E3 Lithium Provides Update on the Clearwater Project and 2025 Demonstration Plant Development Plans
E3 Lithium has outlined its 2025 corporate priorities for advancing the Clearwater Project toward commercial lithium production. The company is making two key changes to its project design: focusing initially on battery-quality lithium carbonate production and implementing a phased approach with three 12,000-tonne/year phases to reduce capital requirements and accelerate timelines.
In 2025, E3 will focus on five initiatives: advancing Phase 1 engineering for the commercial plant, constructing a demonstration facility with Canada's first scaled-up DLE system, submitting environmental applications to Alberta regulators, developing strategic partnerships, and building stakeholder support.
The demonstration facility will operate in three phases to validate the production process, with commissioning expected in early Q3 2025. The company aims to make the Clearwater Project 'shovel ready' by 2026, with permits potentially in place by mid-2026.
E3 highlights Alberta's advantages for lithium development, including its regulatory framework, skilled workforce, and infrastructure. The company reports approximately $18.4 million in working capital and $23 million in undrawn grants at the end of 2024.
E3 Lithium ha delineato le sue priorità aziendali per il 2025 per far avanzare il Progetto Clearwater verso la produzione commerciale di litio. L'azienda sta apportando due modifiche chiave al design del progetto: concentrarsi inizialmente sulla produzione di carbonato di litio di qualità per batterie e implementare un approccio a fasi con tre fasi da 12.000 tonnellate/anno per ridurre i requisiti di capitale e accelerare i tempi.
Nel 2025, E3 si concentrerà su cinque iniziative: avanzare l'ingegneria della Fase 1 per l'impianto commerciale, costruire un impianto dimostrativo con il primo sistema DLE su scala in Canada, presentare domande ambientali ai regolatori dell'Alberta, sviluppare partnership strategiche e costruire supporto tra le parti interessate.
Il impianto dimostrativo opererà in tre fasi per convalidare il processo di produzione, con l'avvio previsto all'inizio del terzo trimestre del 2025. L'azienda mira a rendere il Progetto Clearwater 'pronto per l'uso' entro il 2026, con permessi potenzialmente in atto entro metà 2026.
E3 evidenzia i vantaggi dell'Alberta per lo sviluppo del litio, inclusi il suo quadro normativo, la forza lavoro qualificata e l'infrastruttura. L'azienda riporta circa 18,4 milioni di dollari in capitale circolante e 23 milioni di dollari in sovvenzioni non utilizzate alla fine del 2024.
E3 Lithium ha delineado sus prioridades corporativas para 2025 para avanzar en el Proyecto Clearwater hacia la producción comercial de litio. La empresa está realizando dos cambios clave en el diseño del proyecto: enfocarse inicialmente en la producción de carbonato de litio de calidad para baterías e implementar un enfoque por fases con tres fases de 12,000 toneladas/año para reducir los requisitos de capital y acelerar los plazos.
En 2025, E3 se centrará en cinco iniciativas: avanzar en la ingeniería de la Fase 1 para la planta comercial, construir una instalación de demostración con el primer sistema DLE a gran escala de Canadá, presentar solicitudes ambientales a los reguladores de Alberta, desarrollar asociaciones estratégicas y construir apoyo entre las partes interesadas.
La instalación de demostración operará en tres fases para validar el proceso de producción, con la puesta en marcha prevista a principios del tercer trimestre de 2025. La empresa tiene como objetivo hacer que el Proyecto Clearwater esté 'listo para la acción' para 2026, con permisos que potencialmente estarán en su lugar a mediados de 2026.
E3 destaca las ventajas de Alberta para el desarrollo del litio, incluido su marco regulatorio, su mano de obra calificada y su infraestructura. La empresa informa de aproximadamente 18.4 millones de dólares en capital de trabajo y 23 millones de dólares en subvenciones no utilizadas a finales de 2024.
E3 리튬은 상업적 리튬 생산을 위한 Clearwater 프로젝트를 추진하기 위한 2025년 기업 우선사항을 설명했습니다. 회사는 프로젝트 설계에 두 가지 주요 변경 사항을 도입하고 있습니다: 처음에는 배터리 품질 리튬 탄산염 생산에 집중하고, 자본 요구 사항을 줄이고 일정을 가속화하기 위해 세 개의 12,000톤/년 단계로 단계적 접근 방식을 구현하는 것입니다.
