STOCK TITAN

Dominion Energy Successfully Completes First Monopile Installation Season for On-Time and On-Budget Coastal Virginia Offshore Wind

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

Dominion Energy has successfully completed its first monopile installation season for the Coastal Virginia Offshore Wind (CVOW) project, installing 78 monopile foundations and 4 offshore substation foundations. The 2.6-gigawatt project, located 27 miles off Virginia Beach, is 43% complete and remains on-budget and on schedule for completion in late 2026. The project will include 176 turbines capable of powering 660,000 homes and is expected to generate $3 billion in fuel savings over its first decade. The next installation season begins May 2025, with current focus on substation installation and cable laying. Nearly 1,000 Virginia-based workers are currently engaged in the project.

Dominion Energy ha completato con successo la sua prima stagione di installazione di monopali per il progetto Coastal Virginia Offshore Wind (CVOW), installando 78 fondazioni per monopali e 4 fondazioni per sottostazioni offshore. Il progetto da 2,6 gigawatt, situato a 27 miglia da Virginia Beach, è completato al 43% e rimane nei tempi e nel budget previsti per il completamento entro la fine del 2026. Il progetto includerà 176 turbine in grado di fornire energia a 660.000 abitazioni e si prevede che genererà un risparmio di carburante di 3 miliardi di dollari nel suo primo decennio. La prossima stagione di installazione inizia a maggio 2025, con un focus attuale sull'installazione delle sottostazioni e il posizionamento dei cavi. Quasi 1.000 lavoratori basati in Virginia sono attualmente coinvolti nel progetto.

Dominion Energy ha completado con éxito su primera temporada de instalación de monopilas para el proyecto Coastal Virginia Offshore Wind (CVOW), instalando 78 fundaciones de monopilas y 4 fundaciones de subestaciones marinas. El proyecto de 2.6 gigavatios, ubicado a 27 millas de Virginia Beach, está completado en un 43% y se mantiene dentro del presupuesto y del calendario previsto para su finalización a finales de 2026. El proyecto incluirá 176 turbinas capaces de alimentar 660,000 hogares y se espera que genere 3 mil millones de dólares en ahorros de combustible durante su primera década. La próxima temporada de instalación comenzará en mayo de 2025, con un enfoque actual en la instalación de subestaciones y el tendido de cables. Casi 1,000 trabajadores de Virginia están actualmente involucrados en el proyecto.

도미니언 에너지코스탈 버지니아 해상 풍력(CVOW) 프로젝트의 첫 번째 모노파일 설치 시즌을 성공적으로 완료하고, 78개의 모노파일 기초와 4개의 해상 변전소 기초를 설치했습니다. 이 2.6GW 프로젝트는 버지니아 비치에서 27마일 떨어진 곳에 위치하고 있으며, 현재 43% 완료되었으며, 예산 범위와 일정에 맞추어 2026년 말에 완공될 예정입니다. 이 프로젝트는 660,000 가구에 전력을 공급할 수 있는 176개의 풍력 터빈을 포함하며, 첫 10년 동안 30억 달러의 연료 절약 효과가 예상됩니다. 다음 설치 시즌은 2025년 5월에 시작되며, 현재 변전소 설치 및 케이블 배치에 집중하고 있습니다. 현재 약 1,000명의 버지니아 주 노동자가 이 프로젝트에 참여하고 있습니다.

Dominion Energy a réussi à compléter sa première saison d'installation de monopieux pour le projet Coastal Virginia Offshore Wind (CVOW), en installant 78 fondations de monopieux et 4 fondations de sous-stations offshore. Le projet de 2,6 gigawatts, situé à 27 miles de Virginia Beach, est achevé à 43 % et reste dans les limites du budget et du calendrier pour une finalisation prévue fin 2026. Le projet comprendra 176 éoliennes capables d'alimenter 660 000 foyers et devrait générer 3 milliards de dollars d'économies de carburant au cours de sa première décennie. La prochaine saison d'installation débutera en mai 2025, avec un accent actuel sur l'installation de sous-stations et le tirage de câbles. Près de 1 000 travailleurs basés en Virginie sont actuellement engagés dans le projet.

Dominion Energy hat die erste Saison der Monopile-Installation für das Projekt Coastal Virginia Offshore Wind (CVOW) erfolgreich abgeschlossen und 78 Monopile-Stiftungen sowie 4 Offshore-Umspannwerksfundamente installiert. Das 2,6-Gigawatt-Projekt, das 27 Meilen vor Virginia Beach liegt, ist zu 43% abgeschlossen und bleibt im Budget sowie im Zeitplan, um Ende 2026 fertiggestellt zu werden. Das Projekt umfasst 176 Turbinen, die in der Lage sind, 660.000 Haushalte mit Strom zu versorgen, und es wird erwartet, dass es in seinem ersten Jahrzehnt 3 Milliarden Dollar an Kraftstoffeinsparungen generiert. Die nächste Installationssaison beginnt im Mai 2025, wobei der aktuelle Fokus auf der Installation der Umspannwerke und dem Verlegen der Kabel liegt. Fast 1.000 Arbeiter aus Virginia sind derzeit an dem Projekt beteiligt.

Positive
  • Project remains on-budget and on schedule for 2026 completion
  • Exceeded installation targets with 78 monopile foundations installed
  • Project will power 660,000 homes when complete
  • Expected to generate $3 billion in fuel savings over first 10 years
  • Created nearly 1,000 local jobs with more expected for operations
Negative
  • None.

