CleanSpark (CLSK) released its October 2024 bitcoin mining update, reporting 655 bitcoin mined, a 32% increase from the previous month. The company completed the acquisition of GRIID Infrastructure, expanding its Tennessee Valley Authority-powered operations. CleanSpark's deployed fleet reached 196,032 units with a month-end operating hashrate of 31.3 EH/s. The company sold 2.78 bitcoin at an average price of $62,470. Construction projects are underway in Wyoming, Mississippi, and Tennessee, with new facilities expected to be operational before 2025.

CleanSpark (CLSK) ha pubblicato il suo aggiornamento di mining di bitcoin per ottobre 2024, riportando 655 bitcoin estratti, con un incremento del 32% rispetto al mese precedente. L'azienda ha completato l'acquisizione di GRIID Infrastructure, ampliando le sue operazioni alimentate dalla Tennessee Valley Authority. La flotta di CleanSpark ha raggiunto 196.032 unità con un tasso di hash operativo a fine mese di 31,3 EH/s. L'azienda ha venduto 2,78 bitcoin a un prezzo medio di $62.470. Sono in corso progetti di costruzione in Wyoming, Mississippi e Tennessee, con nuove strutture che si prevede saranno operativa prima del 2025.

CleanSpark (CLSK) lanzó su actualización de minería de bitcoin de octubre de 2024, reportando 655 bitcoin minados, un aumento del 32% en comparación con el mes anterior. La compañía completó la adquisición de GRIID Infrastructure, expandiendo sus operaciones impulsadas por la Tennessee Valley Authority. La flota desplegada de CleanSpark alcanzó 196,032 unidades con un hashrate operativo de fin de mes de 31.3 EH/s. La empresa vendió 2.78 bitcoin a un precio promedio de $62,470. Se están llevando a cabo proyectos de construcción en Wyoming, Mississippi y Tennessee, con nuevas instalaciones que se espera estén operativas antes de 2025.

CleanSpark (CLSK)는 2024년 10월 비트코인 채굴 업데이트를 발표하며 655 비트코인 채굴을 보고했습니다. 이는 지난 달에 비해 32% 증가한 수치입니다. 이 회사는 GRIID Infrastructure 인수를 완료하여 테네시 밸리 권한에 의해 운영을 확장했습니다. CleanSpark의 배치된 함대는 196,032 유닛에 도달했으며, 월말 운영 해시레이트는 31.3 EH/s입니다. 이 회사는 평균 가격 $62,470에 2.78 비트코인을 판매했습니다. 와이오밍, 미시시피 및 테네시에서 건설 프로젝트가 진행 중이며, 새로운 시설은 2025년 이전에 운영될 것으로 예상됩니다.

CleanSpark (CLSK) a publié sa mise à jour d'octobre 2024 sur l'extraction de Bitcoin, rapportant 655 Bitcoin extraits, soit une augmentation de 32 % par rapport au mois précédent. L'entreprise a finalisé l'acquisition de GRIID Infrastructure, élargissant ses opérations alimentées par la Tennessee Valley Authority. La flotte déployée de CleanSpark a atteint 196 032 unités, avec un hashrate opérationnel à la fin du mois de 31,3 EH/s. L'entreprise a vendu 2,78 Bitcoin à un prix moyen de 62 470 $. Des projets de construction sont en cours dans le Wyoming, le Mississippi et le Tennessee, avec de nouvelles installations devant être opérationnelles avant 2025.

CleanSpark (CLSK) hat sein Bitcoin-Mining-Update für Oktober 2024 veröffentlicht und berichtet von 655 geschürften Bitcoin, was einem Anstieg von 32% im Vergleich zum Vormonat entspricht. Das Unternehmen hat die Übernahme von GRIID Infrastructure abgeschlossen und seine betrieblichen Aktivitäten, die von der Tennessee Valley Authority unterstützt werden, erweitert. Die bereitgestellte Flotte von CleanSpark erreichte 196.032 Einheiten mit einer Betriebshashrate von 31,3 EH/s zum Monatsende. Das Unternehmen verkaufte 2,78 Bitcoin zu einem Durchschnittspreis von $62.470. Bauprojekte sind in Wyoming, Mississippi und Tennessee im Gange, wobei erwartet wird, dass neue Einrichtungen vor 2025 betriebsbereit sind.