2025년에는 E3가 다섯 가지 이니셔티브에 집중할 것입니다: 상업 공장의 1단계 엔지니어링을 진행하고, 캐나다 최초의 대규모 DLE 시스템을 갖춘 시연 시설을 건설하며, 앨버타 규제 기관에 환경 신청서를 제출하고, 전략적 파트너십을 개발하며, 이해관계자 지원을 구축하는 것입니다.
시연 시설은 생산 프로세스를 검증하기 위해 세 단계로 운영되며, 2025년 3분기 초에 가동될 예정입니다. 회사는 2026년까지 Clearwater 프로젝트를 '사용 준비 완료' 상태로 만들고, 2026년 중반까지 허가가 가능할 것으로 예상하고 있습니다.
E3는 리튬 개발을 위한 앨버타의 이점을 강조하며, 여기에는 규제 프레임워크, 숙련된 인력 및 인프라가 포함됩니다. 회사는 2024년 말 기준으로 약 1,840만 달러의 운영 자본과 2,300만 달러의 미사용 보조금을 보고하고 있습니다.
E3 Lithium a défini ses priorités d'entreprise pour 2025 afin de faire avancer le Projet Clearwater vers une production commerciale de lithium. L'entreprise apporte deux changements clés à la conception de son projet : se concentrer initialement sur la production de carbonate de lithium de qualité pour batteries et mettre en œuvre une approche par étapes avec trois phases de 12 000 tonnes/an pour réduire les besoins en capital et accélérer les délais.
En 2025, E3 se concentrera sur cinq initiatives : faire progresser l'ingénierie de la Phase 1 pour l'usine commerciale, construire une installation de démonstration avec le premier système DLE à grande échelle du Canada, soumettre des demandes environnementales aux régulateurs de l'Alberta, développer des partenariats stratégiques et construire un soutien des parties prenantes.
L'installation de démonstration fonctionnera en trois phases pour valider le processus de production, avec une mise en service prévue au début du troisième trimestre 2025. L'entreprise vise à rendre le Projet Clearwater 'prêt à l'emploi' d'ici 2026, avec des permis potentiellement en place d'ici le milieu de 2026.
E3 souligne les avantages de l'Alberta pour le développement du lithium, y compris son cadre réglementaire, sa main-d'œuvre qualifiée et son infrastructure. L'entreprise rapporte environ 18,4 millions de dollars de fonds de roulement et 23 millions de dollars de subventions non utilisées à la fin de 2024.
E3 Lithium hat seine Unternehmensprioritäten für 2025 umrissen, um das Clearwater-Projekt in Richtung kommerzielle Lithiumproduktion voranzutreiben. Das Unternehmen nimmt zwei wesentliche Änderungen an seinem Projektdesign vor: zunächst auf die Produktion von Batterie-Qualitäts-Lithiumcarbonat zu fokussieren und einen phasenweisen Ansatz mit drei Phasen von 12.000 Tonnen/Jahr umzusetzen, um die Kapitalanforderungen zu senken und die Zeitpläne zu beschleunigen.
Im Jahr 2025 wird sich E3 auf fünf Initiativen konzentrieren: die Ingenieurarbeiten der Phase 1 für die kommerzielle Anlage voranzutreiben, eine Demonstrationsanlage mit dem ersten großangelegten DLE-System in Kanada zu bauen, Umweltanträge bei den Regulierungsbehörden in Alberta einzureichen, strategische Partnerschaften zu entwickeln und die Unterstützung der Interessengruppen auszubauen.
Die Demonstrationsanlage wird in drei Phasen betrieben, um den Produktionsprozess zu validieren, wobei die Inbetriebnahme für Anfang des dritten Quartals 2025 erwartet wird. Das Unternehmen strebt an, das Clearwater-Projekt bis 2026 'einsatzbereit' zu machen, wobei Genehmigungen möglicherweise bis Mitte 2026 vorliegen.
E3 hebt die Vorteile Albertas für die Lithiumentwicklung hervor, einschließlich des regulatorischen Rahmens, der qualifizierten Arbeitskräfte und der Infrastruktur. Das Unternehmen berichtet von etwa 18,4 Millionen Dollar an Betriebskapital und 23 Millionen Dollar an nicht abgerufenen Zuschüssen zum Ende des Jahres 2024.