Insights

The successful installation of 78 monopile foundations for the 2.6-gigawatt CVOW project marks significant progress in America's largest offshore wind development. The project's on-time, on-budget status at 43% completion demonstrates strong execution capabilities. Expected fuel savings of $3 billion over the first decade of operation represents substantial customer value. The scale of employment creation (800+ Hampton Roads workers) and the project's capacity to power 660,000 homes positions this as a transformative infrastructure development. The regulated utility model proves viable for large-scale offshore wind, potentially setting a precedent for future projects. The systematic approach to construction and clear timeline for completion in 2026 suggests well-managed project risk.

This milestone reinforces Dominion Energy's strategic positioning in the renewable energy sector. The project's scale and execution demonstrate the company's ability to manage complex infrastructure projects while maintaining financial discipline. The regulated nature of the project provides revenue stability and predictable returns, important for investor confidence. The creation of long-term maintenance jobs and substantial fuel cost savings enhances the company's ESG profile while building sustainable competitive advantages in the growing offshore wind sector. This progress strengthens Dominion's market position as a leader in regulated clean energy infrastructure.
  • Exceeded initial objectives with 78 monopile foundations and 4 offshore substation foundations safely installed since May 22
  • Second installation season begins May 2025
  • CVOW is fully permitted by state and federal authorities, remains on-budget and on schedule to complete construction in late 2026

RICHMOND, Va., Nov. 1, 2024 /PRNewswire/ -- Dominion Energy announced today that 78 monopile foundations and 4 offshore substation foundations were installed for the 2.6-gigawatt Coastal Virginia Offshore Wind (CVOW) project during the first installation season, achieving the company's initial objectives of at least 70 monopiles set into the sea floor 27 miles off the coast of Virginia Beach.

CVOW, the largest offshore wind project under construction in the United States, will consist of 176 turbines that will generate enough clean, renewable energy to power up to 660,000 homes and is expected to generate fuel savings of $3 billion for customers during the first 10 years of operation.

CVOW construction remains on-budget and on schedule to be complete in late 2026. The project is now 43 percent complete. For the next few months, the company will focus on installation of the first offshore substation, continued export cable lays and onshore transmission construction, and placement of transition pieces on top of monopiles in preparation for turbine installation starting in 2025.

"Our Coastal Virginia Offshore Wind project shows that regulated offshore wind works in the United States," said Robert M. Blue, Dominion Energy's chair, president and chief executive officer. "As we face unprecedented customer demand, offshore wind is critical to our diverse, all-of-the-above generation mix to keep the lights on for our customers with affordable, reliable and increasingly clean energy."

The monopile foundations, which are being staged at Portsmouth Marine Terminal, are single vertical, steel cylinders manufactured by global leader EEW SPC and are being installed into the sea floor to support the wind turbine generators supplied by Siemens Gamesa Renewable Energy. Consistent with the project construction schedule, monopile installations will resume in May 2025. 

Offshore wind's economic development and jobs benefits are transformative for Hampton Roads and the Commonwealth. Nearly 1,000 Virginia-based workers – more than 800 in the Hampton Roads region – have been engaged on the CVOW project or with other businesses supporting CVOW. More than 1,000 local jobs will be needed to support ongoing operations and maintenance of this facility after the project begins commercial operation.

About Dominion Energy
Dominion Energy (NYSE: D), headquartered in Richmond, Va., provides regulated electricity service to 3.6 million homes and businesses in Virginia, North Carolina, and South Carolina, and regulated natural gas service to 500,000 customers in South Carolina. The company is one of the nation's leading developers and operators of regulated offshore wind and solar power and the largest producer of carbon-free electricity in New England. The company's mission is to provide the reliable, affordable, and increasingly clean energy that powers its customers every day. Please visit DominionEnergy.com to learn more.

This release contains certain forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995 that are subject to various risks and uncertainties. These factors are identified in Dominion Energy's Forms 10-K and 10-Q filed with the U.S. Securities and Exchange Commission. Dominion Energy refers readers to those reports for further information. Any forward-looking statement speaks only as of the date on which it is made, and Dominion Energy undertakes no obligation to update any forward-looking statement to reflect events or circumstances occurring after the date on which it is made.

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/dominion-energy-successfully-completes-first-monopile-installation-season-for-on-time-and-on-budget-coastal-virginia-offshore-wind-302294178.html

SOURCE Dominion Energy

FAQ

How many monopile foundations has Dominion Energy (D) installed in the CVOW project?

Dominion Energy has installed 78 monopile foundations and 4 offshore substation foundations during the first installation season.

When will Dominion Energy (D) complete the CVOW offshore wind project?

The CVOW project is scheduled to complete construction in late 2026 and is currently 43% complete.

How many homes will Dominion Energy's (D) CVOW project power?

The CVOW project will generate enough clean, renewable energy to power up to 660,000 homes.

When does the second installation season for Dominion Energy's (D) CVOW project begin?

The second monopile installation season will begin in May 2025.

Dominion Energy, Inc.

NYSE:D

D Rankings

D Latest News

D Stock Data

46.66B
751.89M
0.12%
77.05%
1.82%
Utilities - Regulated Electric
Electric Services
Link
United States of America
RICHMOND