Positive
  • 32% increase in monthly bitcoin production to 655 BTC
  • Strategic acquisition of GRIID Infrastructure completed
  • Expansion to 400 MW capacity in Tennessee
  • High bitcoin selling price of $62,470 per BTC
  • Significant hashrate increase to 31.3 EH/s
  • Multiple facility constructions nearing completion
Negative
  • None.

Insights

The October update reveals significant operational momentum with 655 bitcoin mined, marking a 32% increase from September. The company's substantial fleet of 196,032 miners achieving 31.3 EH/s hashrate positions them as a major player in the mining sector. The strategic decision to hold most of their mined bitcoin, selling only 2.78 BTC at $62,470 per coin, suggests confidence in bitcoin's long-term value proposition.

The GRIID acquisition and expansion projects in Tennessee, Wyoming and Mississippi demonstrate an aggressive growth strategy. The planned 400 MW Tennessee capacity and additional 75 MW immersion-cooled facilities in Wyoming could significantly boost mining capabilities. The partnership with TVA provides a stable power source, important for maintaining competitive operating costs. The deployment of latest-generation S21 miners across facilities indicates a commitment to maintaining technological edge in the competitive mining landscape.

The diversification of mining operations across multiple states with different power sources represents a sophisticated power strategy. The TVA partnership through the GRIID acquisition is particularly noteworthy, as it provides access to reliable, regulated power rates. The implementation of immersion cooling technology in Wyoming demonstrates forward-thinking efficiency optimization, potentially reducing operational costs and extending equipment lifespan.

The strategic geographical distribution across Tennessee, Wyoming and Mississippi creates a robust operational redundancy while potentially capitalizing on regional power price advantages. The 85 MW Knoxville operation and planned expansions indicate a well-structured scaling approach that balances growth with infrastructure reliability.

Mines 655 bitcoin, a 32% increase from the prior month

Completes acquisition of GRIID Infrastructure Inc.

LAS VEGAS, Nov. 4, 2024 /PRNewswire/ -- CleanSpark Inc. (Nasdaq: CLSK), America's Bitcoin Miner® (the "Company"), today released its unaudited bitcoin mining and operations update for the month ending October 31, 2024.

"October was another remarkable operational month in the books for CleanSpark. We also finalized the acquisition of GRIID Infrastructure Inc., adding more talented people to our team and a pipeline powered by the Tennessee Valley Authority (TVA) that we expect will take us to more than 400 MW in the state. There are just a few short months remaining in the calendar year, but we have a handful of projects under construction that we expect to come online and hashing before the start of 2025," said CleanSpark CEO Zach Bradford.

October Bitcoin Mining Update (unaudited)

  • Bitcoin mined in October: 655
  • CY2024 bitcoin mined: 5,734
  • Total bitcoin holdings as of October 31: 8,7011
  • Total bitcoin sold in October: 2.78
  • Deployed fleet: 196,032
  • Average fleet efficiency: 20.89 J/Th
  • Month-end operating hashrate: 31.3 EH/s

Throughout October 2024, the Company's average hashrate was 29.63 EH/s and average fleet efficiency was 20.89 J/Th, resulting in an average of 21.14 bitcoin mined daily. The single day high reached 22.94 bitcoin. The Company sold 2.78 bitcoin during October 2024 at an average price of approximately $62,470 per bitcoin.

Additional Updates
GRIID Infrastructure Inc. The acquisition of GRIID Infrastructure Inc. was completed on October 30, 2024, following approval of the transaction by stockholders of GRIID at the special meeting of its stockholders on October 28, 2024. The Company plans to grow to at least 400 MW in Tennessee in the coming years.

Knoxville, Tennessee. In early October, separate from the GRIID acquisition, the Company completed the purchase of its two remaining bitcoin mining facilities in the Knoxville area, part of the seven previously announced, bringing an additional 20 MW online. All seven sites are now operational with a combined 85 MW of active power capacity and house S21 pro miners, contributing approximately 5 EH/s to CleanSpark's hashrate.  