- Phased approach reduces initial capital requirements and accelerates timeline to production
- Demonstration facility expected to be commissioned by early Q3 2025
- Company has $18.4 million in working capital and $23 million in undrawn grants
- Alberta's regulatory review process typically takes less than 12 months
- Project could be 'shovel ready' by mid-2026
- Company achieved 99.71% purity in lithium carbonate production
- Resource includes 16.2 Mt of lithium carbonate equivalent in Measured and Indicated resources
- Enhance Energy has filed an application to inject CO2 into the Leduc Formation in the Bashaw District, which E3 opposes
- Lithium market experienced challenging pricing environment in 2024
- North American EV sales growth slowed to 9% year-over-year
E3 Lithium aims to be one of the few North American projects to produce battery quality lithium products before the end of the decade. With a strong jurisdictional advantage, available and proximal infrastructure, and a world leading permitting system for critical minerals,
In 2025, the Company will focus on five main initiatives as it progresses towards commerciality:
- Advance Phase 1 development of the commercial plant, including engineering for the feasibility study.
- Construct and operate a fully integrated demonstration facility, showcasing Canada’s first scaled-up Direct Lithium Extraction (DLE) system to convert brine to battery quality lithium product.
- Submit the required environmental applications in compliance with Alberta Energy Regulator’s environmental standards and begin the process to license the Clearwater Project Central Processing Facility (CPF) and wells with the Alberta Energy Regulator (AER).
- Meaningfully advance strategic partner and future offtake relationships.
- Continue to build strong stakeholder engagement and support
“We are driving to make the Clearwater Project 'shovel ready' in 2026," said Chris Doornbos, CEO of E3 Lithium. "The demonstration facility is expected to be commissioned in the early part of Q3 2025 and will prove the viability of DLE technology to produce battery-grade lithium at scale. As electrification becomes inevitable and energy security critical, our vast resource strategically positions E3 Lithium to become a major supplier of Canadian lithium to the global battery market.”
Methodical and Accelerated Path to Lithium Production
During 2024, the lithium battery industry saw carbonate-based battery chemistries increase market share. The use case lithium-iron-phosphate (LFP) batteries has increased significantly due to the energy density increases and reduction in costs to about
E3 Lithium is set to make significant progress in 2025, focusing on optimizing the design, construction planning and permitting of its first commercial facility. Following the Clearwater Project Pre-Feasibility Study (PFS), E3 has been evaluating a phased approach for the first project with the goal of reducing the initial capital required and increasing speed to market by reducing the engineering and construction timeframes. From that analysis, E3 is making two fundamental changes to the design of the Clearwater Project:
-
The initial plant design will focus on the production of battery quality lithium carbonate, which is expected to provide the following potential benefits:
- In line with the market shift towards Lithium Iron Phosphate (LFP) and mid-nickel cathodes
- Current and near-term forecasted price for lithium carbonate is near parity with lithium hydroxide
- Decreases project risk and capital by simplifying the facility designs
- Decreases operating costs by removing a number of reagents required
- Simplifies product handling and logistics for the first phase
- Retains optionality to add a hydroxide conversion facility at a later date
-
The Clearwater Project is planned to be built in three phases of 12,000 tonnes per year to assist in the reduction of the initial capital requirements, project risk and help accelerate the timeline to initial production:
- Phase 1 will consist of four DLE trains with a combined production capacity of approximately 12,000 tonnes per year of battery quality lithium carbonate. This will be the focus of the initial engineering.
- Expansion of the Clearwater Project to the full capacity target of 36,000 tonnes per year of lithium carbonate will be developed in future phases.
Permitting Progress
E3 is in the process of building strong relationships with various regulatory agencies and developing the necessary engineering information to submit the facility licenses to operate at the CPF, specifically the AER Directive 56 facility license and Environmental Protection and Enhancement Act (EPEA) applications in compliance with provincial environmental regulations. The Company aims to have these permits submitted by early Q3 of this year. While approval timeframes are hard to predict, historically the review process takes less than 12 months to complete, potentially resulting in a fully permitted CPF in mid-2026.
The associated reservoir production scheme and well licence applications will be submitted to the AER over this time with the goal of having sufficient permits in place to be ready for construction in the second half of 2026. In addition, the Company is actively working to consolidate the freehold minerals rights across the Bashaw District.
