Calibre Discovers Significant Gold Mineralization 1,000 metres Beyond the Valentine Gold Mine Resource, Newfoundland & Labrador, Canada; Drilling Intercepts Include 2.43 g/t Gold over 172.8 metres, 2.12 g/t Gold over 95.4 metres and 2.26 g/t Gold over 78.3 metres
Calibre Mining announces significant gold discoveries at its Valentine Gold Mine in Newfoundland & Labrador, extending 1,000 metres beyond known resources. Notable drill results include 2.43 g/t gold over 172.8 metres, 2.12 g/t gold over 95.4 metres, and 2.26 g/t gold over 78.3 metres at the Frank Zone. The Valentine project, currently 85% complete, is on track for first gold production in Q2 2025, targeting approximately 200,000 ounces annually for 12 years. The property hosts 3.95 Moz of Measured and Indicated Resources and 1.10 Moz of Inferred Resources across only 8 km of the 32 km Valentine Lake Shear Zone.
Calibre Mining annuncia importanti scoperte d'oro presso la sua Miniera di Oro Valentine in Newfoundland e Labrador, estendendosi per 1.000 metri oltre le risorse conosciute. I risultati di perforazione notevoli comprendono 2,43 g/t d'oro su 172,8 metri, 2,12 g/t d'oro su 95,4 metri e 2,26 g/t d'oro su 78,3 metri nella Zona Frank. Il progetto Valentine, attualmente completato all'85%, è sulla buona strada per la prima produzione d'oro nel secondo trimestre del 2025, con l'obiettivo di circa 200.000 once all'anno per 12 anni. La proprietà ospita 3,95 Moz di Risorse Misurate e Indicate e 1,10 Moz di Risorse Inferite su soli 8 km dei 32 km della Zona di Lacerazione di Valentine Lake.
Calibre Mining anuncia importantes descubrimientos de oro en su Mina de Oro Valentine en Terranova y Labrador, extendiéndose 1.000 metros más allá de los recursos conocidos. Los resultados de perforación notables incluyen 2,43 g/t de oro sobre 172,8 metros, 2,12 g/t de oro sobre 95,4 metros y 2,26 g/t de oro sobre 78,3 metros en la Zona Frank. El proyecto Valentine, actualmente completado en un 85%, está en camino para la primera producción de oro en el segundo trimestre de 2025, con un objetivo de aproximadamente 200.000 onzas anuales durante 12 años. La propiedad alberga 3,95 Moz de Recursos Medidos e Indicados y 1,10 Moz de Recursos Inferidos a lo largo de solo 8 km de los 32 km de la Zona de Cizalla Valentine Lake.
칼리브르 마이닝이 뉴펀들랜드와 래브라도의 발렌타인 금광에서 1,000 미터 이상에 걸쳐 중요한 금 발견을 발표했습니다. 주목할 만한 시추 결과로는 172.8 미터에서 2.43 g/t 금, 95.4 미터에서 2.12 g/t 금, 78.3 미터에서 2.26 g/t 금이 포함되어 있습니다. 현재 85% 완료된 발렌타인 프로젝트는 2025년 2분기에 첫 금 생산을 목표로 하고 있으며, 연간 약 200,000 온스를 12년 동안 목표로 하고 있습니다. 이 자산은 발렌타인 호수 절리대의 32km 중 단 8km에서 3.95 Moz의 측정 및 지시된 자원과 1.10 Moz의 추정 자원을 보유하고 있습니다.
Calibre Mining annonce d'importantes découvertes d'or dans sa mine d'or Valentine à Terre-Neuve et Labrador, s'étendant sur 1.000 mètres au-delà des ressources connues. Les résultats de forage notables comprennent 2,43 g/t d'or sur 172,8 mètres, 2,12 g/t d'or sur 95,4 mètres et 2,26 g/t d'or sur 78,3 mètres dans la zone Frank. Le projet Valentine, actuellement achevé à 85 %, est en bonne voie pour une première production d'or au deuxième trimestre de 2025, visant environ 200 000 onces par an pendant 12 ans. La propriété abrite 3,95 Moz de ressources mesurées et indiquées et 1,10 Moz de ressources inférées sur seulement 8 km des 32 km de la zone de cisaillement de Valentine Lake.
