Calibre Announces Q3 & Year to Date 2024 Gold Production; Revises 2024 Guidance With Q4 Expected to Be the Strongest Production of the Year; Valentine Remains Fully Funded and On Track for Q2, 2025 Gold Production
Calibre Mining Corp. announces Q3 and YTD 2024 gold production results and revises 2024 guidance. Key points:
- Q3 consolidated gold sales: 46,076 ounces (Nicaragua: 36,427 oz, Nevada: 9,649 oz)
- YTD consolidated gold sales: 166,200 ounces (Nicaragua: 140,646 oz, Nevada: 25,554 oz)
- 2024 production guidance revised to 230,000-240,000 ounces
- Q4 production expected to be 70,000-80,000 ounces
- Valentine Gold Mine construction 81% complete, on track for Q2 2025 production
- Valentine capital cost increased to C$744 million, fully funded
The company cites lower ore deliveries from Volcan open pit and mine sequencing changes at Limon as reasons for the guidance revision. Despite challenges, Q4 is expected to be the strongest production quarter of the year.
Calibre Mining Corp. annuncia i risultati della produzione di oro per il terzo trimestre e da inizio anno 2024 e rivede le stime per il 2024. Punti chiave:
- Vendite consolidate di oro nel Q3: 46.076 once (Nicaragua: 36.427 oz, Nevada: 9.649 oz)
- Vendite consolidate di oro da inizio anno: 166.200 once (Nicaragua: 140.646 oz, Nevada: 25.554 oz)
- Stima di produzione per il 2024 rivista a 230.000-240.000 once
- Produzione prevista per il Q4 tra 70.000 e 80.000 once
- Costruzione della Miniera d'Oro Valentine completata all'81%, in programma per la produzione nel Q2 2025
- I costi di capitale per Valentine sono aumentati a 744 milioni di dollari canadesi, totalmente finanziati
L'azienda cita il calo delle consegne di minerale dalla miniera a cielo aperto di Volcan e i cambiamenti nella programmazione delle miniere di Limon come motivi per la revisione delle stime. Nonostante le difficoltà, si prevede che il Q4 sarà il trimestre di produzione più forte dell'anno.
Calibre Mining Corp. anuncia los resultados de producción de oro del tercer trimestre y del año hasta la fecha de 2024 y revisa la guía para 2024. Puntos clave:
- Ventas consolidadas de oro en el Q3: 46,076 onzas (Nicaragua: 36,427 oz, Nevada: 9,649 oz)
- Ventas consolidadas de oro hasta la fecha: 166,200 onzas (Nicaragua: 140,646 oz, Nevada: 25,554 oz)
- Proyección de producción para 2024 revisada a 230,000-240,000 onzas
- Producción esperada para el Q4 entre 70,000 y 80,000 onzas
- Construcción de la Mina de Oro Valentine completada en un 81%, a tiempo para la producción en el Q2 de 2025
- El costo de capital de Valentine ha aumentado a 744 millones de dólares canadienses, totalmente financiado
La empresa cita menores entregas de mineral de la mina a cielo abierto de Volcan y cambios en la secuenciación de las minas en Limon como razones para la revisión de las proyecciones. A pesar de los desafíos, se espera que el Q4 sea el trimestre de producción más sólido del año.
칼리브레 마이닝 주식회사는 2024년 3분기 및 연간 금 생산 결과를 발표하고 2024년 가이드를 수정했습니다. 주요 사항:
- 3분기 통합 금 판매량: 46,076 온스 (니카라과: 36,427 oz, 네바다: 9,649 oz)
- 연간 통합 금 판매량: 166,200 온스 (니카라과: 140,646 oz, 네바다: 25,554 oz)
- 2024년 생산 가이드는 230,000-240,000 온스로 수정되었습니다
- 4분기 생산 예상량은 70,000-80,000 온스로 예상됩니다
- 발렌타인 금광 건설 완료율 81%, 2025년 2분기 생산 예정
- 발렌타인 자본 비용이 7억 4400만 캐나다 달러로 증가했으며, 완전히 자금이 조달됨
회사는 볼칸의 노천 광산에서의 원광 인도 감소와 리몬에서의 광산 순서 변경이 가이드 수정의 이유라고 언급했습니다. 어려움에도 불구하고 4분기는 올해 가장 강력한 생산 분기가 될 것으로 예상됩니다.