The regulatory framework, enhanced by Bill 82 and overseen by the AER, specifically addresses lithium and critical minerals development. The operational model mirrors oil and gas production, utilizing familiar directives for wells, pipelines, facilities, and environmental protection. This alignment, combined with
Enhance Energy Inc. has submitted an application to the AER for approval to inject CO2 into the Leduc Formation in the Woodbend Group in the northern section of the Bashaw District. E3, and as many as 35 freehold mineral rights holders, have filed their opposition to the application. Brine hosted minerals can create significant value for Alberta’s taxpayers and the conservation of Alberta’s resources are of paramount importance. The path forward should be as easy as co-production of lithium with subsequent injection of CO2 or Enhance could dispose of CO2 in one of the many aquifers that do not hold mineral value as the
2025 Fully Integrated Demonstration Facility
The Demonstration Facility (“Demo Facility”) will be built to demonstrate the operations of continuous brine production to battery quality lithium carbonate. The Demo Facility will collect continuous data and demonstrate that the process can operate at commercial scale. The battery quality lithium carbonate can then be provided to potential customers for pre-qualification.
The Demo Facility will utilize brine from a full-size commercial production and injection well pair and will consist of two DLE systems to confirm various components of the process. Each of these DLE systems will tie into the concentration and purification processes which lead to the carbonation equipment currently operating in the E3 laboratory which will be relocated to the Demo Facility site.
The two DLE systems include:
- A 30-column process optimization skid with a 12 m3/day brine flowrate, which will operate a valve array and computer control system that mimics the commercial design from a process operations perspective.
- A full-size single commercial column with a maximum 800 m3/day brine flowrate, which will operate in the same manner and volume as the planned commercial design to confirm recoveries and operating details. This aims to provide commercial scale data that will be applied directly to the full-scale design.
Lithium chloride from each DLE system will be further refined through filtration and polishing equipment to produce highly concentrated and purified lithium chloride. The lithium chloride will then be converted to battery quality lithium carbonate using the equipment currently operating at the E3 laboratory which has achieved a battery quality purity of
The surface facility will be paired with a full-scale operation of a production and injection well pair outlining the brine production flow rates, including a detailed analysis of the aquifer through tracers, to confirm the final reservoir development plan.
The Demo Facility will be operated in three phases:
Phase 1: Commissioning
- The 30 column DLE system, along with the purification equipment, all currently being manufactured, is being built to replicate the process operations of the commercial system.
- This system will be paired with the lithium carbonation equipment already operational.
- This commissioning will be completed with previously produced brine to minimize risk and ensure proper operations.
- Phase 1 commissioning will conclude upon confirmation of the successful production of battery-grade lithium carbonate.
Phase 2: Wells and 30 column DLE Demonstration Facility Operations
- Drilling of two wells for the production test will occur within the Clearwater Project Area.
- Upon drilling and well completion, the wells will be tied into the Demo Facility to enable continuous operations on-site.
- The wells and 30 column DLE system, along with the downstream processing into lithium carbonate, will operate to confirm the data required for the Feasibility Study and the continuous production of battery quality lithium carbonate.
Phase 3: Full Scale Single Column Operation
- Following the successful completion of Phase 2, the full-size single commercial column DLE system will commence fully integrated operations.
- The purpose of this system is to outline the performance modelled “at” commercial scale by operating a single full-size commercial column. This is important to support project financing and strategic partner conversations.
Following the successful commissioning and data collection phase, both DLE systems will likely operate as needed for several years, feeding the purification and carbonation system to regularly produce battery quality lithium carbonate for pre-qualification.
Advance Strategic Partnerships & Offtake Agreements
E3 Lithium continues to progress discussions with potential customers in the automotive, battery cathode and battery cell sectors, as well as within the energy and mining space. E3’s goal is to secure a strategic partner for the project, either through an offtake agreement or through direct project participation. E3 offers one of the nearest to construction, battery quality lithium projects in
E3 is actively engaged in conversations with other industry participants with a focus on advancing our relationships built over the years to secure a partner that values a long-life project within a secure and stable jurisdiction to bolster their value chain or to provide an entry into the lithium industry. With supply of critical minerals, especially lithium, increasingly becoming a focal point for global energy and national security, projects such as the Clearwater Project are well positioned to attract interest.
Strategic Assets for Future Value Creation:
With the technical demonstration of lithium production in
- South Bashaw: Working with Pure Lithium to advance the integration of a battery production processes using E3’s brine and processing technology. Upon successful completion of this work, the companies will look towards commercialization, which could include a joint venture development on the South Bashaw area.