Calibre Mining gibt bedeutende Goldentdeckungen in seiner Valentine-Goldmine in Neufundland und Labrador bekannt, die sich 1.000 Meter über die bekannten Ressourcen hinaus erstrecken. Bemerkenswerte Bohrergebnisse umfassen 2,43 g/t Gold über 172,8 Meter, 2,12 g/t Gold über 95,4 Meter und 2,26 g/t Gold über 78,3 Meter in der Frank-Zone. Das Valentine-Projekt ist derzeit zu 85% abgeschlossen und auf dem besten Weg, im zweiten Quartal 2025 mit der ersten Goldproduktion zu beginnen, mit dem Ziel von etwa 200.000 Unzen jährlich über 12 Jahre. Das Grundstück umfasst 3,95 Moz an gemessenen und angezeigten Ressourcen sowie 1,10 Moz an geschätzten Ressourcen über nur 8 km der 32 km langen Valentine Lake-Shear-Zone.
- Discovery of significant gold mineralization 1,000 metres beyond known resources
- High-grade intercepts including 2.43 g/t Au over 172.8m, 40% above reserve grade
- Construction 85% complete and on schedule for Q2 2025 production
- Project expected to produce 200,000 ounces annually for 12 years
- Mineralization remains open laterally, vertically and up-dip
- None.
VANCOUVER, British Columbia, Nov. 25, 2024 (GLOBE NEWSWIRE) -- Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) (the "Company" or "Calibre") is pleased to announce initial discovery and resource expansion diamond drill results from its Valentine Gold Mine (“Valentine”) located in Newfoundland & Labrador, Canada. The program, part of the expanded 100,000 metre drilling initiative (see News Release dated July 15, 2024), is focused on discovering new gold mineralization beyond the known resources on the 250 km2 property. Launched earlier this year, the drilling highlights (see News Release dated June 5, 2024) the vast potential that exists outside of the three pit 2022 Feasibility Studyi, which includes a total of 64.6 Mt grading 1.90 g/t gold containing 3.95 Moz of Measured and Indicated Resources and 20.7 Mt grading 1.65 g/t gold containing 1.10 Moz of Inferred Resources. These resources are hosted across only 8 km of the highly prospective 32 km long main Valentine Lake Shear Zone (VLSZ). Drill results include numerous intercepts with visible gold and both high grade intersections and broad zones of continuous mineralization have been identified in several holes, all of which are located outside of known mineral resources.
Highlights from the Frank Zone drill program, southwest of the Leprechaun pit include:
- 2.43 g/t Au over 172.8 metres Estimated True Width (“ETW”) including 3.84 g/t Au over 90.9 metres ETW in Hole FZ-24-048;
- 2.12 g/t Au over 95.4 metres ETW in Hole FZ-24-046;
- 2.26 g/t Au over 78.3 metres ETW in Hole FZ-24-040;
- 10.21 g/t Au over 2.9 metres ETW in Hole FZ-24-028;
- 5.50 g/t Au over 6.0 metres ETW in Hole FZ-24-031;
- 1.73 g/t Au over 11.0 metres ETW in Hole FZ-24-034;
- 13.39 g/t Au over 0.9 metres ETW in Hole FZ-24-035;
- 8.34 g/t Au over 1.0 metres ETW in Hole FZ-24-037; and
- 11.15 g/t Au over 0.9 metres ETW in Hole FZ-24-039.