Calibre Mining Corp. annonce les résultats de la production d'or pour le troisième trimestre et depuis le début de l'année 2024 et révise ses prévisions pour 2024. Points clés :
- Ventes consolidées d'or au T3 : 46 076 onces (Nicaragua : 36 427 oz, Nevada : 9 649 oz)
- Ventes consolidées d'or depuis le début de l'année : 166 200 onces (Nicaragua : 140 646 oz, Nevada : 25 554 oz)
- Prévisions de production pour 2024 révisées à 230 000-240 000 onces
- Production prévue pour le T4 entre 70 000 et 80 000 onces
- Construction de la mine d'or Valentine achevée à 81 %, en bonne voie pour une production au T2 2025
- Coût en capital de Valentine augmenté à 744 millions de dollars canadiens, entièrement financé
L'entreprise cite la baisse des livraisons de minerai de la mine à ciel ouvert de Volcan et les changements de séquençage des mines à Limon comme raisons de la révision des prévisions. Malgré les défis, le T4 est attendu comme le trimestre de production le plus fort de l'année.
Calibre Mining Corp. gibt die Ergebnisse der Goldproduktion für das 3. Quartal und das Jahr bis heute 2024 bekannt und überarbeitet die Prognosen für 2024. Wichtige Punkte:
- Konsolidierte Goldverkäufe im Q3: 46.076 Unzen (Nicaragua: 36.427 oz, Nevada: 9.649 oz)
- Konsolidierte Goldverkäufe bis heute: 166.200 Unzen (Nicaragua: 140.646 oz, Nevada: 25.554 oz)
- Die Produktionsprognose für 2024 wurde auf 230.000-240.000 Unzen überarbeitet
- Die Produktion im Q4 wird voraussichtlich zwischen 70.000 und 80.000 Unzen liegen
- Der Bau der Valentine Goldmine ist zu 81% abgeschlossen und liegt im Zeitplan für die Produktion im Q2 2025
- Die Investitionskosten für Valentine steigen auf 744 Millionen kanadische Dollar, vollständig finanziert
Das Unternehmen führt eine geringere Erzlieferung aus dem Volcan-Tagebau sowie Änderungen in der Reihenfolge der Minen bei Limon als Gründe für die Überarbeitung der Prognosen an. Trotz der Herausforderungen wird erwartet, dass das Q4 das stärkste Produktionsquartal des Jahres wird.
- Q4 production expected to be significantly higher at 70,000-80,000 ounces
- Valentine Gold Mine construction 81% complete and on track for Q2 2025 production
- Valentine project remains fully funded with C$300 million in cash and restricted cash
- Forecast 30,000 ounce stockpile build for processing in 2025
- Ore tonnes and grade from Volcan now aligning with expectations
- 2024 production guidance revised down to 230,000-240,000 ounces from 275,000-300,000 ounces
- Q3 production lower than expected due to higher historical artisanal mining activity at Volcan
- Total Cash Costs revised up to $1,300-$1,350/oz from $1,075-$1,175/oz
- All-In Sustaining Cost revised up to $1,550-$1,600/oz from $1,275-$1,375/oz
- Valentine initial project capital increased to C$744 million from previous estimate
VANCOUVER, British Columbia, Oct. 18, 2024 (GLOBE NEWSWIRE) -- Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) (the "Company" or "Calibre") announces operating results for the three months (“Q3”) and nine months (“year to date” or “YTD”) ended September 30, 2024, updated 2024 guidance and an update on the Valentine Gold Mine (“Valentine”), located in Newfoundland & Labrador, Canada. Calibre will host a conference call to discuss its Q3 operating results, revised full year guidance, and Valentine update this morning, October 18, 2024 at 10 am ET. To view the live webcast of the conference call, please click here. All figures are expressed in U.S. dollars unless otherwise stated.