-
North Bashaw: North of the Clearwater Project, E3 holds similar sized resources with similar potential as the
Clearwater . E3 is working on a Pre-Feasibility Study across a portion of this area that may outline additional value and continuation of adding to our significant reserve base. -
Saskatchewan Lithium: E3 Lithium's strategic position in the Estevan lithium belt presents additional value creation opportunities. The Company will evaluate strategic options for these assets while maintaining focus on
Alberta development. - Garrington: The western trend of the Leduc Aquifer held by E3 also hosts substantial lithium-enriched brine and lithium resources. A Resource update is planned for mid-2025 that will incorporate the full aquifer trend, informing future development strategies.
- Nisku Aquifer: Situated above the Leduc Aquifer, historic sampling has outlined similar lithium concentrations in the Nisku Aquifer. The Company will evaluate the potential for co-production and additional unique production opportunities to increase well rate and enhance potential project economics by reducing capital requirements.
Market Information
During 2024, the lithium development industry experienced significant M&A activity with General Motors, Rio Tinto, Equinor, Volkswagen and others entering the space in a meaningful way. In the automotive industry, global sales of Electric Vehicles grew at
With the lithium market beginning to stabilize and the forecast growth in the EV and ESS segments remaining robust, the expected demand for lithium is continually rising. This, combined with the challenging pricing environment for lithium in 2024, has led to a slow down in the development of some projects leading to a lag in new supply of battery quality lithium products. As a result, market analysts predict that the demand for lithium will remain strong through the end of the decade and beyond3.
E3 Lithium's Strengths Going into 2025
Financial Position: E3 has approximately
Governmental Agency Support: E3 Lithium is grateful to have received strong support from several government agencies including Emissions Reduction Alberta -
First-Mover Advantage in a Friendly Resource Development Jurisdiction: E3 Lithium combines several key competitive advantages that position us as the leader in
-
World-Class Resource: The broader Bashaw District hosts one of
Canada's largest sources of lithium resources with 16.2 Mt of lithium carbonate equivalent (LCE) in Measured and Indicated resources, capable of supporting multiple commercial facilities. The potential production of approximately 200,000 tonnes of battery-grade lithium annually with an estimated 50-year life, will position E3 as a significant long-term, secure source of lithium forCanada , US, EU andAsia . -
First to Market in
Canada : E3 is strategically positioned to beCanada's first lithium-in-brine producer, addressing critical North American supply shortages where regional demand significantly outpaces current production. The Clearwater Project will integrate DLE technology with standard downstream chemical conversion to produce battery-grade lithium carbonate, marking a first forCanada's critical minerals sector and complimenting Canadian national security initiatives. -
Premier Regulatory Framework: Operating in
Alberta's established regulatory environment, E3 benefits from the new Mineral Resource Development Act and associated Brine-hosted Mineral Resource Development Rules. This streamlined framework is leading the industry and sets a clear approval process with well-established permitting timelines. With the permitting inAlberta , we have the opportunity to be shovel ready by mid-2026, putting us as one of the few battery grade lithium projects to be able to get off the ground before the end of the decade. -
Superior Infrastructure Foundation: We have secured an option to purchase land for the CPF in
Central Alberta for the Clearwater Project. This preferred site is strategically located to leverage existing essential infrastructure, including accessible utilities and roadways, a skilled workforce and an established service sector. This mature industrial ecosystem significantly reduces capital requirements and accelerates development timelines compared to greenfield projects.
ON BEHALF OF THE BOARD OF DIRECTORS
Chris Doornbos, President & CEO
E3 Lithium Ltd.
About E3 Lithium
E3 Lithium is a development company with a total of 16.2 million tonnes of lithium carbonate equivalent (LCE) Measured and Indicated 1 as well as 0.9 million tonnes LCE Inferred mineral resources2 in
1: The Clearwater Project NI 43-101 Pre-Feasibility Study, effective June 20, 2024, is available on the E3 Lithium’s website (https://e3lithium.ca/our-assets/technical-reports/) and SEDAR+ (www.sedarplus.ca).
2: The mineral resource NI 43-101 Technical Report for the North Rocky Property, effective October 27, 2017, identified 0.9 Mt LCE (inferred) and is available on the E3 Lithium’s website (e3lithium.ca/technical-reports) and SEDAR+ (www.sedarplus.ca).