Darren Hall, President and Chief Executive Officer of Calibre, stated: “We acquired the 5-million-ounce Valentine Gold Mine in Canada primarily for its near-term production of approximately 200,000 ounces per year for the first 12 years of its 14-year reserve life. With construction
Since our initial due diligence in 2024, the team has been extremely excited by the highly prospective district potential of the Valentine Gold Mine property, which has a similar geologic setting to the prolific Val d’Or and Timmins camps in the Abitibi gold belt. These initial drill results highlight the significant upside potential for further discoveries and resource expansion. Holes FZ-24-048, 2.43 g/t gold over 172.8 metres, and FZ-24-046, 2.12 g/t gold over 95.4 metres, are very encouraging given the grades and widths, with mineralization importantly remaining open laterally, vertically and up-dip. In just a few months, we’ve discovered broad zones of gold mineralization up to 1,000 metres southwest of the Leprechaun open pit with grades more than
Tom Gallo, Senior Vice President Strategy and Growth of Calibre, stated: “The anticipated discovery potential of the orogenic gold setting of the Valentine Gold Mine property is highlighted by today’s drill results. Hole FZ-24-040 sits approximately 400 metres along strike to the southwest of the Leprechaun open pit followed by another 450 metre step out in Hole FZ-24-046 and a further 150 metres in Hole FZ-24-048. These three intercepts define a 1,000- metre corridor outside of our present mineral resource which is now being defined for future delineation drilling. These results, combined with the previously announced Frank Zone drilling, ultimately define continuous gold mineralization extending nearly 1,500 metres southwest of the Leprechaun resource. Furthermore, gold mineralization in the past has been defined proximal to the Valentine Lake Shear Zone (VLSZ), the main mineralized structure. It is, therefore, extremely encouraging to see intercepts such as in holes FZ-24-028 (10.21 g/t Au over 2.9 metres ETW) and FZ-24- 031 (5.50 g/t Au over 6.0 metres ETW), which have outlined gold mineralization 250-300 metres north of the VLSZ, meaningfully expanding the width of this golden corridor.”
Link 1 - Figures
Link 2 - VRIFY
Link 3 - Drilling Tables
Quality Assurance/Quality Control
QA/QC protocols followed at the Valentine Gold Mine include the insertion of blanks and standards at regular intervals in each sample batch. Drill core is cut in half with one half retained at site, the other half tagged and sent to Eastern Analytical Limited in Springdale, NL. All reported core samples are analyzed for Au by fire assay (30g) with AA finish. All samples above 0.30 g/t Au and those in economically interesting intervals are further assayed using metallic screen to mitigate the presence of coarse gold. Significant mineralized intervals are reported in Table 1 as core lengths and estimated true width (80 -
Qualified Person
The scientific and technical information contained in this news release was approved by Nic Capps, P.Geo., Calibre -
Valentine Gold Mine’s Senior Exploration Manager and a "Qualified Person" under National Instrument 43-101.
About Calibre
Calibre (TSX:CXB) is a Canadian-listed, Americas focused, growing mid-tier gold producer with a strong pipeline of development and exploration opportunities across Newfoundland & Labrador in Canada, Nevada and Washington in the USA, and Nicaragua. Calibre is focused on delivering sustainable value for shareholders, local communities and all stakeholders through responsible operations and a disciplined approach to growth. With a strong balance sheet, a proven management team, strong operating cash flow, accretive development projects and district-scale exploration opportunities, Calibre will unlock significant value.
For further information, please contact:
Ryan King
SVP Corporate Development & IR
T: 604.628.1012
E: calibre@calibremining.com
W: www.calibremining.com
Calibre’s head office is located at Suite 1560, 200 Burrard St., Vancouver, British Columbia, V6C 3L6.
X / Facebook / LinkedIn / YouTube
The Toronto Stock Exchange has neither reviewed nor accepts responsibility for the adequacy or accuracy of this news release.
Cautionary Note Regarding Forward Looking Information
This news release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian securities legislation. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", “assume”, "intend", “strategy”, “goal”, “objective”, “possible” or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. Forward- looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond Calibre's control. For a listing of risk factors applicable to the Company, please refer to Calibre's annual information form (“AIF”) for the year ended December 31, 2023, its management discussion and analysis for the year ended December 31, 2023 and other disclosure documents of the Company filed on the Company’s SEDAR+ profile at www.sedarplus.ca.
Calibre's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. Calibre does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, undue reliance should not be placed on forward-looking statements.
i Footnotes:
Refer to the “Valentine Gold Project NI 43-101 Technical Report and Feasibility Study Newfoundland & Labrador, Canada” effective November 30, 2022 found on Calibre’s website at www.calibremining.com and on SEDAR+ at www.sedarplus.ca.
FAQ