Q3 & YTD 2024 Production and Preliminary Cost Results
- Consolidated Q3 gold sales of 46,076 ounces; Nicaragua 36,427 ounces and Nevada 9,649 ounces:
- Consolidated Q3 Total Cash Cost1 (“TCC”) of
$1,580 /oz: Nicaragua$1,615 /oz and Nevada$1,451 /oz; and - Consolidated Q3 All-In Sustaining Cost1 (“AISC”) of
$1,946 /oz: Nicaragua$1,880 /oz and Nevada$1,813 /oz.
- Consolidated Q3 Total Cash Cost1 (“TCC”) of
- Consolidated YTD gold sales of 166,200 ounces; Nicaragua 140,646 ounces and Nevada 25,554 ounces:
- Consolidated YTD TCC1 of
$1,379 /oz: Nicaragua$1,364 /oz and Nevada$1,463 /oz; - Consolidated YTD AISC1 of
$1,656 /oz: Nicaragua$1,554 /oz and Nevada$1,734 /oz; and - In addition to the mine sequence changes at Limon Norte discussed in Q2, year-to-date Nicaragua production was impacted due to lower than budgeted ore deliveries from the new Volcan open pit. Full year production from Volcan is expected to be approximately 20,000 ounces below budget because of the higher-than-expected historical artisanal mining activity. However, ore tonnes and grade from Volcan now align with expectations, as the deposit model has been confirmed by infill drilling. In Nevada, lower tonnes stacked impact metal production by approximately 5,000 ounces for the full year.
- Consolidated YTD TCC1 of
Full Year 2024 Guidance Revision
- Consolidated 2024 production guidance revised to 230,000-240,000 ounces.
- Nicaragua’s Q4 mine plans deliver significantly higher ore tonnes mined, with production expected to be 60,000-70,000 ounces. Despite increasing ore haulage to Libertad by
30% to 3,000 tonnes per day in Q4, the Company forecasts an approximate 30,000 ounce increase in stockpiles by year end, available for processing in 2025. - Consistent with YTD performance, full year spend is anticipated to be in line with budget, with lower ounces sold resulting in higher TCC1 and AISC1 for 2024:
- Consolidated TCC1 has been revised to
$1,300 -$1,350 /oz; and - Consolidated AISC1 has been revised to
$1,550 -$1,600 /oz.
- Consolidated TCC1 has been revised to
Valentine Construction & Capital Cost Update
- Construction at Valentine surpasses
81% completion as of September 30, 2024:- Tailings Management Facility is complete and ready to receive water;
- CIL leaching area tanks construction is nearing completion;
- Reclaim tunnel and coarse ore stockpile construction is progressing;
- Primary crusher installation is well advanced and overland conveyer construction has commenced; and
- Pre-commissioning is underway.
- Through September 30, 2024 Calibre has incurred costs of C
$547 million . Estimated initial project capital has increased and is now forecast to be approximately C$744 million , resulting in a remaining cost to complete of C$197 million , inclusive of approximately C$20 million in contingency. - With approximately C
$300 million in cash (US$115.8 million ) and restricted cash (US$100 million ) at September 30 Valentine’s initial project capital remains fully funded and the project remains on track to deliver first gold in Q2 2025. - The majority of the increase in capital is attributable to underperformance versus plan from certain contractors which has resulted in additional manpower, temporary camp accommodation, and extended time for certain contractor activities. Approximately
30% of the increase is a result of an underestimation in construction materials and scope of site infrastructure. Calibre had time contingencies, therefore remains confident that first gold will be delivered during Q2, 2025.