3: The mineral resource NI 43-101 Technical Report for the Estevan Lithium District, effective May 23, 2024, identified 2.5 Mt LCE (inferred) and is available on the E3 Lithium’s website (e3lithium.ca/technical-reports) and SEDAR+ (www.sedarplus.ca).
Unless otherwise indicated, Kevin Carroll, P. Eng., Chief Development Officer and a Qualified Person under National Instrument 43-101, has reviewed and is responsible for the technical information contained on this news release.
Forward-Looking and Cautionary Statements
This news release includes certain forward-looking statements as well as management’s objectives, strategies, beliefs and intentions or forward-looking information within the meaning of applicable securities laws. Forward-looking statements are frequently identified by such words as “believe”, “may”, “will”, “plan”, “expect”, “anticipate”, “estimate”, “intend”, “project”, “potential”, “possible” and similar words referring to future events and results. Forward-looking statements are based on the current opinions, expectations, estimates and assumptions of management in light of its experience, perception of historical trends, and results of the PFS, but such statements are not guarantees of future performance. In particular, this news release contains forward-looking information relating to: the estimated mineral resources and mineral resources at the Clearwater Project; expectations regarding the PFS, including statements regarding the results of the PFS and interpretations thereof; expectations concerning the Clearwater Project, including extraction, production, pretreatment, purification, volume reduction and conversion process and features and the expected outcomes thereof; the expected economic performance of the Clearwater Project, including capital costs, operating costs, water usage, land use and carbon emissions; statements regarding the Company’s strategy for minimizing environmental impact and liquid waste and maximizing water reuse, with no planned tailings or waste piles; the potential for a secondary revenue stream should the Company be able to sell the calcium carbonate generated during the production of lithium hydroxide; plans and objectives of management for the Company’s operations and the Clearwater Project; and the inherent hazards associated with mineral exploration and mining operations. In preparing the forward-looking information in this news release, the Company has applied several material assumptions, including, but not limited to, that any additional financing needed will be available on reasonable terms; the exchange rates for the
All forward-looking information (including future-orientated financial information) is inherently uncertain and subject to a variety of assumptions, risks and uncertainties, including the speculative nature of mineral exploration and development, fluctuating commodity prices, the effectiveness and feasibility of emerging lithium extraction technologies which have not yet been tested or proven on a commercial scale or on the Company’s brine, risks related to the availability of financing on commercially reasonable terms and the expected use of proceeds; operations and contractual obligations; changes in estimated mineral reserves or mineral resources; future prices of lithium and other metals; availability of third party contractors; availability of equipment; failure of equipment to operate as anticipated; accidents, effects of weather and other natural phenomena and other risks associated with the mineral exploration industry; the Company’s lack of operating revenues; currency fluctuations; risks related to dependence on key personnel; estimates used in financial statements proving to be incorrect; competitive risks and the availability of financing, as described in more detail in our recent securities filings available under the Company’s profile on SEDAR+ at www.sedarplus.ca. Actual events or results may differ materially from those projected in the forward-looking statements and we caution against placing undue reliance thereon. We assume no obligation to revise or update these forward-looking statements except as required by applicable law.
1 Reuters: Battery cell prices fall to record low in September, Oct 30, 2024
2 Benchmark Mineral Intelligence Q4 2024 Lithium Forecast Report
3 Rho Motion: Over 17 million EVs sold in 2024 – Record Year, January 14, 2025
4 Mordor Intelligence: North America Battery Energy Storage System Market Size & Share Analysis - Growth Trends & Forecasts
View source version on businesswire.com: https://www.businesswire.com/news/home/20250225161678/en/
E3 Lithium - Investor Relations
Alexis de la Renaudiere
Investor Relations
investor@e3lithium.ca
587-324-2775
E3 Lithium - Media Inquiries
Kati Dolyniuk
External Relations
communications@e3lithium.ca
587-324-2775
Source: E3 Lithium Ltd.
FAQ
What changes is E3 Lithium making to the Clearwater Project design for 2025?
When will E3 Lithium's demonstration facility be operational?
What is the timeline for E3 Lithium's EEMMF Clearwater Project to be 'shovel ready'?
How much working capital does E3 Lithium (EEMMF) have available?
What is E3 Lithium's production capacity target for the Clearwater Project?
What purity level has E3 Lithium (EEMMF) achieved for its lithium carbonate?