer. 

Contact Information

Allison Pettit, Director of Investor Relations
Tel: (604) 640 4804
Email: apettit@edrsilver.com
Website: www.edrsilver.com

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding the development of the Terronera project, the anticipated timing of wet commissioning at the Terronera project, the anticipated timing of the Company’s quarterly construction updates, the Terronera project's forecasted operations, costs and expenditures, and the timing and results of various related activities. The Company does not intend to and does not assume any obligation to update forward-looking statements or information other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties, and other factors that may cause Endeavor's actual results, level of activity, production levels, performance, or achievements, and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited changes in production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the USA and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development; risks in obtaining necessary licenses and permits; satisfaction of conditions precedent to drawdown under the project loan debt facility; the ongoing effects of inflation and supply chain issues on the Terronera project economics; fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the Mexican peso, Chilean peso, Canadian dollar and US dollar); and challenges to the Company's title to properties; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the SEC and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to the continued operation of the Company's mining operations, no material adverse change in the market price of commodities forecasted Terronera mine economics as of 2024, mining operations will operate, and the mining products will be completed under management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, other factors may cause results to be materially different from those anticipated, described, estimated, assessed, or intended. There can be no assurance that any forward-looking statements or information will be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.


FAQ

When is the new commissioning date for Endeavour Silver's (EXK) Terronera project?

The wet commissioning of the Terronera project is now expected in early Q2 2025, following delays in structural steel deliveries.

What caused the delays at EXK's Terronera project in December 2024?

The delays were caused by delivery issues of critical path structural steel components required for the lower platform construction and tailing filter area installations, compounded by Mexico's holiday season transport restrictions.

How did EXK respond to the Terronera project delays in December 2024?

EXK reduced the site workforce from December 20, 2024, to January 6, 2025, as a cost-saving measure in response to the delays.

What is the current status of the grinding circuit testing at EXK's Terronera project?

The grinding circuit commissioning has begun, with SAG and ball mills successfully tested for multiple hours at full operating speed under no-load conditions.

When will EXK release the next Terronera construction update?

Management will provide a Q4 construction update later in January 2025, including a photo gallery and updated site overhead costs for Q1 2025.

Endeavour Silver Corp.

NYSE:EXK

EXK Rankings

EXK Latest News

EXK Stock Data

931.21M
261.87M
0.16%
37.62%
4.33%
Other Precious Metals & Mining
Basic Materials
Link
United States of America
Vancouver