Darren Hall, President and Chief Executive Officer of Calibre, stated: “Q3 Production was lower than expected primarily due to higher-than-expected historical artisanal mining activity on the initial benches of the Volcan open pit and mine sequencing at Limon. Ore tonnes and grade from Volcan are now aligning with expectations and the deposit model has been confirmed by infill drilling.
Consolidated Q4 production is expected to be 70,000-80,000 ounces driven by Nicaragua’s Q4 mine plans which indicate significantly higher ore tonnes mined. It’s important to note that after increasing ore haulage to Libertad by
We are guiding to finish 2024 approximately
Construction of the multi-million-ounce Valentine Gold Mine is progressing well, reaching
Updated Full Year 2024 Guidance
CONSOLIDATED | NICARAGUA | NEVADA | |
Gold Production/Sales (ounces) | 230,000 - 240,000 | 200,000 - 210,000 | 34,000 - 36,000 |
Total Cash Costs ($/ounce)1 | |||
AISC ($/ounce)1 | |||
Growth Capital ($ million)* | |||
Exploration Capital ($ million) |
*Initial project capital at the Valentine Gold Mine not included
Original Full Year 2024 Guidance
CONSOLIDATED | NICARAGUA | NEVADA | |
Gold Production/Sales (ounces) | 275,000 – 300,000 | 235,000 - 255,000 | 40,000 - 45,000 |
Total Cash Costs ($/ounce)1 | |||
AISC ($/ounce)1 | |||
Growth Capital ($ million) | |||
Exploration Capital ($ million) |
Valentine Gold Mine Construction Progress
Primary Crusher
Tailings Management Facility
Marathon Pit
Plant Site
SAG and Ball Mill
Q3 2024 Production and Valentine Gold Mine Update Conference Call
Date: | Friday, October 18, 2024 |
Time: | 10:00 am ET |
Webcast link: | https://edge.media-server.com/mmc/p/mtkdxi6o |
Instructions for obtaining conference call dial-in number:
- All parties must register at the link below to participate in Calibre’s Q3 2024 Production and Valentine Gold Mine Update conference call.
- To register click https://dpregister.com/sreg/10193357/fdab0e70e7 and complete the online registration form.
- Once registered you will receive the dial-in numbers and PIN number for input at the time of the call.
The live webcast and registration link can be accessed here and at www.calibremining.com under the Events and Media section under the Investors tab. The live audio webcast will be archived and available for replay for 12 months after the event at www.calibremining.com. Presentation slides that will accompany the conference call will be made available in the Investors section of the Calibre website under Presentations prior to the conference call.
The Company’s unrestricted cash position at September 30, 2024 was
Qualified Person
The scientific and technical information contained in this news release was approved by David Schonfeldt P.GEO, Calibre Mining’s Corporate Chief Geologist and a "Qualified Person" under National Instrument 43-101.
About Calibre
Calibre (TSX: CXB) is a Canadian-listed, Americas focused, growing mid-tier gold producer with a strong pipeline of development and exploration opportunities across Newfoundland & Labrador in Canada, Nevada and Washington in the USA, and Nicaragua. Calibre is focused on delivering sustainable value for shareholders, local communities and all stakeholders through responsible operations and a disciplined approach to growth. With a strong balance sheet, a proven management team, strong operating cash flow, accretive development projects and district-scale exploration opportunities Calibre will unlock significant value.
ON BEHALF OF THE BOARD
“Darren Hall”
Darren Hall, President & Chief Executive Officer
For further information, please contact:
Ryan King
SVP Corporate Development & IR
T: 604.628.1012
E: calibre@calibremining.com
W: www.calibremining.com
Calibre’s head office is located at Suite 1560, 200 Burrard St., Vancouver, British Columbia, V6C 3L6.