Cheyenne, Wyoming: The construction of two immersion-cooled bitcoin mining data centers totaling 75 MW is underway. The company expects significant progress of electrical installation for both sites by the end of November 2024. Each site will house the latest generation S21 immersion XPs, adding an estimated 5 EH/s in total to CleanSpark's hashrate once installed and energized.

Clinton, Mississippi. The construction of two bitcoin mining sites near Clinton is nearly complete, and they will be delivered to CleanSpark fully turnkey by mid-November, with operations expected to begin in early December 2024. Upon completion and installation, the sites will house S21 pro miners with an expected combined operating hashrate of approximately 1 EH/s.

About CleanSpark 
CleanSpark (Nasdaq: CLSK) is America's Bitcoin Miner®. We own and operate multiple data centers that primarily run on low-carbon power. Our infrastructure responsibly supports Bitcoin, the world's most important digital commodity and an essential tool for financial independence and inclusion. We cultivate trust and transparency among our employees and the communities we operate in. Visit our website at www.cleanspark.com.

Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. In this press release, forward-looking statements include, but may not be limited to, statements regarding the Company's expectations, beliefs, plans, intentions, and strategies. In some cases, you can identify forward-looking statements by terms such as "may," "will," "should," "expects," "plans," "anticipates," "could," "intends," "targets," "projects," "contemplates," "believes," "estimates," "forecasts," "predicts," "potential" or "continue" or the negative of these terms or other similar expressions. The forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other important factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements, including, but not limited to: the build-out and energization of the Clinton, Mississippi sites; power availability, mining activities, and target goals in Tennessee; the timing of and completion of construction and energization of the Wyoming data centers; anticipated additions and targets to CleanSpark's hashrate and the timing thereof; the risk that the electrical power available to our facilities does not increase as expected; the success of its digital currency mining activities; the volatile and unpredictable cycles in the emerging and evolving industries in which we operate; increasing difficulty rates for bitcoin mining; bitcoin halving; new or additional governmental regulation; the anticipated delivery dates of new miners; the ability to successfully deploy new miners; the dependency on utility rate structures and government incentive programs; dependency on third-party power providers for expansion efforts; the expectations of future revenue growth may not be realized; and other risks described in the Company's prior press releases and in its filings with the Securities and Exchange Commission (SEC), including under the heading "Risk Factors" in the Company's Annual Report on Form 10-K for the fiscal year ended September 30, 2023, and any subsequent filings with the SEC. Forward-looking statements contained herein are made only as to the date of this press release, and we assume no obligation to update or revise any forward-looking statements as a result of any new information, changed circumstances or future events or otherwise, except as required by applicable law.

Investor Relations Contact 
Brittany Moore
702-989-7693
ir@cleanspark.com 

Media Contact
Eleni Stylianou
702-989-7694
pr@cleanspark.com 


1 As of October 31, 2024, CleanSpark's Bitcoin holdings were 8,701 in total (1,108 bitcoin of this amount was posted as collateral)

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/cleanspark-releases-october-2024-bitcoin-mining-update-302295035.html

SOURCE CleanSpark, Inc.

FAQ

How many bitcoins did CleanSpark (CLSK) mine in October 2024?

CleanSpark mined 655 bitcoins in October 2024, averaging 21.14 bitcoin daily with a single-day high of 22.94 bitcoin.

What was CleanSpark's (CLSK) operating hashrate in October 2024?

CleanSpark's month-end operating hashrate was 31.3 EH/s, with an average hashrate of 29.63 EH/s throughout October 2024.

How many bitcoins did CleanSpark (CLSK) sell in October 2024?

CleanSpark sold 2.78 bitcoins in October 2024 at an average price of approximately $62,470 per bitcoin.

When did CleanSpark (CLSK) complete the GRIID Infrastructure acquisition?

CleanSpark completed the acquisition of GRIID Infrastructure on October 30, 2024, following stockholder approval on October 28, 2024.

CLEANSPARK INC

NASDAQ:CLSK

CLSK Rankings

CLSK Latest News

CLSK Stock Data

3.04B
284.60M
3%
43.59%
19.36%
Capital Markets
Finance Services
Link
United States of America
HENDERSON