X / Facebook / LinkedIn / YouTube
The Toronto Stock Exchange has neither reviewed nor accepts responsibility for the adequacy or accuracy of this news release.
Notes
(1) NON-IFRS FINANCIAL MEASURES
The Company believes that investors use certain non-IFRS measures as indicators to assess gold mining companies, specifically TCC per Ounce and AISC per Ounce. In the gold mining industry, these are common performance measures but do not have any standardized meaning. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company’s performance and ability to generate cash flow. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.
TCC per Ounce of Gold: TCC include mine site operating costs such as mining, processing, and local administrative costs (including stock-based compensation related to mine operations), royalties, production taxes, mine standby costs and current inventory write downs, if any. Production costs are exclusive of depreciation and depletion, reclamation, capital, and exploration costs. TCC per gold ounce are net of by-product silver sales and are divided by gold ounces sold to arrive at a per ounce figure.
AISC per Ounce of Gold: A performance measure that reflects all of the expenditures that are required to produce an ounce of gold from current operations. While there is no standardized meaning of the measure across the industry, the Company’s definition is derived from the AISC definition as set out by the World Gold Council in its guidance dated June 27, 2013, and November 16, 2018. The World Gold Council is a non-regulatory, non-profit organization established in 1987 whose members include global senior mining companies. The Company believes that this measure will be useful to external users in assessing operating performance and the ability to generate free cash flow from current operations. The Company defines AISC as the sum of TCC (per above), sustaining capital (capital required to maintain current operations at existing levels), capital lease repayments, corporate general and administrative expenses, exploration expenditures designed to increase resource confidence at producing mines, amortization of asset retirement costs and rehabilitation accretion related to current operations. AISC excludes capital expenditures for significant improvements at existing operations deemed to be expansionary in nature, exploration and evaluation related to resource growth, rehabilitation accretion and amortization not related to current operations, financing costs, debt repayments, and taxes. Total all-in sustaining costs are divided by gold ounces sold to arrive at a per ounce figure.
Cautionary Note Regarding Forward Looking Information
This news release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian securities legislation. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", “assume”, "intend", “strategy”, “goal”, “objective”, “possible”, or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. Forward-looking statements in this news release include, but are not limited to, the Company’s expectations of gold production and production growth; the upside potential of the Valentine Gold Mine; the Valentine Gold Mine achieving first gold production during the second quarter of 2025, higher TCC and AISC for 2024; the Company’s reinvestment into its existing portfolio of properties for further exploration and growth; statements relating to the Company’s priority resource expansion opportunities; and the Company’s metal price and cut-off grade assumptions. Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond Calibre's control. For a listing of risk factors applicable to the Company, please refer to Calibre's annual information form (“AIF”) for the year ended December 31, 2023, and its management discussion and analysis (“MD&A”) for the year ended December 31, 2023, and other disclosure documents of the Company filed on the Company’s SEDAR+ profile at www.sedarplus.ca.
Calibre's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. Calibre does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, undue reliance should not be placed on forward-looking statements.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/e7f90fae-3f43-4420-a7aa-2fcd6d42cab9
https://www.globenewswire.com/NewsRoom/AttachmentNg/0f89174b-b0c8-4ad9-9dac-0942892788a5
https://www.globenewswire.com/NewsRoom/AttachmentNg/ab403424-3e0c-4a0a-b533-f5e3c2965723
https://www.globenewswire.com/NewsRoom/AttachmentNg/267caa82-2b3a-41a5-a356-c934fa750963
https://www.globenewswire.com/NewsRoom/AttachmentNg/8d2ceef3-930e-4663-94e6-4f8661d6514e
FAQ
What is Calibre Mining's revised 2024 gold production guidance?
How much gold did Calibre Mining (CXBMF) sell in Q3 2024?
What is the completion percentage of Calibre's Valentine Gold Mine as of September 30, 2024?
What is the revised capital cost estimate for Calibre's Valentine Gold Mine project?